BALARAJA-SEMANAN TOLL ROAD

INDONESIA INVESTOR REPORT

1
Soekarno – Hatta
International
Airport

To Merak Port

To Bandung

Under Construction/ Planning

TOLL ROAD IN JAKARTA


GREATER AREA
To Bogor 2
SPATIAL PLANNING OF TANGERANG REGENCY
West Greater Jakarta (Jabodetabek) Toll Road Plan

Tol Kartaraja

Tol JORR 2

Tol Balaraja Semanan

Tol Jakarata Tangerang

Tol JORR

Serpong Balaraja
Balaraja – Semanan Toll (e)

Junction Rajeg 08+150 Interchange


Connected to Kartaraja Toll Lebak Wangi 20 +300
Road Connected to Jalan Karet
Interchange Sepatan 16 + 779 Kota Bumi
Connected to Jalan Raya Mauk

Junction Batuceper 27+100


Connected To Kunciran-Bandara
Toll road

- Interchange
Pasar Kemis 4 + 650

To Pasar Kemis and Rajeg


Connected to
Jl Raya Pasar Kemis

End Project 32+166


Connected to Semanan Sunter (6
Section Toll Road DKI)

Interchange Sta
- Interchange Pasar Kemis 4 + 650
- Interchange Susun Sepatan 16 + 779
- Interchange Lebak Wangi 20 +300

Junction Balaraja 00+000


Connected to Serbaraja and
Jakarta Tangerang Merak Toll
Road
Typical Cross Section Mainroad
Typical Cross Section Mainroad
Typical Cross Section of Elevated Mainroad
Typical Cross Section of Elevated Mainroad
ELEVATED TOLL ROAD DESIGN

10
INVESTMENT
I. GENERAL INFORMATION
DESCRIPTION TOTAL SECTION 1 SECTION 2 SECTION 3 SECTION 4
Length Km 32,72 8,15 9,55 3,50 11,52
JB 00+00 JR 08+150 SSSP 17+700 SSLB 21+200
SSPK 04+650 SSSP 17+700 SSLB 21+200 At Grade 25+250
JR 08+150 Elv Btn 30+800
Elv DKI 32+715
Land m2 2.958.877,89 1.132.754,65 1.001.778,70 358.023,88 466.320,66

II. INVESTMENT COST


LAND AND CONSTRUCTION (Rp) Rp.000.000

DESCRIPTION TOTAL SECTION 1 SECTION 2 SECTION 3 SECTION 4

LAND 5.255.417,91 2.039.062,20 918.385,83 464.632,82 1.833.337,06


CONSTRUCTION 10.163.699,16 2.890.068,92 1.572.473,13 838.753,36 4.862.403,75
DED, OH, VAT, IDC 1.638.258,14 487.502,80 246.694,44 131.293,08 772.767,83
IDC 1.324.355,92 602.026,15 155.751,01 82.612,70 483.966,06
TOTAL INVESTMENT 18.381.731,13 6.018.660,07 2.893.304,40 1.517.291,96 7.952.474,70

BIAYA PROYEK 10.115 2021 2022 2023 2024 2025


1. Biaya Proyek -
Tanah 5.255.418 - 1.548.960 2.876.647 829.811 -
Konstruksi, Design, Alat 10.163.699 - - 3.772.253 5.145.985 1.245.461
PPN, OH, FC 1.638.258 - 19.684 640.819 794.451 183.304
IDC 1.324.356 - 34.122 335.290 782.338 172.606
11
TOTAL Biaya Proyek 18.381.731 - 1.602.765 7.625.009 7.552.586 1.601.371
TERIMA KASIH
THANK YOU
DANKE
MERCI GRACIAS
GRAZIE 12