Professional Documents
Culture Documents
Lecture 4a - WK 4
Lecture 4a - WK 4
CV-457
Contract Management
Contract Management
CV-457
CONTRACT MANAGEMENT
Lecture-4– (Week-4)
Topics to cover
Non-Traditional Methods of Project Delivery
❖ Managed methods
➢ Construction Management
➢ Project Management (Managing Contracts Approach)
Book reference :
FUNDAMENTALS OF BUILDING CONTRACT MANAGEMENT- Thomas E. Uher & Philip Davenport
2
CV-457
Contract Management
Managed Methods:
Construction Management or PCM
Approach
3
CV-457
Contract Management
▪ The construction team members ideally work together from the inception to the
completion of the project. The project lifecycle stages are treated as integrated
tasks within a construction system.
4
CV-457
Contract Management
▪ Generally, CM methods of project delivery are grouped into ‘Agency CM’ and ‘Non-agency
CM’ depending on the role performed by the construction manager.
5
CV-457
Contract Management
Agency CM Method
6
CV-457
Contract Management
Agency CM Method
▪ In ‘agency construction management’ the construction manager operates as the client’s
agent in managing construction. The construction manager’s main tasks are to manage the
construction stage and coordinate the activities of subcontractors or separate contractors.
The construction manager has no contract to build.
▪ The client selects a design consultant to design a project, and a construction manager to
manage construction. A construction manager can be a contractor or design consultant.
The key requirement in appointing a construction manager is the knowledge and
experience of managing construction.
19.11.
7
2019
CV-457
Contract Management
8
CV-457
Contract Management
9
CV-457
Contract Management
Agency CM Method
The contract between the principal and the Construction
manager
10
CV-457
Contract Management
▪ The principal is willing to accept more risk, including that related to the execution
of separate construction contracts. In doing so, the principal expects that effective
teamwork within the project team will offset the principal’s higher exposure to
risk.
11
CV-457
Contract Management
▪ The first task of the construction manager is to coordinate with the design
consultant in verifying the accuracy of the brief, after which the construction
manager will formulate work packages that the design consultant will design and
document.
12
CV-457
Contract Management
▪ The construction manager will assist the design consultant by providing input on
technical matters and feedback on design buildability and cost.
▪ The construction manager will then administer a tender system through which
separate (trade) contractors will be selected and engaged, usually on lump-sum
contracts.
13
CV-457
Contract Management
14
CV-457
Contract Management
19.11.
15
2019
CV-457
Contract Management
Non-Agency CM Method
16
CV-457
Contract Management
Non-Agency CM Method
17
CV-457
Contract Management
Non-Agency CM Method
▪ The principal wants to retain the benefits of teamwork between himself, the design
consultant, and the construction manager but requires the construction manager to
take full responsibility for construction by entering into direct contracts with
subcontractors.
18
CV-457
Contract Management
Non-Agency CM Method
▪ Instead, subcontracts will be let on a competitive basis with the construction manager
assuming the role of a sole contractor.
19
CV-457
Contract Management
20
CV-457
Contract Management
21
CV-457
Contract Management
Non-Agency CM Method
The contract between the principal and the Construction
manager
22
CV-457
Contract Management
▪ The principal may engage the construction manager either by tender or by negotiation.
▪ The appointment will be made early in the project’s lifecycle.
▪ Using competitive tendering, the construction manager may then progressively select
subcontractors as the design documentation becomes available and will enter into
subcontract agreements. In the construction stage, the main role of the construction
manager will be to construct the facility through the work of subcontractors.
23
CV-457
Contract Management
▪ The construction manager may also be paid the ‘agreed labor rates for the work performed
directly by the construction manager.
▪ The construction manager will be paid for all incurred ‘cost’ items including payments
made to subcontractors and suppliers, and for the cost of preliminary items.
24
CV-457
Contract Management
▪ The principal largely relies on the skill and integrity of the construction
manager to maintain budget integrity.
▪ The construction manager’s contract may also contain liquidated damages for late
completion, bonuses for early completion, or a savings incentive clause.
25
CV-457
Contract Management
Summary
▪ For clarity, important issues shown graphically in various organization charts are briefly
summarized as below:
i. It is worth noting that Non-Agency CM differs from Agency CM only in that separate
contractors are replaced with subcontractors, who are now contracted directly to the
construction manager (represented by a solid line linking the subcontractors to the
construction manager). There is no direct contract between the principal and the
subcontractors (no solid line linking the principal and the subcontractors).
