You are on page 1of 4

Professional guidance

Temporary Works Toolkit | Part 9 thestructuralengineer.org

Temporary Works Toolkit


Part 9: The role of the The Temporary Works Toolkit is a series
of articles aimed primarily at assisting the
permanent works designer with temporary

principal designer works issues. Buildability – sometimes


referred to now as ‘construction method
engineering’ – is not a new concept and one

with reference to always recognised as vital to the realisation of


one’s ideas; it ought to be at the forefront of an
engineer’s mind.
temporary works www.twforum.org.uk

a principal designer or principal contractor).


John Banks examines the role of principal designer under You become a designer because you are
specifying – it’s as simple as that.
CDM 2015 and discusses how this relates to temporary
The principal designer role only occurs
works design on a project. during the pre-construction phase, which is
any period where design is being undertaken
and on most projects will continue well into
the construction phase. CDM 2015 talks as
if the pre-construction phase stops and the
construction phase begins (as shown in the
top part of Figure 1) but, in practice, most
projects will have design continuing into the
construction phase (as shown in the bottom
part of Fig. 1). For many projects, the pre-
construction phase can last until the end of
the construction phase.

Health and safety risks


Managing health and safety risks is a large
part of the responsibility of being a principal
designer and designer. Since the initial advent
of CDM in 1995, construction site safety in
 Figure 1
Pre-construction phase
and construction phase
the UK has improved vastly; particularly on
the larger projects. The same cannot be said
for health. Slightly fewer than one person
per week dies on a construction site due to
Introduction used and maintained healthily and safely by safety reasons (we call them accidents, but
The second article in this series1 examined contractors who are provided with sufficient the term is ill-advised). Over 100 construction
the impact of the Construction (Design and information on reduced significant residual workers per week die from ill-health caused
Management) Regulations 2015 (CDM 2015) risks to ensure, within reasonable bounds, by their work in construction. Designers need
and temporary works on permanent works that construction workers can go home safe to concentrate on the effect their design has
design in the UK. This article looks in more and as healthy as they arrived for work in the on the health of construction workers while
detail at the role of the principal designer morning. not forgetting safety.
under CDM 2015. The word ‘designers’ means both
The role of principal designer should permanent works designers and temporary Who can be a principal designer?
encompass working with clients and works designers. It refers to all designers. The principal designer must be a designer,
designers, during the pre-construction phase, Almost anybody can be a designer. You appointed in writing by the client as principal
to produce efficient designs that can be built, don’t have to be appointed to the role (unlike designer (an e-mail will do) with control

16 March 2017 | TheStructuralEngineer

17-19_TSE63_Temporary Works.indd 16 16/02/2017 11:13


Professional guidance
thestructuralengineer.org Part 9 | Temporary Works Toolkit

over the health and safety elements of the less than an hour to complete. Client brief
pre-construction phase. One of the design Neither CDM 2015, nor the accompanying You should start with the client brief for the
team, perhaps the lead designer, may be best guidance2, explain how principal designers project. There are informed clients that can
placed to undertake the role, but the principal and designers (permanent and temporary) provide a great brief, but there are many
designer does not have to be a designer determine if the risk management action they clients with little construction knowledge
on the project. Note the sensible flexibility have undertaken is compliant. In the absence who require assistance from the principal
in CDM 2015 to cater for our multifaceted of such advice, it is suggested that the designer.
and amorphous construction industry where principal designer and designers:
projects are unique.  follow contemporary industry practice Resource schedule and fees
where available; if it is available, but not Using the agreed client brief (after necessary
Delivering the role of adopted for good reason, provide an discussion), a resource schedule should be
principal designer explanation for record purposes produced, showing the resources required
The requirements for the role of principal  where no contemporary advice is available, to undertake the role of principal designer
designer are set out in Box 1 and Figure 2. use engineering judgement stemming from against the project programme in order to
All of the principal designer’s duties must capable individuals. determine a fee for the role. Always charge an
be undertaken proportionally for every appropriate fee for the principal designer role.
appointment for every construction project. Necessary documentation
‘Proportionally’ means that all of the duties The best way to discharge the role of Pre-construction information
listed in Box 1 have to be undertaken but, principal designer is via a set of necessary CDM 2015 does do not demand this is
depending on the size and complexity of the and appropriate documents. These are: in writing, but how else will the principal
project, the time take to discharge individual  client brief designer manage this process for most
duties may vary from just minutes to several  resource schedule and associated fee projects? Pre-construction information
days. (charge a reasonable fee for the role of means, initially, information in the client’s
For example, input into a Highways England principal designer) possession (or reasonably obtainable) which
Health and Safety File on several kilometres  pre-construction information is relevant to the project, with an appropriate
of trunk road complete with bridges will take  design ‘significant residual risk’ schedules level of detail and proportionate to the project
months of work; for small projects, the Health  Health and Safety File. risks involved. Pre-construction information
and Safety File may be a single page and take is subsequently and continuously used by
ASSOCIATION FOR PROJECT SAFETY

