Course Outcomes:
Following are the course outcomes of the subject:
CO Code Course Outcome (CO) Bloom's Level
KCE503. Understand the importance of units of measurement and preliminary estimate for L2-Understanding
1 administrative approval of projects.
KCE503. L2-Understanding
Understand the contracts and tender documents in construction projects.
2
KCE503. Analyze and assess the quantity of materials required for civil engineering works as per
L4-Analyzing
3 specifications.
KCE503. Evaluate and estimate the cost of expenditure and prepare a detailed rate analysis
L6-Evaluating
4 report.
KCE503.
Analyze and choose cost effective approach for civil engineering projects. L4-Analyzing
5
Section: A
Section: B
Section: C
b) Calculate 10 KCE503.3 L4
i) The expected completion time
ii) Variance for the following project &
iii) The Critical Path
Activity A B C D E F G H
Predecessors - - A B A C,D C,D,E F
T0 (In days) 1 1 3 3 1 3 2 4
Tm (In days) 4 5 5 4 3 5 9 4
Tp (In days) 7 9 7 5 9 8 11 4
a) Prepare a detailed estimate of part of a wall of a building from the given plan 10 KCE503.1 L4
and section and general specifications
General Specifications:
(i) Foundation concrete is RCC.
(ii) Foundation and plinth shall be of 1 st class brickwork in lime
mortar.
(iii) Damp Proof Course- 2.5 mm c.c. 1:1.5:3 with water proofing
.compound.
(iv) Superstructure- 1st class brick work in cement mortar.
Consider column is located at ends having size of 230*300 mm 2 and
footing is 2m x 3m.
b) The following information is available about the various activities of networks. 10 KCE503.3 L4
Activit Normal Normal Cost Crash Crash
y duration (INR) Duration Cost
(weeks) (weeks) (INR)
1-2 6 5000 4 9000
2-3 8 10000 5 16000
1-3 12 5000 6 11000
Project overhead cost is 2500/ week, Contrast direct cost vs time relationship.