Professional Documents
Culture Documents
Chapter one
1. INTRODUCTION
1.1 General
Water plays a major important role in life existence. That is why we say “water is life”. All living
things on the earth like human beings, animals and plants use water for their survival. For example,
a man can survive without food for month together but without water to quench his thirst; his
survival beyond 40 hours would be a miracle (source, water supply and sanitary installation by
A.C PANCHDHARI)
About 75%of earth is covered by water. But from this high amount only 3% of it is available as
fresh water , which is found in lakes, rivers, springs, ice and ground water etc. Even this little
amount of fresh water is not found evenly distributes in all parts of the earth. In addition, it is
polluted and contaminated by water born diseases like typhoid, cholera, Bacillary, Disunity,
Amoeba and other kinds of bacteria. In addition the density of population in cities and towns is
high. Therefore, the provision of safe, clean, sufficient and potable water and disposal of garbage
and undesirable material has become an important factor to live with. This is the e main
responsibilities of the water Engineers especially Hydraulic Engineers to design, construct, operate
and maintain the water supply and sanitary services.
1.2 Location
Assosa is a regional town of the Benishangul-Gumuz Regional state located 690 km west of Addis
Ababa. About 335km of the road is asphalt road while the remaining 355km is all weather gravel
road. It is situated on a flat plane at an average altitude of 1645m ASL.
1.3 Climate
The average annual rainfall at Assosa is 1172mm. The coefficient of variation of annual rainfall is
17% which indicates modest variability among dry and wet years. The monthly rainfall pattern
shows a uni model rain fall pattern with longer rainy season from May to October with the highest
rainfall occurring in June, July, August and September.
The Inter Tropical Convergence Zone (ITCZ) is the major rain causing mechanism in Ethiopia.
The movement of the ITCZ in the northern direction brings moisture from the South Atlantic
Ocean, which results in the high rainfall in the Assosa area. The position of ITCZ at different
months between March and November determines the amount and distribution of rainfall in
Ethiopia; rainfall increases from north to south, Because Assosa
is located in the southwest of Ethiopia where the ITCZ reaches the area early and leaves late. It
gets rainfall for a longer period that is from May to October.
The monthly average, maximum and minimum temperature of Assosa varies between 19.70c-
25.80c, 24.30c-33.90c and 14.60c-17.80c respectively. The maximum temperature occurs in March
and the minimum in October, November and December.
1.4 Socio- economic characteristics In Assosa, the major economic activities are mainly
related to selling and buying agricultural products and retail trade of consumable goods. Economic
activities related to traditional gold mining is also important in Assosa town.
1.6.2 Sanitation
The sanitary condition of the town is poor, like many similar towns in Ethiopia. Most of the
households surveyed use pit latrines that are in poor condition and domestic solid waste disposal in
any available open field is common. This has been observed by the survey. The socio-economic
survey on the sample house holds use dry pit latrine while
two percent used open fields. As to usage of latrine, 96 percent use private facilities while the
remaining four percent use shared facilities.
1.6.3 Treatment
For the existing water supply system, No proper treatment process is conducted other than
chlorination. Disinfection using calcium hypo chlorite is said to take place at a reservoirs prior to
distributions. During the site visit it was reported that 40gm calcium hypochlorite has been added
to 50m3 of water.
Chapter two
2.0 DESIGN PERIOD AND POPULATION FORCASTING
2.1 Design period
A water supply scheme shall, almost without exception, cater for a requirement which is
continuously increasing with the coming years. Hence a new water supply scheme is normally
made large enough to meet the needs of growing communities for an economically justifiable
number of years in future. Huge and costly construction works like dams, reservoirs, treatment
works and distribution pipelines are required for a complete water supply scheme. These works
can not be replaced easily and conveniently for future expansion. Hence these works should be
designed for sufficient capacity to meet the future demand of the town for an established length of
time. This length of time or the number of years for which the design of the water supply works
has done is known as design period.
The design period should neither be too long that the financial burden is thrown on the future
generation nor should be too small that the whole financial burden is thrown on the present
generation and the design of water work becomes uneconomical. The design period is not only
limited by general economic consideration but also the following factors.
Funds available for the completion of the project if more funds are available
design period may be more, but if small funds are available the design period
shall be less.
As far as possible the design period should be nearly equal to the materials used
in the water supply work.
Rate if interest on the loans taken to complete the project. If rate of
interest is less, it will be good to keep design period more. But if the interest rate
is very high, the design should be small.
For design of water supply schemes for small towns, a design period of 20-25 years is considered
appropriate. For Assosa town water supply project by considering the above factors we adopt a
design period of 20 years. This period is divided in to two phases. The first phase covers the time
up to 2018 and the second up to 2028.
very easy to design the water supply scheme for the particular zones. The future development of
the various stages of the water works is also designed on the basis of the master plan.
n =decade
k=growth rate
Year population
1984 4049
1994 11749
Pn=Po+kn
From the above population data lets estimate
P1994 P1984
K =
n
K=770
Let =11749
=11749+700*14 =22529
Using similar fashion
Let
+ K*n =22529+770*5
Let
- stage 1
let 30229
Let
-stage 2
Summary
, n=10
11749=4049
K=0.112
11749 = 16155
16155 =27468
27468 =51934
51934 =88303
150141 =283876
Summary
11749 =13609
13609 =17300
17300 =22936
22936 =28723
3 =35791 –stage 1
150141 =46326
Summary
Therefore the population of Assosa town for the selected design period of 20 years and by assuming
the commissioning of the project in 2008 is the following
Forecasted population
CHAPTER THREE
3.0 WATER DEMAND
3.1 General
The design and execution of any water supply scheme requires an estimate of the total amount of
water required by community. The total amount of water demand is affected by the expected
development of the city, presence of industries, quality of water and its cost, characteristics of the
population and efficiency of the water work administration. Generally speaking in designing the
water supply scheme for a town or city, it is necessary to determine the total quantity of water
required for various purposes. The demand for various purposes is divided under the following
categories.
domestic water demand
Commercial water demand and industrial water demand.
Loss due to leaking joints.
Open taps on unauthorized tapping of water.
Fire water demand.
The basic human water requirement for different use could vary based on the mode of service to be
used and the closeness to water supply facilities. The following table shows the composition of the
basic human per capital water demand based on needs for different use adopted for the estimation
of water demand for Assosa town.
Table 3.1: Consumption of water for different purposes (lpcd) in 1999
Activity HC YC PF
Drinking 1.6 1.6 1.6
Cooking 6 6 6
Ablution 2.5 2 1
Washing 4.5 3.5 2
Utensils 8.5 8.2 3.4
Laundry 4 2.5 2
House cleaning 15.8 8.5 2
Toilet 6.5 4.5 1
total 49.4 36.8 19
(Source: twelve town Water supply study result)
Estimation of per capital water domestic demand by mode of service for the year
2008, 2018 and 2028:
Change in living standard and improved service coverage are two of the main factors which often
have substantial influence on percentage distribution of population by modes of services. In
estimating projected per capital water demand corresponding to each mode of service, Water
Works Design and Supervision Enterprise (WW DSE) had adopted the following growth rates.
HC = 2%, YC = 2%, PF= 1%,
To calculate the domestic demand by mode services the following formula is derived as follows.
HC1999 is given
For HC2000=HC1999+(HC1999* R)
HC2000=HC1999 (1+R)-------------------------------------------------a
For HC2001 = HC2000+(HC2001*R)------------------------------------b
Substitute equation “a” in to equation “b”
HC2001 = HC1999+ (HC1999*R) + (HC1999 (1+R)*R)
HC2001 = HC1999 (1+R)(1+R)
----------------------------------------------
HC2001 = HC1999 (1+R) 2 c
For HCn = HC1999 (1+R)a
Where n is the year for which domestic demand by mode of service is to be estimated, a is the
number of years between HC1999&HCn and R is growth rate per year.
Sample calculation for year 2018, HC
Activity type; cooking in HC
HC = 6 l/c/d
a = 2018-1999 = 19
n= 2018
HC2018 = HC1999 (1+R) a
HC2018 = 6(1+2%) 19 = 8.74
Table 3.4 domestic demand by mode service for year 2008, 2018, 2028
HC YC PF HC YC PF HC YC PF
drinking 1.6 1.6 1.6 1.6 1.6 1.6 1.6 1.6 1.6
Cooking 7.17 7.17 6.56 8.74 8.74 7.25 10.66 10.6 8.01
Ablution 2.99 2.39 1.09 3.64 2.91 1.21 4.44 3.55 1.33
Washing 5.38 4.18 2.19 6.56 5.10 2.42 7.99 6.22 2.67
utensil
Laundry 10.16 9.8 3.72 12.38 11.95 4.11 15.09 14.56 4.54
House 4.78 2.99 2.19 5.83 3.64 2.42 7.10 4.44 2.67
cleaning
Bath or 18.88 10.16 2.19 23.2 12.38 2.67 28.06 15.09 2.67
shower
Toilet 7.77 5.38 1.09 9.47 6.56 1.21 11.54 7.99 1.33
total 58.73 43.67 20.63 71.42 52.88 22.89 86.48 64.11 24.82
(NB: the above calculation is done by the growth rate of HC=2, YC=2 and PF= 1)
Table 3.5: projection of per capital water demand by mode of service for 2008, 2018, and 2028
Projection of Population distribution by modes of service for year 2008, 2018 and
2028
As shown above in table 3.3 the percentage populations of house connection (HC) and yard
connection (YC) users are increasing, where as the public fountain users are decrease.
Calculation for the percentage of population for years 2008, 2018, 2028, are follows. Mode
service type......................................................house connection(HC)
Percentage of population in 2005…………PHC-2005 =5.9%
Percentage of population in 2015…………PHC-2015 =15.5%
Percentage of population in 2025…………PHC-2025 =25.0%
Percentage growth rate from 2005 to 2015
Where R= percentage growth rate Percentage
growth rate from 2015 to 2025
Sample calculation of the above table for the year 2018 Data:
Total population =35781
Population distribution by mode of service (%)
HC =18.35%
YC = 48.48%
PF = 25.47%
Projected population = population distribution by mode of service * total population
Therefore,
HC = 18.35%* 35781 = 6568
YC = 48.48% * 35781 = 17351
PF = 25.4% * 35781= 9116
. Thus, the over all adjustment of the projected average domestic demand for the town can be
calculated as
D adjusted = D* socio-economic factor * climatic factor
Where: - D adjusted = adjusted average domestic demand D=
The projected average domestic demand
For Assosa town,
D adjusted = D * 1.05* 1.0= 1.05D
The results are tabulated below.
