Vilma is the Event Manager of Channel V's Big V Concert and she is tasked to organize the event and

finish the preparation at the earliest possible time. She was able to determine the sequence of activities
and the time needed to finish each activity. The figures are summarized in the table.

When is she going to finish the project? What is the Critical Path?

Step 1: draw the network

Activity Predecessor/s Time t (days) Description


A - 16 Process permits
B A 22 Organize Team
C B 12 Book Performers
D A 20 Reserve Venue
E C 14 Schedule Rehearsals
F E 18 Meet the Press
G D, E 24 Sell Tickets
Conduct & Evaluate
H F, G 10
the Concert

Step 2: develop the critical path table

1. Do the forward pass with the earliest start (Se) and the earliest finish (Fe) based on time (t)
Se = maximum Fe of predecessor/s or 0 if none
Fe = Se + t

Activity A: Se = 0 Fe = 0 + 16 = 16
Activity B: Se = maximum (16) = 16 Fe = 16 + 22 = 38
Activity C: Se = maximum (38) = 38 Fe = 38 + 12 = 50
Activity D: Se = maximum (16) = 16 Fe = 16 + 20 = 36
Activity E: Se = maximum (50) = 50 Fe = 50 + 14 = 64
Activity F: Se = maximum (64) = 64 Fe = 64 + 18 = 82
Activity G: Se = maximum (36,64) = 64 Fe = 64 + 24 = 88
Activity H: Se = maximum (82,88) = 88 Fe = 88 + 10 = 98
2. Do the backward pass with the latest start (Sl) and the latest finish (Fl) based on time (t)
Fl = maximum Sl of successor/s or maximum Fe if none
Sl = Fl + t

Activity H: Fl 98 Sl = 98 - 10 = 88
Activity G: Fl = minimum (88) = 88 Sl = 88 - 24 = 64
Activity F: Fl = minimum (88) = 88 Sl = 88 - 18 = 70
Activity E: Fl = minimum (64,70) = 64 Sl = 64 - 14 = 50
Activity D: Fl = minimum (64) = 64 Sl = 64 - 20 = 44
Activity C: Fl = minimum (50) = 50 Sl = 50 - 12 = 38
Activity B: Fl = minimum (38) = 38 Sl = 38 - 22 = 16
Activity A: Fl = minimum (44,16) = 16 Sl = 16 - 16 = 0

3. Compute the slack and determine the critical activities:


Slack = Fl — Fe
= critical if 0, not critical if otherwise

Activity A: = 16 - 16 = 0 = critical
Activity B: = 38 - 38 =0 = critical
Activity C: = 50 - 50 = 0 = critical
Activity D: = 64 - 36 = 28 = not critical
Activity E: = 64 - 64 = 0 = critical
Activity F: = 88 - 82 = 6 = not critical
Activity G: = 88 - 88 = 0 = critical
Activity H: = 98 - 98 = 0 = critical

Activit Predecessor/ Time Earliest Earliest Latest Latest Slac Critica


y s (days) Start Finish Start Finish k l Path?
A 16 0 16 0 16 0 YES
B A 22 16 38 16 38 0 YES
C B 12 38 50 38 50 0 YES
D A 20 16 36 44 64 28 NO
E C 14 50 64 50 64 0 YES
F C 18 64 82 70 88 6 NO
G D,E 24 64 88 64 88 0 YES
H F, G 10 88 98 88 98 0 YES
= A+B+C+E+G+H

= 16 + 22 +12 + 14 + 24 + 10

= 98

The earliest time to finish the project is 98 days.

Step 3: draw the critical path

Activity Predecessor/s Time t (days) Description


A - 16 Process permits
B A 22 Organize Team
C B 12 Book Performers
D A 20 Reserve Venue
E C 14 Schedule Rehearsals
F E 18 Meet the Press
G D, E 24 Sell Tickets
Conduct & Evaluate the
H F, G 10
Concert

Thus, the earliest time to finish the


project is 98 days.