Professional Documents
Culture Documents
Lecture 3b Week 3
Lecture 3b Week 3
CV-457
Contract Management Contract
Management
CV-457
CONTRACT MANAGEMENT
Lecture-3b – (Week-3)
Topics to cover
2
CV-457
Contract
Management
3
CV-457
Contract
Management
4
CV-457
Contract
Management
5
CV-457
Contract
Management
6
CV-457
Contract
Management
7
CV-457
Contract
Management
▪ It gives the contractor the responsibility for both the design and
construction.
▪ The contractor may be a company with the capacity to design and construct
or a joint venture comprising a construction contractor and a design firm.
▪ Alternatively, the contractor may subcontract the design to design
consultants.
8
CV-457
Contract
Management
▪ The principal’s position at the head of the structure makes the principal a de
facto project manager. If required, the principal may engage services of a
specialist consultant (referred to in some conditions of contract as
superintendent) to act as the principal’s agent in much the same manner as
the superintendent’s role defined under the traditional method.
11
CV-457
Contract
Management
▪ This approach may, however, extend the lines of communication and isolate
the principal from the day-to-day affairs of the project.
12
CV-457
Contract
Management
13
CV-457
Contract
Management
14
CV-457
Contract
Management
▪ It may appear that the contractor carries the entire project risk. However,
the contractor’s risk under D&C is probably not as high as under the
traditional method of delivery where the contractor is paid a lump sum.
▪ The risk is further reduced if the contract includes a provision for cost
rise and fall.
15
CV-457
Contract
Management
16
CV-457
Contract
Management
▪ Another risk the principal may face under the D&C contract is related to
prior approval of the contractor’s design drawings, specifications, or
samples.
17
CV-457
Contract
Management
18
CV-457
Contract
Management
19
CV-457
Contract
Management
20
CV-457
Contract
Management
21
CV-457
Contract
Management
22
CV-457
Contract
Management
23
CV-457
Contract
Management
24
CV-457
Contract
Management
25
CV-457
Contract
Management
Advantages
• Single point responsibility for design and construction
• Inherent buildability
• Contractors to come up with different design solutions
• Overall duration is shorter due to design and construction overlap
26
CV-457
Contract
Management
Disadvantages
• Limited control over the design by the client (client's design intent can
be affected)
• Incomplete client brief affects the design
• Changes will be costly and have time implications
27
CV-457
Contract
Management
28
CV-457
Contract
Management
▪ The difference between the general conditions needed for a traditional and
a D&C contract is so slight that there is no real need to have a different set
of conditions.
▪ Design is work. It is work to be described in the specification, not in the
general conditions of contract. It fits into the definition of ‘work’ in all
commonly used forms of contract.
29
CV-457
Contract
Management
30
CV-457
Contract
Management
31
CV-457
Contract
Management
Thank You!
32