Detail of Works L (m) B (m) D (m) 1) Earthwork Excavation 1 2 1.5 1.95
2) RCC Work 1:2:4 in Foundation 1 2 1.5 0.45
3) RCC Work 1:2:4 in Column 1 0.4 0.3 4.7
4) Steel reinforcing bars include bending
a, 10 mm dia bars in footing (longer span) no. of Bars=((200-8)/10)+1 20 2.1 Unit weight @ 0.62 2.1*0.62 b, 10 mm dia bars in footing (shorter span) no. of Bars=((150-8)/15)+1 11 1.6 Unit weight @ 0.62 1.6*0.62 c, 20 mm dia bars in column 8 4.9 Unit weight @ 2.47
d, 8 mm dia bars lateral ties
no. of Bars=(4.9/0.15) 33 1.1 Unit weight @0.39
TOTAL
ABSTRACT OF ESTIMATED COST
S.NO Detail of works Quantity Units Rate(Rs.P) Amount(Rs.P)
1) Earthwork Excavation 5.85 m^3
2) RCC Work 1:2:4 in Foundation 1.35 m^3
3) RCC Work 1:2:4 in Column 0.564 m^3
4) Steel reinforcing bars include bending 147.93 kg