Dear Sir,
We are pleased to submit our quotation for the above-mentioned subject and
scope of works.
Scope of Works:
I – Mobilization (Lump Sum) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱18,000.00
II – Demobilization (Lump Sum) - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱18,000.00
III – Portion of ground floor slab to be break
11.20 square meter at 1,100.00/m² - - - - - - - - - - - - - - - - - - - - - - ₱22,176.00
IV – Removal of existing firewall
36.80 square meters at 600.00/m² - - - - - - - - - - - - - - - - - - - - - - - ₱39,744.00
V – Excavation of electrical entrance post
And move toward to rodellas lot (L, S) - - - - - - - - - - - - - - - - - - - - ₱10,800.00
VI – Excavation of 3 column footings
4,824 cubic meters at 650.00/m² - - - - - - - - - - - - - - - - - - - - - - - - ₱5,644.08
VII – Reinforcing Bars
1. F-2 3 Sets – 6pcs. 12mmØ - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱2,700.00
2. Columns 3 sets – 13 pcs. 12mmØ - - - - - - - - - - - - - - - - - - - - - - ₱5,850.00
3. Columns Ties – 18 pcs. 10mmØ - - - - - - - - - - - - - - - - - - - - - - - ₱6,480.00
4. Wall Footings – 6 pcs. 10mmØ - - - - - - - - - - - - - - - - - - - - - - - - ₱2,160.00
5. Roof Beam – 6 pcs. 12mmØ - - - - - - - - - - - - - - - - - - - - - - - - - - ₱2,700.00
6. Roof Beam Stirrups – 7 pcs. 10mmØ - - - - - - - - - - - - - - - - - - - - ₱2,520.00
VIII – Formworks
Columns and Roof Beams
1. Columns 3 sets = 13.6145 square meters - - - - - - - - - - - - - - - - - ₱12,253.06
2. Roof Beams = 9.6 square meters - - - - - - - - - - - - - - - - - - - - - - ₱8,640.00
IX – Masonry Works
Concreting
1. Columns 3 sets 0.432 cubic meters footing - - - - - - - - - - - - - ₱5,054.40
2. Columns 3 sets 0.6334 m³ - - - - - - - - - - - - - - - - - - - - - - - - - ₱7,410.78
3. Wall Footing 0.64. m³ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱7,488.00
4. Roof Beams 0.2032 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱2,377.44
5. Floor Slab 0.64m³ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱7,488.00
Tileworks – 4.80 square meters- - - - - - - - - - - - - - - - - - - - - - - - ₱10,368.00
Plastering – 73.60 m² - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱46,368.00
X – Roof Framing (Lump Sum) - - - - - - - - - - - - - - - - - - - - - - - - - - ₱5,400.00
XI – Roof (Lump Sum) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱5,400.00
XII – Electrical Works - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱5,400.00
XIII – Plumbing Works - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱5,400.00
XIV – Carpentry Works - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱9,000.00
XV – Painting Works - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ₱10,800.00
XVI – Hauling of Construction Debris - - - - - - - - - - - - - - - - - - - - - - - ₱18,000.00