Professional Documents
Culture Documents
COMMISSIONING OF TRANSFORMER
After finalization of the erection work the following tests should be conducted :-
(a) Sample of oil taken from the transformer and subjected to e l e c t r i c test
(break down value) of 50KV (RMS) as specified in IS: 335.
(b) Release trapped air through air release plugs and valve fitted for the purpose
on various fittings like radiators, bushing caps, tank cover, Bushing turrets etc.
(c) The float lever of the magnetic oil level indicator (if provided) should be
moved up and down between the end position to check that the mechanism
does not stick at any point. If the indicator has signaling contact they should
be checked at the same time for correct operation. Checking the gauge by
draining oil is a more positive test.
(d) Check whether g a s operated really (if provided) is mounted at angle by placing
a spirit l e v e l on the top of the relay. See that the conservator is filled up to the
filling oil level marked on plain oil gauge side and corresponding to the pointer
reading in MOG side. Check the operation of the alarm and trip contacts of the
relay independently by injecting air through the top cocks using a dry air bottle.
The air should b e released after the tests. Make sure that transformer oil runs
through pert cock of Buchholz relay.
(e) Check alarm and trip contacts of WTIs, Dial type thermometer, magnetic oil
gauge etc. (if provided).
(f) Ensure that off circuit switch handle is locked at the desired tap position
with padlock.
(g) Make sure that all valves except drain, filter and sampling valves are opened
(such as radiator valves, valves on the buchholz relay pipe line if
Provided).
(h) Check the condition of silicagel in the breather to ensure that silicagel in the
breather is active and colour is blue. Also check that the transformer oil is
filled in the silicagel breather upto the level indicated.
(i) Check tightness of external electrical connections to bushings.
(j) Give a physical check on all bushing for any crack or any breakage of
porcelain. Bushing with cracks or any other defects should be immediately
replaced.
(k) Check the neutral earthing if specified.
(l) Make sure that neutrals of HV / LV are effectively
earthed. (m) Tank should be effectively earthed at two
points.
(n) Check that the thermometer pockets on tank cover are filled with oil.
TESLA TRANSFORMERS LTD
(o) If the oil temperature indicator is not working satisfactorily, loosen and remove
the thermometer bulb from the pocket on the cover and place it with a
standard
TESLA TRANSFORMERS LTD
thermometer in a suitable vessel filled with transformer oil. Warm the oil slowly
while string it and take reading of the thermometers if an adjustment of the
transformer thermometer is necessary the same many be done. Also check
signaling contacts and set for the desired temperature.
TEST
The ratio should be checked at all taps and between all the windings. Ratio is usually
checked by applying a single phase 230V (Approx) supply on the high voltage side and
measuring the voltage on the low voltage side at all tap positions. The measured voltage on
LV side shall
conform to declining trend between tap (min) to tap (max) position for all phases.
Polarity and interphone connections are checked while measuring the ratio. This can be
checked by the Avometer method. The primary and secondary windings are connected
together at points indicated in sketch shown below. A low voltage three phase supply is then
applied to the HV terminals. Voltage measurements are then taken between various pairs of
terminals as indicated in the diagram. Readings obtained should be the
vectorial sum of the separate voltages of each winding under consideration.
Insulation Resistance
The insulation resistance between winding and earth should be measured with a good
2500/1000 Volts megger and values should be compared to the test report values. It is
preferable to have a motor operated megger and the readings taken after one minute from
starting. Before measuring the insulation resistance, it should be made sure that the bushings
are cleaned thoroughly with clean cotton cloth. The lead wires of the meaggers should not have
joints. They should also give reading of more than maximum value readable on the megger.
Magnetizing Current
A three phase 415 Volts supply is given to the HV winding of the three phase transformer and
simultaneous current readings of the three phases are taken using low range AC ammeters
of the same accuracy class. Values should be recorded for the future reference.
Alarm Circuits
Tests
a) Buchholz relay – air injection test
Alarm & trip circuits
b) Oil temperature indicator – alarm & trip
circuits c) Magnetic oil level gauge – alarm
circuits
d) Winding temperature indicator – alarm & trip circuits.
Oil Sampling Test
Electric strength (break down voltage) should be 50 kv (RMS) when tested to IS 335-
1992 please see section 3 for other details.
COMMISSIONING
After tests are completed satisfactorily, the transformer may be energized from the incoming side
on no load and operated for one or two hours.
The transformer hum should be observed for any abnormality. After two hours transformer
may be switched off and the gas operated relay checked for gas collection. Sometimes
dissolved air or air bubbles comes out due to energizing which is misunderstood for gas. So in
case of gas collection it should be energized again. Other instruments may also be
checked for any abnormal indications. If everything is found satisfactory, the transformer
may be energized
again and loaded gradually.
The nature of the test conducted and the results of test should be recorded and made
available in the station as a permanent record for future reference.
Tools Required
(a) Screw drivers of appropriate
size. (b) Spanner of appropriate
size.
Transformer Oil
Oil is used as coolant and dielectric in the transformer and keeping it in good condition will
assist in preventing deterioration of the insulation, which is immersed in oil. Transformer oil is
always exposed to the air to some extent therefore in the course of time it may oxidize and form
sludge if the breather is defective, oil may also absorb moisture from air thus reducing dielectric
strength.
Testing
Oil after filtration should meet the requirements as laid down under the clause
specification. However, to know the conditions the following preliminary tests can be carried out.
(a) Crackle test
A rough test can be made by closing one end of a piece of steel tube 2.54 cm dia (1
inch B.S. pipe is suitable), heating the closed end to just under dull red heat and plunging
it into the oil sample with the ear close to the open end. If the oil contains large moisture a
sharp crackle will be heard. Dry oil will only sizzle.