Project: OSP Zamboanga City Date: 4/24/2019

Owner: Zamboanga City Government


P.O. No. 106
CLIENT: A-WIN Entreprise and Solutions Inc.

Project Accomplishment Update


1.0 48 Core FOC Cabling Installation Status
a. Command Center to Data Center City Hall ( 200 mtrs. ) DONE
b. Data Center City Hall to Paseo Delmar I.T. Center ( 1,000 mtrs ) DONE
c. DBM Area to Jollibee Tetuan FOC Nodes ( 1,400 mtrs. ) DONE
d. Jollibee Tetuan to KCC Mall FOC Nodes ( 1,000 mtrs. ) DONE
e. KCC Mall to Baliwasan FOC Nodes ( 1,8500 mtrs. ) Ongoing 90%
f. Baliwasan to City Hall Data Center Server FOC Nodes ( 2,600 mtrs. ) Additional Work Required
g. DBM Area to City Hall Data server FOC Nodes ( 600 mtrs. ) DONE

2.0 2 Core FOC Installation/CCTV Installation Status


a. From FOC main back Don Alfaro street to Mayor Jaldon CCTV Camera DONE
b. From FOC back bone Don Alfaro street to Nunez street CCTV Camera DONE
c. From FOC back bone Don Alfaro street to Lapuresima street CCTV Camera DONE
d. From St. Cruz market to Mcore Ongoing
e. From Airport to Baliwasan Staggard Schedule

3.0 Installed CCTV Count


a. PTZ Camera 23 units
b. Fixed Camera 57 units
c. 4k Bullet Type Camera 1 unit
d, 4k Dome Type Camera 1 unit
e ONT Box 20 units
f. Com. Box 20 units
g. UPS 20 units
h. Cyber Power 12V 20 units

Problem Encountered
a. Breakdown of Service Vehicle
b. Untimely Rain Fall affecting scheduled daily activity

Prepared by: Noted by:

Nelson Relatado Raymond Averos