Table 3.11 adjusted domestic water demand
Table 12: water demand for various institutions in Assosa town in 2005, 2015, and 2025
In the table above the demand for various institution of the Assosa town is given in the year 2005,
2015 and 2025. Hence the demand of water in the year 2008, 2018 and 2028 is calculated as
follow.
Sample calculation:
Educational water demand type
Demand in 2005…...................................37.0m3/day
Demand in 2015…....................................174.4m3/day
Demand in 2015…....................................319.40m3/day
Growth rate (R) of demand from 2005 to 2015
Table 13: water demand for various institutions in Assosa town in 2008, 2018, and 2028
The demand for the year 2008, 2018, and 2028 are calculated and summarize as follow Table 14:
commercial water demand of Assosa town in year 2008, 2018and 2028
2018 217.94
2028 428.71
continuous flow of water going to waste. Care full maintenance and universal metering can
minimize this.
Generally, 20%-30% of the daily demand is allocated for water losses. For Assosa town, 25% of
the daily demand is considered as loss.
Table 3.16: summary of total average daily water demand, maximum daily water demand and
peak hourly water demand
180
160
water demand in 140 average daily water (l/s)
120 maximum daily water demand
100 peak hourly water demand (l/s)
80
60
40
20
0
2000
2010 2020 2030
time in year
CHAPTER FOUR
4.0 SOURCE OF WATER
4.1 General
Estimating the water demand of the Assosa town at the design period for water supply scheme is
discussed in the previous chapter. Knowing the water demand of the population at the design
period, the next step is to search water source, which may be able to supply the required quantity
of water. The source of water can be either surface source of water or subsurface source of water
(ground water).
may also be constructed on those perennial rivers, where supplies are considerably reducing during
dry weather periods.
The quantity of water obtained from rivers is generally not reliable, as it contains large amount of
silt, sand, and a lot of suspended matter. Disposal of sewerage in to the river is further liable to
contaminate the water. The river water must therefore be properly analyzed and well treated before
supplying to the public.
So, for Assosa town water supply schemes, the two alternatives are considered.
Alternative 1: Ground water from areas of Selga, Hoha and Gambella located in the Hoha,
Selga and Gambela valley respectively around the town.
Alternative 2: surface water from Selga, Afa and Hoha stream through impoundment dam.The
three rivers or steams called Hoha, Afa and Selga are considered as the main source of the town's
water supply schemes.
1. Afa stream
This stream is located 20km south of the Assosa town. The source of this stream is mainly
precipitation and it is non- perennial river .so, it needs a construction of dam to store water during
the low flow period. At the selected dam site, the stream has a catchments area of 144km2.
2. Selega stream
This stream originates near the Assosa town and drain to the east direction away from the town.
So, it contains highly polluted contaminated water, which also drains from the town. Like the Afa
stream, it is non- perennial. It requires the construction of dame to store water during the low
flow season. The possible dam site selected is 30km from the town and the reservoir area block the
road connecting Assosa town and Dabus village.
3. Hoha river
This river is located about 12km North West of the town and it is the only perennial gauged river
in the basin. It has about 161km2 catchments area at the proposed site of diversion. The river is
gauged at down streams of the bride on the Assosa- kurmuk road.
1. Location- the source of water should be as near to the town as possible. If there are both
surface and ground sources available to the town the selection will be deciding by considering
other factors also.
2.Quantity of water- the source of water should have sufficient quantity of water to meet up
all the demands of city such as domestic, industrial, fire fighting, public etc through out the year.
There should be sufficient extra quantity of water to be required in the future while expansion of
the city is done.
3. Quality of water – the quality of water should be good which can be easily and cheaply
treated. It should not contain disease germs or other pathogenic bacteria which may endanger the
health of the public. Therefore as far as possible the water of the source should be safe and free
from pollution.
4. Cost of water supply scheme- the cost of water supply project should also be taken in to
account while selecting the source of water. The cost of water supply scheme depends on many
factors as system of supply, ground levels of city, distance between source and distribution system
etc. if the water flows under the gravitational force it will be cheap, but if it is to be pumped it will
be costly.
Generally; the selection of the source of water supply is done on the above points and the source
which will give good quality and the quantity at less cost will be selected.
According to the analysis of the given hydrometric data flow of Hoha river, the 95% dependable
minimum flow read from the flow duration curve is (Q 95percentage=88L/S). And the maximum daily
demand at the end of the design period (year 2028) is 85L/S which directly indicates the river flow
is much enough for the proposed water supply project and for down stream users.
Based on the above criteria the source of water selected for the Assosa water supply project is
surface source of water specifically Hoha River.
4.5. Hydrology
4.5.1 General
The primary objectives of hydrological investigations are mainly in connection with the design,
construction and operation of hydraulic structures. The established river flow characteristics are:
mean daily and monthly flow, daily and monthly flow duration curves, firm flows and probable
maximum flood. Hydrology is required in the design stage to determine the maximum, minimum
and mean flow of the river at the proposed location of the structure. Design flood corresponding to
a certain return period is required to design efficiently and economically functioning hydraulic
structures. The maximum flow is used to design the hydraulic structure and the minimum possible
flow is used to determine whether storing the flow or not.
H=µ1≠µ2
Under the hypothesis, Ho pooled variances (sp) SP=
(n 1)2 (n1122 1) 2
n1 n2 2
tcal = x x (
1
sp1 * (2 1n 1n2 )
) 1 2
0.108 0.509 0
= = -1.892
0.618 * ( 1 1 )
1717
On the basis of a two-tailed test at α=0.05 level of significance, we would reject Ho
if tcal were out side the range
-t(1-α/2) to t(1-α/2) for
n1+n2 - 2 = 17 + 17 – 2 = 32 degree of freedom.
t(1-0.05/2) = t (0.975) = 2.03 for degree of freedom =30
Hence, t(0.975) = -2.03 ≤ -1.892 ≤ t(0975) = 2.03,
Hence, tcal, is inside the range
Thus, we cannot reject Ho, at a 0.05 level of significant
n1
F= ; wherever n-1>n-2
n2
The computed F is compared with the tabulated ordinates of the F- distribution for the
significance level of (two tailed test, and (m-1) and (n-m-1) degrees of freedom. If the
2
computed value is less than the tabulated value, then hypothesis (Ho) are estimates of the same
population variance can be accepted. The calculation is as follow.
Table 4.3 the F-test for Hoha River
бn-1 19.25025 бn-2 = 14.69263
S.No year Qmax s.no year Q max
N= 17 N = 17
1 1966 5.51 18 1983 9.188
2 Q =1967 12.845
10.15 19 Q 1984= 14.89335
9.707
3 1968 7.24 20 1986 7.113
4 1969 12.25 21 1987 17.155
5 1970 4.65 22 1988 17.155
6 1971 9.06 23 1989 46.815
7 1972 8.78 24 1990 9.225
8 1973 4.199 25 1991 9.225
9 1974 10.169 26 1992 9.225
10 1975 13.691 27 1993 3.839
11 1976 86.805 28 1994 9.225
12 19777 6.468 29 1995 3.407
13 1978 8.746 30 1996 12.35
14 1979 4.751 31 1997 11.539
15 1980 10.201 32 1998 5.293
16 1981 9.532 33 1999 15.264
17 1982 6.163 34 2000 57.462
n1
F=
n2 = 19.25025 =1.31
14.69263
Degree of freedom =34-17-1=16
The tabulated value of F for 16 and 16 degrees of freedom and a significance level of 2.5% are
found to be 2.9885 (from table). Hence the computed value is less than the tabulated values, then
the hypothesis (Ho) are estimates of the same population variance can be accepted.
3. Test for outlier
A) Maximum flow
Outliers are date points that depart significantly from the trend of the remaining data. The retention
or deletion of this outlier can significantly affect the magnitude of statistical parameters computed
from the data; especially for small samples procedures for trending outliers require judgment
involving both mathematical and hydrological considerations. According to the water resources
council, if the station skew is greater than +0.4 tests for high outliers are considered first; if station
skew is less than -0.4, test for low outlier are considered first. Where the station skew is between
0.4 tests for both high and low outlier should be applied before eliminating any outliers from the
data set.
The following frequency equation can be used to detect high outliers.
Yh= Y +K *бn-1
Where: -Yh=is the high outlier threshold in log units
K=value read from table for sample size
n-1=standard deviation
n-1=
(Yi Y )2
n 1
QH = (10) Yh
A similar equation can be used to detect low outliers
Yl=Y -K * бn-1 , Where Yl=is the low outlier threshold in log units.
QL = (10) YL
Test I
For higher outliers
Y 0.97484
n =34
n-1 = 0.307
For n=34, K=2.616 (from table) Yh
=Y +K* бn-1
=0.97484+2.616*0.307
=1.778952
QH= 60.11078m3/s
In the given data there is discharge of 86.805m3/s which is greater than QH = 60.11078 m3/s
therefore there is high outlier. Therefore 86.805m3/s should be removed from the data and the next
test will be done for 33 years data.
For lower outliers
YL 0.17073
Q 1.48159m3 / s
L
There is no lower outliers because there is no discharge less than QL= 1.561m3/s in the given
data.
100
90
80
70
60
50
40
maximum
30 Series1
20
10
0
-101960
Test II
For higher outlier
Y 0.969
n= 33
n-1 =0.263
For n=33
K=2.604 (from table)
Yh= Y +K * бn-1
=1.652601
QH= 44.937m3/s
In the given data there are discharges of 57.462 and 46.815m 3/s which are greater than
QH=44.937m3/s. Therefore there are high outliers. 57.462m3/s and 46.81 m3/s should be removed
from the data and the next test will be done for 31 years data.
For lower outliers
YL 0.285
Q 1.929m3 / s
L
There is no lower outliers because there is no discharge less than QL= 1.929007m3/s in the given
data.
70
60
50
40
30
20
10
MAXIMUM
Series1
0
1960 1970 1981 1992 2002
YEAR
Test III
For higher outlier
Y 0.921
n= 31
n-1 =0.184
For n=31 K = 2.577 (from table)
There is no lower outliers because there is no discharge less than QL= 2.795m3/s in the given
data.
20
18
16
14
12
10
8
MAXIMUM
6 Series1
4
2
0
1960
B) Minimum flows
The procedures are already mentioned in the above section
Test I
(For high outlier)
Y 1.10494
n-1 =0.617
For n=31 K=2.577 (from table)
0.35
0.3
0.25
0.2
0.15
0.1
0.05
MIN.