 Figure 2
Role of principal designer

TheStructuralEngineer | March 2017 17

17-19_TSE63_Temporary Works.indd 17 16/02/2017 11:13


Professional guidance
Temporary Works Toolkit | Part 9 thestructuralengineer.org

designers who, working under the health


and safety control of the principal designer,
will add to and recirculate information to
other designers (this should include both
permanent works and temporary works
designers) and contractors.
The principal designer should:
 ensure that immediate information from
the client is circulated to designers at the
start of the project
 ensure that information gaps are identified
by designers and the principal designer
(continuous process)

ASSOCIATION FOR PROJECT SAFETY


 managing the distribution of further
information as it becomes available
(continuous process)
 distribute information supplied by
designers on health and safety hazards
from the design and construction
process and how they will be addressed
(continuous process)  Figure 3
Proportionality
 distribute information to the principal
contractor to allow incorporation into the
Construction Phase Plan and management risks) provided by designers as the design of say, lack of an appropriate site investigation.
of significant residual health and safety the project progresses should be relevant, As part of the temporary works designer’s
hazards (continuous process). appropriately detailed and proportionate to role, they should add design information
the risks involved (Figure 3). into the pre-construction information which
Design significant residual Permanent works designers produce is shared with the principal contractor to
risk schedules information in conjunction with the principal inform the Construction Phase Plan and
The pre-construction information should designer and should provide appropriate provide information for risk assessments and
continue to be developed by the principal pre-construction information to enable the method statements to allow construction
designer during the pre-construction phase. temporary works designers to undertake work to be undertaken healthily and safely.
All designers need to be identified and their design. Part of a temporary works The temporary works designer may need to
listed to enable appropriate communication. designer’s duty, in conjunction with the supply information to the principal designer/
Supplementary pre-construction information principal designer, is to assess the pre- principal contractor for the project Health
(including appropriate significant residual construction information for gaps, such as, and Safety File.

BOX 1: THE ROLE OF PRINCIPAL DESIGNER

 Plan, manage, monitor and  Identify, eliminate or control, pre-construction information of the construction phase,
coordinate health and safety so far as is reasonably  Provide pre-construction hand the completed Health
matters to ensure that, so far practicable, foreseeable risks information, promptly and in and Safety File to the client
as is reasonably practicable, to the health or safety of any a convenient form, to every ● if the principal designer
the project is carried out person: designer and contractor appointment ceases before
without risks to health or ● carrying out or liable to be appointed, or being the end of the construction
safety affected by construction considered for appointment phase, hand the Health and
 Consider the general work  Liaise with the principal Safety File to the principal
principles of prevention, ● maintaining or cleaning a contractor and share contractor for completion
Construction Phase Plan and/ structure information relevant to  Not accept the principal
or Health and Safety Files ● using a structure designed monitoring and coordination designer appointment unless
when: as a workplace of health and safety matters capable
● design, technical and  Ensure all designers comply during the construction phase  Provide comprehensible
organisational aspects with their duties  Prepare a Health and information or instruction as
for items of work take  Ensure, in relation to the Safety File during the pre- soon as practicable
place simultaneously or in pre-construction phase, all construction phase and  Cooperate with others on the
succession persons cooperate with the review, update and revise as site and adjoining sites
● estimating the period of client, principal designer and necessary, and:  Be satisfied that the client is
time required to complete each other ● if the principal designer aware of their duties under
such work or work stages  Assist the client in provision of appointment is to the end CDM 2015

