You are on page 1of 2

BAR BENDING SCHEDULE FOR COLUMN FOOTING

S.NO Particulars of Item and No. Measurement


Detail of Works L (m) B (m) D (m)
1) Earthwork Excavation 1 2 1.5 1.95

2) RCC Work 1:2:4 in Foundation 1 2 1.5 0.45

3) RCC Work 1:2:4 in Column 1 0.4 0.3 4.7

4) Steel reinforcing bars include bending


a, 10 mm dia bars in footing (longer span)
no. of Bars=((200-8)/10)+1 20 2.1 Unit weight @ 0.62
2.1*0.62
b, 10 mm dia bars in footing (shorter span)
no. of Bars=((150-8)/15)+1 11 1.6 Unit weight @ 0.62
1.6*0.62
c, 20 mm dia bars in column 8 4.9 Unit weight @ 2.47

d, 8 mm dia bars lateral ties


no. of Bars=(4.9/0.15) 33 1.1 Unit weight @0.39

TOTAL

ABSTRACT OF ESTIMATED COST

S.NO Detail of works Quantity Units Rate(Rs.P) Amount(Rs.P)

1) Earthwork Excavation 5.85 m^3

2) RCC Work 1:2:4 in Foundation 1.35 m^3

3) RCC Work 1:2:4 in Column 0.564 m^3

4) Steel reinforcing bars include bending 147.93 kg

5) Contigencies 3 to 5 %

6) Workchareged Establishment 1.5 to 3%


TING

Quantity units Remarks

5.85 m^3

1.35 m^3

0.564 m^3

26.04 kg

10.912 kg

96.824 kg

14.157 kg

147.933 kg

Amount(Rs.P)

You might also like