0
1960 1970 1980 1990 2000 2010
YEAR
Series1
In the total year method the entire available record is used for plotting the flow duration curve. All
the data’s are tabulated in descending order starting from the wettest month on the entire period
and ending with the driest month of the period for which the flow record is available.
As the total year method incorporates all the flow records, it gives more accurate result than the
calendar year method. Thus it is used to plot the flow duration curve for this project.
By using Weibull formula i.e.
m
P *100
N 1 Where; m =is the order of the discharge
Pp=percentage probability of the flow magnitude being equaled or exceeded N=
number of data points that are used in the listing
0
0.2512.75 25.25 37.75 50.25 62.75 75.25 87.75
percentage of excedence
Selecting higher return period means the corresponding flood magnitude is high. Such a very high
flood may not occur during the lifetime of the structure. On the other hand if a very low discharge
corresponding to lower return period is chosen for the design and if it is exceeded it will result in
the failure of the structure causing more damage than would have been caused by in the absence of
the structure.
The general guidelines for selecting the return period for a given design flood is as shown
below:
Weirs and other small structures Return period of 100 or 50 yrs depending on
the importance of the project.
For diversion structure a 50 or 100 years return period can be adopted depending on the
importance of the structure. For Assosa water supply project a return period of 50 years is
considered.
At a given location in the stream, flood peaks enable one to assign a frequency to a given flood
peak value. In the design of all hydraulic structures, the peak flows that can be expected with an
assigned frequency are of primary importance to adequately proportion the structures to
accommodate its effect.
To estimate the magnitude of a flood peak the following alternative method are available -
Rational Method
- Empirical method
- Unit hydrograph technique and
- Flood frequency studies.
Rational method is applicable to a small site (<50km2) catchments but the Hoha has an
approximate area of 161km2.
Regarding the unit hydro graph method it is normally restricted to moderate size catchments with
areas less than 5000Km2.Though the catchments satisfy the condition for the project, it is not
used due to shortage of available data like rain fall resulting floods and infiltration.
As empirical formulas are used for the estimation of peak flood is mostly regional formula and it is
not applicable for this project.
Flood frequency studies are statistical methods of frequency analysis that can correlate the given
hydrological data in to a best fit. Therefore, considering the desired objective, the available data
and the importance of the project, frequency analysis method is selected for the estimation of peak
flood.
To select and evaluate the parent distribution, L-moment, which is the recent method and that
gives efficient result as compared with the others is used.
Let X (i/n) is the Ith largest observation in a sample of size n (i=1 corresponding to the largest).
Then, for any distribution the second L- moment is a description of scale based on the expected
difference between two randomly selected observations.
L2 0.5 * E[ X 1 X 2 ]
2 2
1
L * E[ X
4 1 3*X2 3*X3 X4 ]
4 4 4 4 4
b E{X [F ( X )]r }
r
When unbiased ness is important one can employ unbiased PWM ESTIMATOR
bo=Qmean = 9.04741935
n1
(n
j 1
j)(xj)
b1 = = 6.64093011
n(n 1)
n2
(n 1)(n j 1)
(xj)
b2= = 4.06610857
j 1
n(n 1)(n 2)
n3
Distribution Z3 Z4
uniform 0 0
exponential 1/3 1/6
Normal 0 0.1226
Gubmel 0.1699 0.1504
Log-normal distribution
Z4 = 0.12282 + 0.77518 Z32 + 0.12279 Z34 - 0.13638 Z36 + 0.11368 Z38
Z4 (0.097565) = 0.13021445
General extreme value distribution
Z4=0.1070+0.1109Z3+0.84838Z32+0.06669Z33+0.00567Z34-
0.04208Z 5+0.03763Z
3
6
3
Z4 (0.097565) = 0.125966
Pearson distribution
Z4 = 0.1224 + 0.30115 Z 2 +3 0.95812 Z 4 - 0.57488Z
3
6
+ 0.19383Z
3
8
3
Z4 (0.0977565) = 0.125354820.34231155
Based on the L-Moment estimator, the value of sample Z4 is close to the value of Z4 of the
Gumble. Therefore, the most fitted probable distribution for this specific water supply project is
Gumble distribution.
The graphical representation of the relationship between L-skew ness (Z 3) and kurtosis (Z4)
and the values of Z3 and Z4 of the diversion site is given below.
Z4 PERSO Z4GEV
1.2 Z4 LOG NORMAL
Z4N0MAL Z4UNIFORM Z4GUMLE Z4EXPENTIAL
1 HOHA RIVER
0.8
0.6
0.4
0.2
0 0.5 1 1.5
This equation has been shown by chow to be the governing equation for almost all the theoretical
frequency distribution functions. According to Gumbel’s theory of extreme events, the probability
occurrence of on event equal to or larger than a value xo is given by
P(XXo) =1-e-lny
b= (1 1.3k 1.1k 2
CHAPTER FIVE
In this case the Hoha diversion weir site is located about 200m u/s of the bridge over the Hoha
River on the Assossa – Kurmuk road. The bed level of this 1460m a.s.l
The river bed is massive basaltic rock foundation.
q = 1.7H 3/2
d
Elevation of T.E.L = River bed level + head over crest weir +Weir height
= 1462.39m a.s.l
= 1462.39- 0.0356
= 1462.3564m a.s.l
Elevation of d/s T.E.L = u/s T.E.L – Afflux
= 1462.354 – 1
= 1461.354m a.s.l
=1461.354m a.s.l
State 1) Head water at the crest level and no water to the d/s side
-overturning moment with no shutter (assuming no shutter is provided) Mo
=γH3/6
-Resisting moment
M r = γ HG/6(b2+ab-a2) , G=2.24KN/m3
Equating overturning and resisting moments
γH3/ 6 =γ HG/6(b2+ab+a2)
H2=G (b2+ab-a2)
1.52 = 2.24(b2+0.65b-0.652)
b2+0.65b- 1.427 =0
Solving quadratic equation, b=0.913m
State -2) The weir is just submerged
- Overturning moment
Mo= hH2/2
Resisting moment
M r = H (G-1)/12*(b2+ab-a2)
layer at the bottom and its total thickness is usually between 50cm to 70cm (irrigation
structure and water power eng ’g).
Thus provide 1m*1m*1m concrete block over 0.5m thick inverted filter and the open joint with
10cm gap are filled with river sand.
- Minimum length of d/s launching apron
= 1.5d2= 1.5*2.5=3.75
Length of d/s protection work =3.75+3.75 =7.5
U/s protection work
Minimum length of u/s concrete blocks = d1 = 1m
Provide 1m*1m*1m thick concrete block.
Minimum length of u/s launching apron at horizontal position = 1.5 * d1= 1.5*1 = 1.5m
Thickness of horizontal launching apron T
T 5 *1
2d 5*t 1.118 1.2m
5 * d1 1* t 2
2
Hence provide launching apron of length 1.5m and thickness of 1.5mand thickness of 1.2m
Actual creep length (L)
L = 2d1+L2+B+Ld+2d2
L = 2*1+2+2.46+6.75+2*2.5
L = 18.21m
Residual head at the toe of the weir wall or at point B
H
h H (2d
1 Lu B)
L
1.5
h 1.5 (2 *1 2 2.46)
18.21
h 0.968m
Thickness of impervious floor (t) using Bligh’s theory
4 1 4
t * h * 0.968
3 G 3 2.24 1
Arba Minch University
Hydraulic Eng ‘g Page 64
Assosa Water Supply Project Final Year Project, June 2008
1.04m
Therefore provide thickness of 1.04m for d/s floor from just near its junction with weir wall.
H
hH * (2d
L
1 Lu B 3)
4
Thus thickness (t) * h 0.72m
3 4
h 0.81
0.77 0.8m
G 2.24
*
1 3 1
Therefore, provide thickness of 0.8m for the next 3m from point c
Residual head at point D, at a distant of 5.5m from the toe of the weir wall
H
h H * (2d
1
L Lu B 5.5m)
h 1.5 1.5
* (2 *1 2 2.41 5.5)
18.21
h 0.51m
4
Thus thickness (t) *
3
h 4
0.64
0.548m
G 2.24
*
1 3 1
Therefore provide thickness of 0.6 for the last 1.25m of d/s impervious floor.
And also provide a nominal thickness of 0.5m below the u/s floor and below the weir wall.
b 11.16
11.16
d1 1
1 (1 2 )
b= 11.17m d1 = 1m 6.1
2
1 1 2 1 1 6.1 2
E1
* cos * cos
6.1
E 1 26.53%
D 8.48%
Correction for C1
Correction due to mutual interference
D * (d D)
Correction = 19 *
b' b
b’=b=11.21
D= 2.5-0.5=2m and d = 1-0.5 = 0.5m
Correction = 19 * D * (d D)
19 3.78%(ve)
b' b * 2* (0.5 2)
11.2111.21
Thickness correction
D1 C1 81.52 73.47
d1m *t * 0.5 4.025%(ve)
1
Correction due to slope at C1 is nil, as C1 is neither situated at the start nor at the end of the slope.
Therefore corrected C1 73.47 4.025 3.78 81.275%
B. d/s pile
b=11.21m d2= 2.5m
b
d 11.21 4.484
2
2.5
1
(1 2 )
2.79
2
1 1 2 1 1 2.79 2
E 2 * cos * cos
2.79
1
E * 73.39 40.77%
2 * 180
1 1 1 1 1 2.789 1
D2 * cos * cos
2.789
1
D * 50.09 27.83%
2 * 180
C 2 0%
Correction for E 2
b=b’=11.21
D=1-0.6=0.4 &
d=2.5-0.6=1.9
Correction = 19 * D * (d D)
19 * 0.4 * (1.9 0.4) 1.62%(ve)
b' b 11.2111.21
Thickness correction
E2 D2 40.77 27.83
2.5m
*t * 0.5 2.588%(ve)
d
2
h 1.2965
Thickness of floor at B, t 1.04..................................................ok!
G 1 2.24
1
Percentage pressure at pt, C
C 1 E 2
E * Bc'
B 2
b
81.27 36.57
36.57 * 3.75 51.52%
B
11.21
Thus residual head at C = 2*51.52% = 1.03m
1
h 1.03
Thickness of floor at B, t
G 1 2.24
Arba Minch University
Hydraulic Eng ‘g Page 71
Assosa Water Supply Project Final Year Project, June 2008
0.83 >0.8..................................................
There fore take t =0.83m from the 2.5m of the d/s impervious floor.
Percentage pressure at D
C1 E2
E * Cc'
C 2
b
81.27 36.57
36.57 * 21.25 41.55%
C
11.21
Thus residual head at D = 2*41.55% = 0.83m
h 0.83
Thickness of floor at B, t 0.63 0.6..................ok !