18 March 2017 | TheStructuralEngineer

17-19_TSE63_Temporary Works.indd 18 16/02/2017 12:12


Professional guidance
thestructuralengineer.org Part 9 | Temporary Works Toolkit

The principal designer should manage the Advice to temporary works designers the Construction Industry Training Board’s
process of identifying residual significant When undertaking temporary works industry guidance3.
health and safety risks across all designers design, find out who the principal designer
by using design risk schedules. The principal is. For most projects there will be more Acknowledgements
designer should ensure that designers than one contractor on site and, therefore, Figures 2–4 in this article are derived from
contribute to the agreed project design risk a principal designer should have been the Principal Designer’s Handbook and
management method (using a consistent pro appointed. Demand sufficient pre- Guide to the CDM 2015 Regulations4, which
forma). Designers must talk, communicate by construction information to enable you to is available in digital and hard copy versions
other means and keep all appropriate parties successfully eliminate, reduce and control from www.aps.org.uk.
in the loop. They must provide information risks emanating from your design. Sufficient
about their design for construction and the pre-construction information may already be John Banks is a Past President and Honorary
Health and Safety File (Figure 4). available as the permanent works designers Fellow of The Association for Project Safety
and principal designer should have and was part of the Handbook editorial team.
Health and Safety File considered the provision of temporary works He is a corresponding member of the ICE
The Health and Safety File should highlight and provided information on significant Health and Safety Expert Panel.
significant health and safety risks for future residual risks. If this information is not
construction work. The principal designer available (for instance, you require further
must prepare the initial Health and Safety site investigation) you have every right to REFERENCES
File and review, update and revise it as the demand this is provided, although you may
project progresses. The principal designer well end up arranging for this provision.
E1) Carpenter J. (2016) ‘Temporary
must pass the completed Health and Safety Work with the principal designer to
Works Toolkit. Part 2: CDM 2015 and
File to the client to keep if their appointment provide information for the principal the responsibilities of permanent works
lasts until the end of the construction phase. contractor on significant residual risks that designers with regard to temporary works’,
If the principal designer’s appointment need to be taken into account when the The Structural Engineer, 94 (11), pp. 34–36
finishes before the end of the project, the temporary works are being constructed,
partially completed Health and Safety File used or dismantled. If necessary, provide E2) Health and Safety Executive (2015)
L153: Managing health and safety in
must be passed to the principal contractor information for the Health and Safety
construction: Construction (Design and
to complete. File on significant residual risks relating Management) Regulations 2015: Guidance
With the role of the principal designer to temporary works necessary for on Regulations [Online] Available at:
ended, i.e. at the end of the pre-construction maintenance/demolition. www.hse.gov.uk/pubns/priced/l153.pdf
phase, the principal contractor has (Accessed: 31 March 2016)
responsibility for reviewing, updating and Recommendations
revising the Health and Safety File and It is strongly recommended that both E3) CITB (2017) Construction (Design and
Management) Regulations 2015: Industry
passing it to the client when the project permanent works and temporary works
Guidance [Online] Available at: www.citb.
finishes. Temporary works designers may designers read the Health and Safety co.uk/health-safety-and-other-topics/
have to provide information for the Health Executive’s document L1532, which contains health-safety/construction-design-and-
and Safety File. the CDM Regulations and guidance, and management-regulations/cdm-guidance-
documents/ (Accessed: 31 March 2016)

E4) Association for Project Safety (2016)


Principal Designer’s Handbook and Guide
to the CDM 2015 Regulations, London:
RIBA Publishing

FURTHER READING

ETemporary Works Forum (2017) Information


Sheet No. 3: The Construction (Design &
Management) Regulations 2015: Principal
Designer: Guidance on Temporary Works
[Online] Available at: www.twforum.org.uk/
ASSOCIATION FOR PROJECT SAFETY

media/89339/twf_information_sheet_no._3_
final_10.1.17.pdf (Accessed: February 2017)

HAVE YOUR SAY

To comment on this article:


 Figure 4
Design risk management process
Eemail Verulam at tse@istructe.org
Etweet @IStructE #TheStructuralEngineer

TheStructuralEngineer | March 2017 19

17-19_TSE63_Temporary Works.indd 19 16/02/2017 11:13

You might also like