) Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify
the critical path for the project.
If the slack is zero, then it is a critical path. So far, Activity A, B, G, E, and H are critical path.
Solution:
Answer:
If the slack is zero, then it is a critical path. So far, Activity A, C, F, and H are critical path of 41 weeks.