G 1 2.24 1
Therefore take t=0.63m from the last 1.25m of d/s impervious floor.
%age presser at D
E 2
ØD=Ø+ c1 * DD /
b
81.27 36.57
=36.57+ ( ) *1.25 =41.55%
11.21
Therefore; Residual head at D=2*41.55%
=0.83m
Therefore; Thickness of floor at D
h
t= = 0.83
G1 =0.63.......................Ok
2.24
1
t=0.63m>0.6m
Therefore take t =0.63m from the 1.25 of downstream impervious floor.
5.5 Water profile at weir site
5.5.1 Water profile u/s of the weir
Water profile u/s of the river
Effect of back water curve on structure
To suggested weather river training works are required or not
To find out whether the water surface is high enough to deliver the required
discharge to the off take canals
Water profile d/s of the weir
Required, to
Carry out the stability analysis of the weir.
Design the weir structurally
Design the d/s ring wall and protector
Hydraulic jump
To check weather the hydraulic jump is occurs or not, if the d/c between u/s and d/s energy
grade line is very high, there fore the energy must be dissipation be fore it reaches the natural river
course, other wise it causes damage to the banks and d/s of the apron.
Hydraulic jump is used to dissipate energy which is caused to increase by (He)
= 0.891m
Applying Bernoulli equation between section 1-1 and section 2-2 take reference datum river
bed level Zo=Z1
V 12
Zo+P+hd+
2g
Where Zo=Z1 and He= hd+Va2/2g
Va 2 V 12
P+hd+ =Y +
1
2g 2g
V 12 V 12
P+He= Y + =1.5+0.89= Y +
1
1
2g 2g
V 12......................................
2.39= Y + Equation 1
1
2g
V1=q/Y1= 1.43
=6.53m/s
0.219
V1 6.53
Fr1 (Fraud number)= = =4.455
g * y1 9.81* 0.259
(Y 2 (1.274 0.219)3
HL= = =1.032m
Y1) 4 *1.274 *
4Y 1Y 2 0.219
Length of jump
L=5(y2-y1) = 5(1.274-0.219) = 5.275
= 5.275 < 6.75(d/s impervious length)…….ok!
The down stream floor length (Apron length )should be greater than or equal to the length of the
jump to accommodate the hydraulic jump in it.
The Apron length determined for satisfying seepage requirement is enough to
accommodate the jump.Finally, it is calculated that measures such as using chute blocks
and end sill or extending the length of the down stream impervious floor which are used to bound
the jump in the downstream impervious floor are not necessary.
W1=23.4KN
W2=M*A*L=24 KN/m3*1/2*1.81*1.5*1
W2=32.58KN
- Uplift pressure
U=1/2* γw *H*b =1/2*9.81*1.5*2.46 U=
18.099 KN
Data available
Height of retaining wall above the foundation
=H++freeboard
=1.5+0.946+0.5m (assumed)=2.9463m
Top width of retaining wall=0.4m (with vertical water face)
Assuming back slope of 1V:0.5H
Angle of repose =30o
Ranking coefficient of active earth pressure
1 sin 1 sin 30
Ka= = =1/3
1 sin 1 sin 30
2) Weight of soil
W4=A4*s*1=0.5*1.5*3*19*1=42.75 KN , where s = Unit weight of soil
= 19KN/m3
W5=A5*s*1=0.5*3*19*1=28.5 KN
3) Active earth pressure
PA=0.5*Ka*s*H2=0.5*1/3*19*32=28.5KN
4) Water pressure
Pw=0.5*w*H2*1=0.5*9.81*1.52*1=11.036KN
5) Uplift earth pressure
U=0.5*H*w*B*1=0.5*3*9.81*2.46*1=36.199KN
∑M=∑M+-∑M-=227.56-93.378=134.182KN.m , ∑H =17.464KN.m
a) Check the stability against over turning
1. For no water condition
Fso= M 227.56
= 28.5 =7.78>1.5 ….OK! , where ∑M-=excluding hydrostatic and
uplift force
M
CHAPTER SIX
1. The intake site should be such that the water available is of best quality and can be easily
and economically purified.
2. The intake should be located at such a site where sufficient quality of water remains
available under all circumstances.
3. Site should be such that the intake work can provide more quality of water if required in future
for expansion of water works
4. At selected site the velocity the velocity of flow in the source should gentle, otherwise heavy
currents may endanger the safety of the intake towers and stirrup the silt from
the bottom.
5. The site should be easily accessible without any obstruction and should be free from the
effects of loads.
6. It should be near the treatment plant so that conveyance cost from the source to the works
can be minimized.
7. It should not located in navigation channels generally polluted and may also damage the
structure.
8. It should not be on curve in case o meandering river. If there is no alternative, then intake
should be located on the outer bank and not on the inner bank. Water concentrated more
near the outer bank although erosion problem will be
there. Inner bank always keeps on silting and this may bock the intake and put it out of
commission.
9. It should be located on the upstream side of the town. Water will not be contaminated due to
sewerage disposal.
1. Intake wells: this is a circular masonry tower, two to six meters in diameter, provided on
the bank. The water flows in to the intake wells through the penstocks located at
different levels. The penstocks can be closed or opened with valves. These penstocks
face down stream to avoid the entry of silt. This type of intake is adopted for rivers,
which have sufficient flow through out the year.
2. Weir Intake: water is drawn from the through a channel into a sump well. For rivers which are
more or less dry in summer, a weir is built across the river to the required height, to store excess
floodwater during the rainy season. A channel is provided from the river to the intake well
from where water flows by gravity or is pumped.
3. Pipe intake: when a small quantity of water to be drawn the pipe intake ids economical.
The required number of intake pipes is laid across the river bed. The pipes are
supported on masonry blocks at regular intervals. The ends are provided with strainers and
anchoreerd firmly by masonry blocks. The pipes carry water to a jack well.
3. Gates: are used in intake structure to control inflow of water from the raw water source into the
water conveyance system. Gates typically in intake structures are sluice gates.
4. Coarse screen-trash rack: intake ports should be equipped with a coarse screen to prevent
large objects form entering the conveyance systems
5. Fine screen: Fine screens are used to remove smaller objects that nay pumps or other
equipment.
hl= ( w
4/3 * Va
2 *Sin <0.15 ,(maximum head loss)
b ) 2g
where hl = head loss
w = width of bars
b = clear space between the bars Va
= velocity head
= angle wich the bars make with the
horizontal
= dimensional coefficient that is a function of
bars geometry and is equal to 2.42 for rectangular b
Arba Minch University
Hydraulic Eng ‘g Page 84
Assosa Water Supply Project Final Year Project, June 2008
10 *103
4/3 (0.15)2 -4
* *Sin (90) =3.246*10 m
Hl=2.42( 3
) 2 * 9.81
50 *10
=3.246*10-4mthemaximum head
loss=0.15m…...........................ok!
Provide two ports bottom and top of intake tower. The bottom port should be at least
1mabove the bed of the river to prevent rolling bodies to enter in to the ports.
6.2 Construction
The intake structure should be constructed from R.C.C structure to with stand the water pressure
and some impact force due to the rolling stoned and logs. The foundation depth should be below
the normal scour depth the normal scour depth. The steel sluice gates are provided at the
openings or the impacts should have a capacity to resist lateral pressure
6.3 Pump
6.3.1 General
Pump is a mechanical device to increase the pressure energy of a liquid. In most of the case pump
is used for raising fluids from a lower level to a higher level. This is achieved by crating a low
pressure at the inlet or suction end and high pressure at the outer or delivery end of the pump.
Head
In pump system the head refers to both pump systems having one or more pumps and
corresponding piping system. The height to which a pump can raise liquid is the pump head and the
head required to overcome the losers in a pipe system at a given flow rate is the system head. The
head against which the pump must work when water is being pumped is called total dynamic head.
Efficiency
Thee pump should be selected to operate near its peak efficiency point. In typical water supply
applications, pumps operate over a bond of head conditions. Therefore they can not operate at
their peak efforts all the time.
6.3.3 Determination of pipe size from sump well to treatment plant (phase 1)
a) diameter of suction pipe q
= 39.44l/s
Velocity of flow in the pipe may vary from 0.8m/s to 1.8m/s
Take v = 1.8m/s
A = Q/V = (39.44*10-3m3/s)/1.8m/s
= 0.0219m2
D2 4*A 4 * 0.0219
Area= , d= = =0.167m=167mm
4
So provide d=200mm (available in the market)
Check velocity of flow
Q 0.03944
V 1.255m / s
A * 0.2 2
4
V 1.255m / s 1.8m / s........ok!
b. Diameter of delivery pipe
To determine economic diameter of pumping main we use lea formula
D 0.97to1.22Q
Where Q is in m3/s
D-economic diameter of pipe in (m)
Assuming, Q 39.44 *103
D 1.00 0.199m 199mm
1.00
Provide pipe size of D=200 mm (market available)
Check velocity of flow
Q 0.03944
V 1.255m / s
A * 0.2 2
4
V 1.255m / s 1.8m / s........ok!
6.3.3.1 Determination of total lift of the pump
The total head against which the pump should work includes discharge lift and total loss of head due to
friction, entrance, exit etc in suction and rising mains
fLV 2
hf
2gd
Where hf
=head loss in (m)
L=length of pipe in (m)
V=velocity of flow in pipe(m/s)
g=acceleration due to gravity
f=dimensionless friction factor
Cast iron is selected for rising main. Length of pipe from pumping station to treatment plant.
L =0.555Km=555m
f=0.02(for cast iron)
Q 0.03944
V 1.255m / s
A * 0.2 2
kV 2
h1
0.5 * 0.0401m
2g
(1.255)2
2 * 9.81
k=0.5 for circular pipe
H L h f he h1 4.46 0.040 0.040 4.54m
Static head against which the pump lift is
Hs= (elevation of treatment plant –elevation of sump well) +depth of sump well below ground
level)
Hs= (1470-1460) +5=15m
Hence total dynamic head (Hf) =Hs+HL Hf
=15+4.54
=19.54m
Therefore for the first phase two pumps one as stand by each discharging a capacity of 39.44l/s and
head of 19.54m required for the second phase one additional pump with delivery head of 19.45m is
required.