26
CV-457
Contract Management
Summary
ii. Non Agency CM organization structure clearly shows that the principal cannot sue the
subcontractors for breach of contract and that the construction manager is
contractually liable for the work of the subcontractors.
27
CV-457
Contract Management
Summary
28
CV-457
Contract Management
Summary
29
CV-457
Contract Management
Summary
v. This reflects the fact that the design consultant no longer has the traditional role of
managing the construction contract for the principal. The construction contractor
(now called a construction manager) manages as well as constructs. The contractual
relationship between the construction manager and the principal in the non-agency
CM method is exactly the same as under the traditional method of delivery.
19.11.
30
2019
CV-457
Contract Management
Summary
vi. In the traditional method, the design consultant has two functions, too (i) design and
(ii) manage, and the construction contractor has one function, to construct. In Non-
agency CM, the design consultant has only one function, to design, while the
construction manager has two functions, to (i) manage and (ii) construct.
31
CV-457
Contract Management
32
CV-457
Contract Management
Project Management
▪ The project management delivery method is a unique organizational structure with the
project manager as the leader of the team.
▪ In order to successfully deliver the project, the project manager will apply the concept of
project management throughout its lifecycle.
▪ The project management (PM) delivery method is a more refined form of the agency CM
method with the addition of a project manager who assumes total responsibility for
managing the project from inception to completion.
19.11.
33
2019
CV-457
Contract Management
Project Management
▪ The principal appoints and empowers the project manager to represent his interests as
the leader of a project team and to bring a business-like approach into the coordination
and management of a diverse range of skills and organizations in producing a facility.
▪ Since the project manager assumes responsibility for the entire project lifecycle, it
follows that the client will need to appoint the project manager early in the life of the
project, usually at the start of the conceptual stage.
34
CV-457
Contract Management
Project Management
▪ The project team, led by the project manager, comprises the design consultant,
construction manager, and other relevant consultants. The principal is also a member of
the project team but is fully represented by the project manager in day-to-day decision-
making.
▪ Apart from being an effective team leader and motivator, the project manager is
responsible for the development of a strategic plan, organization of the necessary
resources both human and physical, coordination and integration of activities at each
stage of the project’s lifecycle, and control of the entire process.
35
CV-457
Contract Management
36
CV-457
Contract Management
▪ The project manager has no contracts with any other team member.
▪ While the principal empowers the project manager to lead the team and be the main
day-to-day decision-maker, the principal assumes the responsibility for contracts with
the other team members.
37
CV-457
Contract Management
38
CV-457
Contract Management
▪ The project manager is the principal’s agent and is required to act in the principal’s best
interest.
▪ The principal will engage the project manager in the early part of the conceptual stage to
assist in defining the project scope, feasibility, strategic planning, and briefing.
▪ The project manager will make recommendations to the principal on the selection of the
design consultant and the construction manager.
39
CV-457
Contract Management
▪ From the beginning of the design stage, the project manager will work closely with the
design consultant and the construction manager on developing the design, agreeing on
work packages, coordinating and integrating the production of documentation,
arranging for competitive tendering, awarding contracts to separate contractors and
managing construction activities.
40
CV-457
Contract Management
▪ The PM contract, due to its fast-tracking nature, is also cost plus and the principal may
insist on a guaranteed maximum price.
▪ The project manager may be required to pay a separate contractor, but the money would
come from a bank account set up by the project manager with the principal’s funds.
▪ The project manager will be paid a management fee in the form of a lump sum or a
percentage of the final construction cost and will be reimbursed for any out-of-pocket
expenses and approved expenditures.
41
CV-457
Contract Management
▪ Because its success is totally dependent on the project manager’s ability to lead,
manage and motivate the interdisciplinary organizations that form the project team,
the selection of a proficient project manager is one of the most important decisions of
the principal.
42
CV-457
Contract Management
PM Method – Advantages
▪ The PM method provides a more professional approach to the
overall management of the project.
▪ The principal is in total control over the rate of expenditure on the project.
▪ Project management is an ideal approach to handle fast-tracking, for projects that are
complex in nature and where the risks are high.
43
CV-457
Contract Management
PM Method – Disadvantages
19.11.
44
2019
CV-457
Contract Management
• Client’s characteristics:
• Knowledge and experience
• Resources
• Project’s characteristics
• Complexity
• Size
• Location
Quiz :1
Friday, 7 October 2022
Wk-1 to Wk-3
CV-457
Contract Management
Example Problem:
Which project delivery method would you suggest to the client? Justify your answer by evaluating the
merits & demerits of each contractual method.
48
CV-457
Contract Management
Thank You!
49