6.3.6 Determination of total lift of the pump from clear water well to service
reservoir (phase I)
Friction loss (hf) =flv2/2gd
Cast iron is selected for the rising of main length of pipe from clear water well to service
reservoir is 5km
L = 13888.88m=13.88Km
F = 0.02 (for cast iron)
V= Q/A= 0.03944/3.214 *0.22/4 =1.255m/s
i) Hf = flv2/2gd = 0.02*13888.88*1.2552/2*9.81*0.2= 111.49m
ii) entry loss(he) = v22(2g)+ 0.04m
iii) loss due to valve and pipe fitting hl = kv2/2g= 0.5*1.2552/2*9.81=0.04m HL
=hf+he+hl = 111.57+0.04+0.04= 40.22m
Static head against which the pump lift
Hs = elevation of service reservoir – elevation of clear water well+4.42m
= 1720 -1470 +4.42
= 254.42m
H is to prevent air entry
Total dynamic head = 254.42 +111.57 = 365.99m
Therefore from treatment to service reservoir two pumps is needed one as stand by each discharging
a capacity of 39.44l/s and the head of 365.99m is required for the second phase one additional pump
is required to deliver the head of 365.99m
6.3.7 Power requirement of pump from clear water well to service reservoir
The water horse power =QWH/75 = 39.44*10-3*1000*365.99/75
= 192.46Hp
The power input to the pump
Pp = WHP/Ep = 192.46/0.8 240.58Hp
Where, Ep = efficiency of pump
Power required for the second phase
The water horse power =QWH/75= 119*10-3*1000*365.99/75
= 580.7Hp
6.3.7.1 Selection of Suitable type of pump Criteria for the selection of type of pump
For proper selection of a pump it is necessary to brave certain essential data on the pump installation
The information should includes
1) Nature of liquid to be pumped
2) Capacity of pump
3) Suction condition
4) Discharge condition
5) Total head
6) Location of geometrical in doors ,outdoors ,elevation….etc
After having the idea of essential data on the pump installation the following points may be kept in
mind while selecting any pumping necessary for the water works.
1) Reliability of service – it should be reliable and should not fail suddenly and cause
trouble
2) Capacity – it should be capable of pumping required quantity of water
3) Cost –it should be cheap in initial cost
4) Power – The which issued for running pump should be available easly at low cost
5) Maintenance – the maintenance cost of running ump be as less as possible
6) Efficiency – pump should have high efficiency
7) Depreciation – pump should have long life and depreciation
8) Promptness – it sho0uld be prompt enough in service
Considering all the above factors, among the available type of pump we select centrifugal pump
out of the other type of pump, because centrifugal pump is used in most water supply system due to
its satisfactory and economical than the other type of pump and fulfils all the above criteria.
Generally from the above consideration for Assosa town water supply projects to lift water from
sump well to treatment plant one working and one stand by multistage centrifugal pump which has
a capacity to lift a head of 19.54m and a discharge of 0.03944m 3/s connected parallels should be
provided and also to lift a water from clear water well to service reservoir .for the second phase
two working and one stand by multistage
centrifugal pump is required which has a capacity to lift 365.99m from sump well to treatment plant
and a discharge of 0.119m3/s and which has a capacity of lift 19.54m from clear water well to
service reservoir and a discharge of 0.119m3/s connected parallel should be required
CHAPTER SEVEN
7.0 WATER QUALITY AND TREATMENT
7.1. Objective of treatment
The objective treatment process is to remove all the undesirable impurities, to the extent where
they do not cause any trouble to human health and water is available to the consumers as per health
standards. Following may be the objects.
To remove color, dissolved gasses, and murkiness of water.
To remove objectionable taste and color.
To kill the troublesome bacteria
To estimate the corrosive properties of water .this treatment is essential from
pipes and pipe fittings safely point of view.
To make safe for drinking and domestic purpose, and also for various industrial
purposes like brewing, dying, stream boilers etc.
7.2. Water quality analysis
The quality of raw water should be compared with the world health organization (WHO) drinking
water quality guide lines and treatment will be done for unacceptable parameters.
In order to remove suspended solids, biological and microbiological impurities, high turbidity due
to iron and floating or other non chemical pollution, color odor and taste an appropriate and sound
treatment must be carried out before supplying the water for the community.
degree of treatment directly depends up on the nature of water or in other words on the source.
Screening –used to exclude floating mater, it is done just at the intake.
Aeration – employed where elements causing taste and odor have to be removed.
Sedimentation and coagulation – in this process suspended impurities like silt, clay,
sand, and some bacteria are removed.
Filtration – employed to remove very fine particles and colloidal matter which may have
escaped from sedimentation process ,micro-organisms are also removed largely.
Other processes – used in specific cases ;
- removing hardiness if it is beyond permissible limits.
- Removing color taste and odor if any.
-Removing iron and manganese if present.
-maintain fluorides between 1to 1.5 p.p.m by adding if in deficiency and
removing if in excess.
7.4 Treatment plant location
Correct location of the plant plays a very important role in its success. A comparative study of
site involves a number of considerations such as
All the processes should be located in such a sequence that water may be flowing
from one process to the other.
Elevations of different processes should be such that no pumping is required and water
keeps on flowing from one plant to the other.
All plants should be located in such a way that minimum area is covered by it
.adequate place for the future extension.
Residual colony should be located by the side of the water works. This facilitates better
working and control on the working of different units.
A well establishment laboratory should be located at the site so that the quality of water
may cheeked, before treatment and after treatment
The two types of flocculators are mechanical flocculator and hydraulic flocculator.
In Mechanical flocculator the velocity gradient is created by mechanical power input. They also
require extensive maintenance and the system is complex.
In hydraulic flocculators hydraulic energy provides the necessary velocity gradient. However, due
to these difficulties with mechanical flocculation techniques, flocculators using hydraulic
energy are appropriate for water treatment plant in developing countries. The most widely used
hydraulic flocculator is the baffled channel flocculator (Schulz and Okun 1984) .it is widely used
in developing countries and performs efficiently over a wide range of flows. Baffled
channels can be classified in to horizontal flow and vertical flow flocculator. Horizontal flow
flocculator with around the end baffles are some times preferred over vertical flow flocculator
with over and under baffles because they are easier to drain &clean
loss of head is 15 to 60 cm
(source SCHULZ & OKUN)
The flocculator will be designed for a maximum day demand of the town and plus
treatment loss of around 5% of the maximum day demand.
The flocculator is divided in to three sections of equal volume, each section having
constant velocity gradient of 55, 40, 25sec-1 respectively.
Maximum day demand=0.055217m3/sec
Qmax = Q+5 %( Q)
= 0.055217+ (5/100)*0.055217m3/sec
=0.058m3/sec
Length of flocculator is taken as 5m
- Viscosity of water (µ) =1.14*10-3Kg/m-sec
-density of water (ρ) = 1000Kg/m3
-roughness coefficient of baffles (f) = 0.3
-detention time for the total section = 18min
Design of the first flocculation basin section
-detention time=6min
-velocity gradient=55sec-1
-water velocity=0.3m/sec
-depth of water=1.8m
-flocculation time=18min
Total volume of flocculation
V=Q*t
V=0.058*20*60=69.6m3
Top width of flocculator,W
W=V/A
= = =7.73m
Width of each section = 7.73/3 = 2.6m
2 *1.14 *103 * 6 * 1 3
60 1.8 * 5 * 55 2
Therefore, n * 74
1000 * (1.14 0.058
0.3)
L 5
Spacing between baffles, s 0.067m
n 74
Since 0.067m is below the minimum range of design criteria, we take the minimum
spacing between baffles as 0.45m
= 0.126m
2 *1.14 *103 * 6 *
21 3
60 1.8 * 5 * 40
n * 32
1000 * (1.14 0.058
0.3)
Spacing between baffles, s,
L 5
s
n 32 0.156m 0.45m
Since 0.156m is below the minimum range of design criteria, we take the minimum
spacing between baffles as 0.45m
Spacing between end of baffles and the walls is = 1.5*spacing between baffles
= 1.5*0.45m
= 0.675m
1.14 *103 * 6 * 60 *
Head loss h =
402
1000 * 9.81
h = 0.0669 (say 0.07m)
Design of third flocculation basin section
Detention time = 5min.
Velocity gradient = 25sec-1
Number of baffles in the third flocculation section
2 *1.14 *103 * 6 * 1 3
60 1.8 * 5 * 25 2
n *
1000 * (1.14 0.058
0.3)
n 23
Since 0.217m is below the minimum range of design criteria, we take the minimum
spacing between baffles as 0.45m
7.6.4 SEDIMENTATION
The sedimentation process in water treatments provides for the settling and removal of flocculated
particles prior to filtration.
The removal efficiency in the sedimentation basin determines the subsequent loadings on the
filters and, accordingly has a marked influence on their capacity, the length on the filters and
quality of the filtered water.
The two major classifications for the design of sedimentation basins are:-
- Horizontal – flow unit
- Up flow unit
The design of such unit include:-
-Shape - Detention time
-Number of basins - Volume of sludge storage
-Dimensions - Method of sludge removal
-Velocity - Inlet and out let arrangements
The horizontal – flow sedimentation basin is preferable and chosen for our treatment due to the
advantage of
It is widely used in the world because of its efficiency and inherent simplicity.
It is with out mechanical sludge removal, so that does not require no important
equipment and labor for cleaning.
Constriction cost is low, permitting over sizing.
Operational and maintenance are simple.
7.6.4.1 Design of horizontal flow sedimentation
For the design purpose, the horizontal flow sedimentation tank may be divided in to four zones.
Inlet zone
Settling zone
Sludge zone and
Outlet zone
The sedimentation tank is designed with the assumption that the flow remains steady and all the
suspended particles are uniformly distributed on the full cross section of the tank at right angles to
the flow for the full length of the settling zone.
The inlets and outlets are designed in such a manner that they cause minimum disturbance to the
flowing water in the tank. The flow is designed to meet the following requirements,
The amount of water flowing out from the tank in 24 hours should at least be equal to the
daily demand.
Velocity of flow should be so adjusted that suspended impurities of coarser nature are
removed.
The design of sedimentation tank is governed by;
-the quantity of water to be treated
-the selected detention period
= (0.058m3/s)/0.25m/s=0.232m2
-Area of each opening with a diameter of 50mm;
= =0.00196m2
-Number of baffle holes required= 0.232/0.00196 = 118
-Head loss=
35m/day=4.05*10-4m/sec= , where
L=4*W Therefore, W=6m and
L=24m
Depth (d) =
T= (2-3hr)------ok!
Check for horizontal flow
v= (4-36m/hr)- - -ok!
Therefore provide a rectangular settling tank with,
Length= 24m
Width= 6m
Depth= 2.9m
The some standard and number of unit should be provided for the phase II.
The formula for acceptable weir length (adopted, from IRE, 1981)
0.2 Q
L Where L = Combined weir length (m)
Hvs
7.6.5 FILTRATION
Filtration is a physical, chemical and biological process for separating suspended impurities from
water by passage through a porous media.
Screening of water removes larger suspended solids from water and sedimentation following
chemical coagulation removes most of the residual suspended matter. However, there will still
remain suspended matter and some fine floc particles. Flirtation of water is
done to remove them and to produce still further positive bacterial content in the water. Filtration
is also done to ensure safe, clear, and attractive water.
Filtration process is the most important part of water purification. It consists of passing water
through a thick layer of sand. During its passage through sand, the following effects take place,
I.Fine suspended and colloidal matter which may be present in water is removed almost
completely.
II. Chemical characteristics of water get reduced.
III.The number of bacteria is considerably reduced.
These phenomena can be explained on the basis of four actions
Mechanical string
Sedimentation
Biological metabolism
Electrolytic changes
Performance of filter unit is predicted in terms of;
- The influent characteristics
- The characteristics of media
- The mode of operation of filter
Classification of filters
Filters may be classified under two heads
1. Pressure filters
2. Gravity filters
I. Slow sand filters and
II. Rapid sand filters
I. Slow sand filters
Consists of an enclose tank, under drainage system, base material or gravel, filter medium of
sand and other ancillary fixtures for the proper functioning of the filter. They installed in a water
tight tank made from stone masonry, brick masonry or cement concrete. The floor and sides are
all coated with water proofing agent. Generally slow sand filters;
Based on the rate of filtration, rapid sand filter is preferable. In most cases, when population
growth is high and the town expands extensively, as for assosa town case, rapid sand filter is
recommended from economical point of view.
Filter Unit.
The size of a filter unit is determined by the required amount of water needed. It consists of two
or more units of sizes depending upon the capacity of the plant.
- Depth of tank ranges between (2.5-3.5m)
- Length to breadth ratio of between (1.25-1.33)
- Surface area of each filter ranges between (10-80m2)
- Rate of filtration is between (4000-5000l/m2/hr)
Based on the above recommendations
- Assume rate of filtration =5000l/m2/hr
- Total quantity of water to be treated = 0.055217m3/hr
=0.1988*106 l/hr
= = 39.76m2 ≈40m2
W= =3.2m
L = 1.3*3.2m = 4.2m
Therefore, provide four numbers of rapid sand filters with the size of each unit 3.2*4.2.one unit is
required for stand by or during repair work of any other units.
The same standard and number of filter units will be provided in the second phase.
Filter media
The choice of filter media is dictated by the durability required, the desired degree of purification
and the length of filter run and ease of backwash sought. Sand is the cheapest filter medium and
has been widely used. The ideal medium should have such a size and be of such a material that it
will provide a satisfactory effluent, retain a maximum quantity of solid, and be readily cleaned
with a minimum of wash water.
The sand used in rapid sand filters should be free from dirt, hard resistance, and preferably of
quartz or quartzite. Conventional rapid sand filter generally uses sand layer of effective size
varying from 0.45mm to 0.55mm having uniformity coefficient (D60/D10)
ranging from 1.2 to 1.7. The sand depth, when used alone ranges from 600mm to 700mm in most
applications.
In standard rapid sand filters the filter medium may be underlain by 400 to 600mm gravel which
serves to support the sand, permit the filtered water to remove freely to ward the under drain and
also allows the wash water to move more or less uniformly upward to the sand. It is placed in 5 or
6 with the finest size on top. It is also specified that it should be hard, rounded, and durable, weight
approximately 1600 Kg/m3, be free from flat, thin or long pieces and contain no loam, sand, clay,
shells or other foreign materials.
Table 7. .A common grading and layer thickness are as follows:-
sand gravel
Grading (mm) Thickness (mm) Grading (mm) Thickness(mm)
40 to 60 120 to 200 2.5 70
20 to 40 80 to 120 7.5 70
10 to 20 80 to 120 15 100
5 to 10 60 to 80 30 100
2.5 to 5 60 to 80 50 160
Total depth = 400 to 600 Total=500mm
= 700 mm + 500 mm
= 1200 mm
= 1.2 m
method of back washing. The under drain contain a central manifold and lateral that are
perforated.
The selected under drain system,
- Collect the filtered water percolating down through the sand and gravel layers
- Durable, reliable, and cost effective
- Ensure uniform flow distribution of the back wash
Design guide line for the design of pipe under drain system (NWS and DB 1988)
1. Ratio of length of lateral to its diameter should not exceed 60.
2. Diameter of perforations is the lateral should be from 6-12mm
3. Spacing of perforations along the lateral may vary from 75mm for the smaller holes to
200mm for the larger.
4. Ratio of total area of perforations in the under drain system to total cross sectional area of
laterals should not exceed 0.5 for the larger holes and should decrease to
0.25 for the smaller.
5. Ratio of total area of perforation in the under drain system to the entire filter area may
be as low as 0.002.
6. Spacing of lateral may be as great as 300mm
7. Rate of washing may be varied from 0.15-0.9/min.
Design based on the guide lines
-Area of each filter = 3.2*4.2 =13.44m2 Total
area of perforation =0.3% of area of filter
=0.003*13.44 = 0.04m2
Total area of lateral= 2*area of perforation
=2*0.04 = 0.08m2
Assume diameter of lateral = 0.05m
Number of lateral =
Spacing of laterals =
= =0.001m2
= = 7. 5 (take 7)
Area of each perforation =
= =1.4286cm2≈1.43cm2
< 60
< 60...............ok!
Total number of perforation = number of perforation per lateral*number of laterals
= 7*40 = 280
Area of perforation =1.43cm2
..................
Total area of perforation = 1.43*280 = 400cm2 = 0.04m2 ok!
This is equal to the designed total area of perforation (0.04m2)
Depth of storage tank for wash water should be between 2.3-3.5m. Taking
d=3m
For a circular tank of depth 3m, the diameter will be; V=A*d
D= = = 6.55m
There fore provide wash water tank of 6.55m diameter and 3m deep with free board of 0.3m.
7.7.2. Wash water supply main
Size of the down water pipe bringing the water to the filters for back washing be 40cm in
diameter. The time taken for washing is 10 min.
=
=1.5m/sec < 3m/sec…........ok!
Therefore, provide a wash water supply main having a diameter of 40cm.
= = 1718.055h.p
Assuming efficiency of the motors and pumps as 80%and 70%, the B.H.P off the pumping sets.
B.H.P =1718.055/(0.8*0.7)
= 3067.955hp
7.8.Filter control system
It is essential to control the rate of filtration, because, a sudden increase in the rate will make water
to pass through the filter bed with out proper treatment or the dissolved gases may get released due
to sudden increase in the negative pressure. On the other hand a sudden reduction in filtration rate
will also release bubbles of gas present in the sand, making a hole through the filter bed.
Therefore, to obtain a constant rate of filtration, a rate controlling device is fitted to the filter.
There are two practical methods of operating filters and these differ primarily in the way that the
driving force is applied across the filter. These methods are referred to as constant rate filtration
and declining rate filtration.
In constant rate filtration, when water is taken out of service for back washing or returned to
service after back washing, the water level gradually rises or lowers in the operating filters until
sufficient head is achieved to handle the flow. Thus, the rate changes are made slowly and
smoothly without the abrupt changes associated with automatic or
manual equipment. The head loss for a particular filter is evidenced by the water level in the filter
box. When the water reaches a desired maximum level, back wash of that filter is required.
Declining rate filtration provides significantly better filter effluent quality than constant rate
filtration. Less available head loss is needed compared with that required for constant rate
operation because the flow rate through the filter decreases toward the end of the filter run. The
head loss in the under drain and effluent piping system, therefore, decrease and becomes available
to sustain the run for a longer period than would be possible under constant rate operation with the
same available head.
The water levels in the filters should be 1.2m above the filter media at the beginning of a filter run
and raise to full available depth of 3.2m before back washing becomes necessary.
7.10. Coagulation
The single most important step in removal of very fine suspended solids from water is proper
coagulation. Once the coagulation step is performed properly, operation of the
plant is comparatively simple. Its main objective is to unit several colloidal particles together to
form bigger sized settle able flocs which may settle down easily.
The principle of coagulation may be explained from the following 2 aspects.
1- Floc formation – when coagulant is added to the water and thoroughly mixed, it
produces a thick insoluble gelatinous precipitate. This precipitate is called floc. The
floc has the property of removing fine and colloidal particles quickly.
2- Electrical charge – the floc ions are found to posses the positive electric charge
while all the colloidal particles have negative charge, therefore flocs attract the
colloidal particles and cause their removal by settlement at the bottom of tank.
The common chemicals generally used for coagulation are;
1. Aluminum sulphate
2. Sodium sulfate
3. Ferrous sulfate
4. Magnesium carbonate
5. Poly electrolyte
The dosage of coagulants which should be added in the water depends on the following factors;
- Kind of coagulants
- Turbidity of water
- Color of water
- PH-value of water
- Temperature of water
- Mixing and flocculation time
7.11. Disinfection
A safe water supply is the prime concern of any water supply project. Safty against disease is of
utmost importance in water supply, especially the water borne, water related, or water based
diseases such as cholera, typhoid, and many others. Even though a certain degree of disease
causing pathogen removal is achived in treatment process such as flocculation and filtration, there
still exist a significant number of pathogens that are not removed by these processes. This
necessitates subsequent treatment to remove pathogens, which are conventionally carried out by
disinfection. Disinfection is generally the final treatment process in water treatment train.
Disinfection is carried out through chemical means.
PH value. The gas is toxic, and irritating to eyes, impairs respiration, and can cause death at high
dosages.
Chlorination can be achieved in two ways: direct solution feed, where chlorine gas is fed directly
into the treated water, or else using hypochlorite salts such as calcium hypochlorite and sodium
hypochlorite. Hypochlorite tablets are used for emergency disinfection in times of disaster, when
normal water treatment is not operating.
Factors affecting efficiency of chlorine are
1. Nature of pathogens to be destroyed
2. Type and concentration of disinfectant
3. Temperature of water
4. Time of contact
5. Physical and chemical properties of water to be treated
6. PH (alkalinity/acidity) of water
CHAPTER EIGHTH
DISTRIBUTION RESERVOIR
8.1 Service reservoir
Distribution reservoir is also called service reservoir. Service reservoirs are used for storing the
treated water with in or near to the demand (distribution) area, distributing the treated water to the
customers. They are also designed to meet the water demand during fire break, pumps failure,
repair, etc and used to balance the hourly fluctuation of water demand.
Distributions reservoirs are classified based on their support, shape, and material of construction.
A) Based on support of ground Distribution
reservoirs are of two general types:
1. Surface reservoirs
These reservoirs have little or no elevation above the ground and which are usually
constructed of earthen, masonry, or a combination of both, or reinforced cement concrete.
They can be circular or rectangular in shape.
2. Elevated reservoirs
These reservoirs built entirely above the ground such as stand pipes and elevated
Tanks. They help to reduce pumping cost by giving head for gravity flow
distribution. They are usually of steel reinforced concrete or wood. Many surface reservoirs
are built on hills and thus comprise elevated storage.
B) Based on geometry
Circular reservoir
Rectangular reservoirs
Generally distribution reservoirs are located near the central portion of the distribution area. It is
always better to construct them on high ground of city or town at such place where it can be
constructed economically and also by considering the elevation of the highest building to be
supplied
The location of the proposed reservoir site selected should be to fully the gravity distribution
system because it reduces the cost of pumping and also to enable a good flow to be maintained
to those top most places
Following are the various accessories, which are commonly provided in the reservoirs
i. Inlet pipe for the entry of water.
ii. Outlet pipe for the withdrawal of water.
iii. Over flow pipe to prevent over flow of water.
iv. Float switch to stop the pump when the tank is full.
v. Float gauge to show the depth of water in the tank.
vi. Washout pipe for washing out the suspended impurities in the tank
vii. Manhole for providing entry into the tank.
viii. Access ladder to inspect the top & bottom of the tank.
ix. Ventilation for fresh air circulation in the tank.
x.Chlorinator incase when the water is directly pumped in the over head reservoir from the
tube wells
Time 1 2 3 4 5 6 7 8 9 10 11 12
Hourly factor 0.3 0.3 0.3 0.3 0.3 0.6 1.1 2 1.8 1.6 1.5 1.4
Time 13 14 15 16 17 18 19 20 21 22 23 24
Hourly factor 1.3 1.3 1.3 1.5 1.6 1.4 1.2 0.9 0.7 0.5 0.4 0.3
When water is supplied for balancing the variable demand against a constant rate of pumping
for 24 hrs
The analysis of storage capacity can be calculated as follows.
Phase I (2008 – 2018)
Total demand of the town =3407.7m3/day
Total demand of the town in liters per day=34077
Hourly demand of the town = 141987.5 liters Pumping
hours=16
Thus the reservoir capacity for phase I from the above table will be
Maximum value of excess supply = 184583.75liters
maximum value of excess demand = 511155liters
capacity of reservoir = 184583.75+511155
=695738.75liters=695.739m3
For fire requirement (10%) = 69.574m3
Miscellaneous losses (3%) = 20.87217m3
Total recommended reservoir capacity = 786.1852m3
Say=800m3 of standard reservoir capacity
Using mass curve method
3.5
cumulative supply and demand in miliun
2.5
2
cumulative supply
comulative demand
1.5
0.5
02468101214161820222
4
-0.5
time in (hrs)
Phase II (2018-2028)
Total demand of the town =7329.309m3/day
Total demand of the town in liters per day=7329309Hourly demand of the town =
305387.875liters
Pumping hours=20
Pumping rate=366465.45liters/hour
Thus the reservoir capacity for phase I from the above table will be
Maximum value of excess supply = 855086.05liters
maximum value of excess demand = 977241.2liters
capacity of reservoir = 855086.05+977241.2=1832327liters
=1832.327m3
For fire requirement (10%) = 183.233m3
Miscellaneous losses (3%) = 54.96982m3
Total recommended reservoir capacity = 2070.53m3
Say=2100m3 of standard reservoir capacity
Provide additional two reservoirs with capacity of 500m3 and 800m3 for second phase
Excess
Time Hourly Hourly Hourly Cumulative Cumulative
supply (liters) demand
(hr) Factor supply(liters) demand(liters) hourly hourly
supply (5) – (6) +ve (liters) – (5)
(1) (2) (3) (4) demand(liters)
value only +ve value
(liters) (6)
(7) only
(5)
(8)
1 0.3 0 91616.363 0 91616.3625 91616.363
2 0.3 0 91616.363 0 183232.725 183232.73
3 0.3 366465.5 91616.363 366465.45 274849.0875 91616.3625
4 0.3 366465.5 91616.363 732930.9 366465.45 366465.45
5 0.3 366465.5 91616.363 1099396.35 458081.8125 641314.538
6 0.6 366465.5 183232.73 1465861.8 641314.5375 824547.263
7 1.1 366465.5 335926.66 1832327.25 977241.2 855086.05
8 2 366465.5 610775.75 2198792.7 1588016.95 610775.75
9 1.8 366465.5 549698.18 2565258.15 2137715.125 427543.025
10 1.6 366465.5 488620.6 2931723.6 2626335.725 305387.875
11 1.5 366465.5 458081.81 3298189.05 3084417.538 213771.513
12 1.4 366465.5 427543.03 3664654.5 3511960.563 152693.938
13 1.4 0 427543.03 3664654.5 3939503.588 274849.09
14 1.3 0 397004.24 3664654.5 4336507.825 671853.32
15 1.3 366465.5 397004.24 4031119.95 4733512.063 702392.11
16 1.5 366465.5 458081.81 4397585.4 5191593.875 794008.47
17 1.6 366465.5 488620.6 4764050.85 5680214.475 916163.62
18 1.4 366465.5 427543.03 5130516.3 6107757.5 977241.2
19 1.2 366465.5 366465.45 5496981.75 6474222.95 977241.2
20 0.9 366465.5 274849.09 5863447.2 6749072.038 885624.84
21 0.7 366465.5 213771.51 6229912.65 6962843.55 732930.9
22 0.5 366465.5 152693.94 6596378.1 7115537.488 519159.39
23 0.4 366465.5 122155.15 6962843.55 7237692.638 274849.09
24 0.3 366465.5 91616.363 7329309 7329309 0 0
6
cumulative supply and demand in 10^6
4
cumulative supply
comuulative demannd
3
0 2 4 6 8 101214161820222 4
-1
time in(hrs)
The different types of reservoirs depending on the geometry (Circular and Rectangular), supports
(resting on the ground, under ground and elevated), and end restraints (free sliding, hinged and
fixed at top and/or base) should be compared and selected based on their suitability and economic
condition during the design of water containing reservoirs.
For small capacities rectangular tanks are usually used. And for bigger capacities circular tanks are
generally used to ensure economical and efficient system of work.
The design of tank should also consider both full and empty conditions, and the assumptions
regarding the arrangement of loading conditions so as to cause the most critical effects. When the
structure is empty it must have strength to withstand the active pressure of any retained earth.
The possible resistance of the earth, never certain to act, is generally ignored when designing for
structure full of water.
Important considerations have to be given in limiting the size of crack (mostly with no cracks) so
that leakage does not take place. The design generally governed by the requirements of the elastic
design method, but stability considerations are particularly important. The design has to take
careful account of the construction methods to be used.
The requirements for the elastic design method are listed as follows.
Concrete grade class as C- 30 with a minimum cement content of 330 kg/m 3 and has maximum
water cement ration = 0.55, but the concert should not be more than the maximum cement
content to keep the shrinkage down.
The maximum cracked width is limited to 0.2mm for all faces of liquid containing or
excluding structures, unless aesthetic appearance is critical, where 0.1mm is required to
avoid staining of concrete.
Minimum cover = 40mm
Maximum bar spacing = 300mm
The allowable tensile stresses in concrete than control cracks in concrete grade of C-30
shall be 1.44 N/mm2 and 2.02 N/mm2 due to direct tension and bending respectively.
The allowable tensile stresses in steel taken as 100 N/mm2 using deformed bars for
alternate wetting and drying exposure conditions.
The maximum steel area in each of the two directions at right angle are 0.3% of the
concrete area (0.15% near each face) for deter med bars.
The operational processes with in the water and other industries dealing with fluids often require
circular structures to ensure their systems of work carried out efficiently and economically.
Hence circular tank is chosen for the design of Assosa town water supply project.
The primary stresses set up with in the structure are usually a result of the ring tension generated
by the contained liquid and the main reinforcement therefore consists of bond of circular steel
hops. The ability of the cylinder to increase in diameter is resisted, however at the base where
restraints occur. If out ward movement is prevented by a fixed joint the ring tension will be zero
and vertical bending movement and sheared force will occur.
Out of three types of base conditions i.e. free sliding, pined and fixed base, fixed base is the most
effective due to the above reasons i.e. the ring tension will be zero and only
vertical bending moment and shear force will occur. Therefore, due to its effectiveness, fixed
base type is selected for the design of the circular reservoir
F W *H
4V 4 * 800
D= = 3.1416 * 4 =16m
*H
Then the corresponding value of moment and hoop tension coefficients is calculated as follows.
4 0.0003 0.0015 0.0028 0.0047 0.0.0066 0.0077 0.0069 0.0023 -0.0080 -0.0268
4.444 0.000212 0.001192 0.002272 0.00390 0.00572 0.003908 0.00646 0.002852 -0.007032 -0.02477
8
5 0.0001 0.0008 0.0016 0.0029 0.0046 0.0059 0.0059 0.0028 -0.0058 -0.022
4 0.067 0.16 0.256 0.339 0.403 0.429 0.409 0.334 0.210 0.073
4
4.444 0.0484 0.15 0.2511 0.3421 0.4171 0.4503 0.409 0.3624 0.2318 0.0814
2
5 0.025 0.13 0.245 0.346 0.428 0.477 0.409 0.398 0.259 0.092
7
Considering alternative exposure of wetting and drying the allowable stress based on BS: 5337
(elastic design method)
For strength design
fs, allow= 100N/mm2 (direct tension)
fc, allow=11N/mm2 (due to bending)
n=15
For no crack design
fct, allow=2.02N/mm2 (due to bending)
fct, allow=1.444N/mm2 (due to direct tension)
8.9.2.4 Detail Reinforcement
a) Vertical section of the tank wall: -It is treated as tension member with cracked section i.e.
only reinforcement resists the maximum hoop tension. The maximum hoop tension occurs at 0.5H
with a coefficient 0.4503.
I. horizontal reinforcement
For the analysis purpose let divided wall into two pars
Case1:
For the top half of the wall, from 0.0H to 0.5H
From the table above the minimum coefficients is 0.4503
Hence the hoop tension can be calculated as
TH = max.coeff * w * H *
where r= D/2=16/2=8m
r
ok
Spacing of 14 ring bars required
b * as 1000 *153.86
s 108.844mm2 Smax=300mmor t=225mm
As 1413.582
Provided:
wall
14 ring bars at 70mm c/c in one layer placed on water face of for upper half
Check thickness of wall for no cracks
Thickness of wall is determined using requirement of resistance to crack; therefore
thickness of wall is determined by limiting tensile stress in the concrete to allowable stress value as
fct
TH 141.3582 *103
0.5775N / mm2 fct ,allow 1.44N / mm2
Ac (n 1) * As 1000 * 225 (15 1)
*1413.582
Therefore, provide 14 ring bars @ 120mm c/c in one layer placed on water face for bottom
half of wall.
b) Horizontal section of the tank wall: -The internal forces in this section are (+ve) and (-
ve) moments with maximum coefficients of 0.006908 and -0.02477 respectively
i. Vertical reinforcement
The maximum positive and the maximum negative moment is calculated as follows
M max max.coeiff * * H 3
w
jkb 1
b
3 0.8136
dreq
M max 6.4040 *106 50.5638mm
Rb * 2.5025 *1000
t=250 d=178
b=100
Taking a unit width of reservoir and 250mm bottom thickness of the centriods of section is
*Y
x i
A i
1000 * 250 *125 15 * 675 *178
1000 * 250 15 * 675 127.063mm
A i
I ce b * x3 b * (D
n * As * (d x)2
3 x)
3
as * b 153.86 *1000
S 228.056mm Smax=300mm or t=225mm
As 675
Therefore provide: 14 bars at 225mm c/c vertically in the inner face.
as * b 153.86 *1000
S 228mm Smax=300m or t=225mm
As 4 * 675
Therefore spacing S= 225mm should be taken. Provide
14 bars at 225mm c/c in the outer face
Where
w fcu=300MPa fy=300MPa
1.5
For S-300MPa maximum design constant for single reinforcement according to ACI
t=thickness of slab=200mm
=0.2*25=5 Kn/m2
Live load (LL) =0.5 KN/m2 (based on EBCS; 1995)
qd= 7.3KN/m2
D=16m
w 2 7.3 * 8.152
M r 0, M x
d
60.611KN M
8 8
Check thickness for flexure
b
0.0028 0.0028
f 0.0035 0.5828
yd 260.87
0.0035
Es 2 *103
1 40.952mm
Treq dreq cov er / 2
=140.952+40+14/2=187.952mm
Treq 187.952mm tassum 225mm
And
d tassum 40 / 2
=(200-40-14/2)mm=153m
Reinforcement
a) At the center of slab
M r M 90.916kn m
fcd M 90.916 *106 0.290
*b*d 13.4 *100 *1532
2
Then
1 1 0.352
(1 2) (1 2 * 0.290)
Spacing using
14 bars
as * b 153.938 *1000
SS 55.646 300mmor400mm
max
As 2766.4mm 2
Therefore, provide 14 bars at 55mmc/c in the form of mesh at the center of slab
M r 60.611KN M
fcd M 60.611*106 0.193
* b * d 13.4 *1000
2 *1532
fctd
0.35 * fctk 0.35 * 30 1.278N / mm2
1.5 1.5
As
b* 1697.563 0.011
d 1000
*153
0.011
/2 0.005
2
vc 0.4 *1.278 * (1 50 * 0.0053) *1000 *153 97.767KN Vmax 29.748kn
Considering exposure condition for base slab continuous liquid contact thus the allowable stress
used for design are
fs,allow=130N/mm2, fc,allow=11N/mm2, and n=15
Design constant of balanced section for flexural member
f s,allow
r f 130 n 15
c,allow kb 0.539
n 15 11.82
11.82
11 r
j kb 1
b
3 0.8136
Shear at the base of wall = direct tension developed in the base slab
H2
Thus, the coefficients of 4.444 from table is 0.12999
D*
t
Therefore direct tension developed in the base of slab is calculated as follow
For simply supported circular slab (with radius =4m) the maximum radial and
circumferential moments are obtained by
3 * q * a 2 3 * 55.34 * 42
Mr M d
166.020KN at the center of the slab
16 16 m
Msupport= (-ve) Mbase,wall=6.4040KN-m …. Restraint moment at the base of
wall
Reinforcement of base of slab
Minimum area of reinforcement for base of slab of unit width (BS: 5337)
0.3 * b * t 0.3 *1000 * 400
Asmim= 1200mm2
100 100
At the center of the slab design for combined action of TR= 20.3855KN and M=166.02KN-
m
Therefore the required reinforcement is determined by
(+ve)As=
M TR 166.02 *106 20.3885 *103
4616.1014mm2
fs* j* 130 * 0.8136 * 352 130
d fs
Spacing of 20 bar
b * as 1000 * 314.16
S 68.057mm Smax=300mm
As 4616.1014
Provided: 20 bars at 65 mm c/c in the form of mesh placed at the bottom of slab At the
support:
Design for combined action of T=20.3885KN and M=-6.4040KN-m Therefore required reinforcement is
determined by
Y
( A *Y ) 400 *1000 * 200 15 *1200 * 352 206.5455mm
A 400 *1000 15 *1200
Moments of inertial and area of equivalent un-cracked concrete section of wall
3
I 5731296970mm4
c
fctb
M *(D Y 6.404 *106 *(400 0.2162N / mm2
)
206.5445)
I ce 5731296970
TR
20.3885
ct
f Ace 0.05097
*103
400 *1000
Then check tensile stress interaction equation for no concrete crack
CHAPTER NINE
Distribution system
9.1 General
After the water has reached to the service reservoir, it becomes necessary to distribute it to a
number of houses, industries and public places by means of network of distribution system. The
distribution systems, the distribution systems consist of pipes of various sizes, valves, meters,
distribution reservoirs, pumps, hydrants etc. the pipe lines carry water to each and every street and
road. Valves control the flow of water through the pipes. Meters are provided to measure the
quantity of water consumed by the individual as well as by the town. Hydrants are provided to
connect the water to the fire fighting equipment during fine accident. Service connection is done to
connect the individual building with the water line passing through the streets. Pumps are provided
to pump the water to the elevated service reservoir or directly in the water mains to obtain the
required pressure in the pipe lines. The layout of the roads and the elevation of the town also
considered to select the layout of the distribution systems respectively the following are the
requirement of a good distribution system
It should convey the reacted water to the consumers with the same degree of purity.
The water should reach to every consumer with the required pressure head.
Sufficient quantity of reacted water should reach for the domestic and industrial use.
The distribution system should be economical and easy to maintain and operate.
It should be able to transport sufficient quantity of water during emergency shuch as
fire fighting.
During repair work, it should not cause obstruction to the traffic.
It should be safe against any future pollution. The pipe lines as much as possible should
not be laind below the sewer lines.
The quality of the pipe should be good and it should not burst.
It should be water-tightt and the water losses dur to leakage should be bare
minimum as much as possible.
For efficient distribution it is required that water should each to every consumers with
required rate of flow. There fore, some pressure in pipe lines is necessary
which should force the water to reach at every place.
If the power fails, the whole supply of town will be stopped. Therefore, it is better to have a
diesel pumps in addition to the electric pumps as standby. During fires, the water dan be
pumped in the required quantity by the stand by units also.
iii) This system has the advantages that during power failure, the balance water
stored in the reservoir will be supplied to the town.
iv) The pumps have to work at constant speed with out any variation in their speed. In
Assosa town the water is distributed to the community by the gravity system because
the service reservoir is located at high elevation of the town. So the water reaches to
every consumer in sufficient quantity.
ii. Grid-iror system: - this system is most convenient for towns having rectangular layout of roads.
Actually, this system is an improvement over dead end system. All the dead ends ae interconnected
with each other and water circulated freely through out the system. In this system mainline is laid
along the main road. Sub-mains are taken in both directions along other minor roads and streets.
From these sub-mains branches are taken out and are interconnected to each other and water
circulates freely through out the system. This system removes all the disadvantages of dead end
system.
ii. If one section is to be repaired more number of valves are required to be closed. iii.The
design is difficult and costlier.
Considering the above advantage and layout of roads of Assosa town this method is adopted.
III circular or ring system:- this system is adopted only in well planned locality of cities. In this
system each locality is divided into square and the water main are laid around all the four sides of
the square. All the sub-mains and branches ae taken off from the boundary mains and are are inter
connected. This system is the best of the other system but it requires many valves and more pipe
length. The ring system is most suitable for towns and cities having well planned road.
iv.Radial system:- actually this is the reverse of ring system and water flows towards outer periphery
from one point. The entire district is divided in to various zones and one reservoir is placed for
each zone which is placed at the center of the zone. The water lines are laid radically from it.
Among different types of pipes, existing on the market PVC pipes are selected for the
distribution system. This is because PVC pipes are light in weight, cheap, easy to
join and install durable, good electric insulators and free from corrosion. Additionally, DCI
pipes are extended from borehole to service reservoir due to its strength and
resistance to corrosion.
If adequate head is not available at the connection to the building, the water will not reach the
upper storey, to overcome this difficulty the required effective head is maintained lithe street pipe
lines.
The water should reach for each and every consumer. Therefore it should reach on the upper most
storeys. The pressure which is required to be maintained in the distribution system depends up on
the following factors:-
The height of the highest building up to which water should reach without boosting.
The distance of the locality form the distribution reservoir
Supply is to be metered or not, higher pressure will be required to compensate for the high
loss of head in meters.
How much pressure will be required for fie hydrants.
The funds available for the project work.
CHAPTER TEN
Environmental Impact and Assessment
10.1 General
When we implement the water supply project, there are impacts that imposed on the environment at
the designing process of the project. We should consider the impacts during construction and
resulted from operation and maintenance of the system. Therefore, we have tried to discuss the
possible positive and negative impacts and their corresponding mitigation process.
The most common adverse impacts on the environment due to water resource development projects
are
Water borne diseases
Land subsidence
Deforestation in the u/s area of the project(storage area)
Sedimentation of reservoir(cause flooding)
Bird mitigation, wild life destruction
Displacement of people
To perform the project development work certain area is required for water storage, service
reservoir construction, transmission pipeline etc. This may affect residential buildings and may
cause property damage. The sound and vibration of machinery service
for construction, loading /unloading purpose; vehicles serve for project work and materials serves
for construction affect the comfort of dwellers of area.
*some Negative impacts due to poor sanitation condition
There is a well established sewerage system. The waste released from each house may normal
living facility of town. The flood during rainy season stored on the road, due to lack of proper
drainage system, damages the road causes traffic problems.