You are on page 1of 28

 

Report on
GEOTECHNICAL STUDY
PROWSE STREET APARTMENTS 
14 PROWSE STREET, WEST PERTH 
 

Submitted to:
A‐Lijn Built Forms
410 Oxford Street 
MOUNT HAWTHORN  WA  6016 
 

 
 
 
 

www.galtgeo.com.au 
2/39 Flynn St, WEMBLEY  WA 6 014 
  T: +61 (8) 6272‐0200 
J1501056 001 R Rev0  F: +61 (8) 9285‐8444  10 April 2015 

  
J1501056 001 R Rev0        
10 April 2015     

TABLE OF CONTENTS 
1.  Introduction ................................................................................................................................................................ 1 

2.  Site Description and Proposed Development ............................................................................................................. 1 

3.  Project Objectives ....................................................................................................................................................... 1 

4.  Fieldwork ..................................................................................................................................................................... 2 

5.  Site Conditions ............................................................................................................................................................ 3 

5.1  Geology ............................................................................................................................................................... 3 

5.2  Sub‐surface Conditions ....................................................................................................................................... 3 

5.3  Groundwater ....................................................................................................................................................... 3 

6.  Geotechnical Assessment ........................................................................................................................................... 3 

6.1  Site Classification................................................................................................................................................. 3 

6.2  Site Subsoil Class ................................................................................................................................................. 3 

6.3  Footings ............................................................................................................................................................... 4 

6.3.1  Shallow Footings ........................................................................................................................................... 4 

6.3.2  Piled Foundations .......................................................................................................................................... 5 

6.4  Earth Retaining Structures .................................................................................................................................. 6 

6.4.1  Retaining Options .......................................................................................................................................... 6 

6.4.2  Retaining Wall Design Parameters ................................................................................................................ 6 

6.5  Site Preparation .................................................................................................................................................. 7 

6.6  Compaction ......................................................................................................................................................... 7 

6.7  Approved Fill ....................................................................................................................................................... 8 

6.8  Stormwater Disposal ........................................................................................................................................... 8 

6.9  Pavement Design ................................................................................................................................................ 9 

7.  Closure ........................................................................................................................................................................ 9 

 
   

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | i  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014 
 
J1501056 001 R Rev0        
10 April 2015     
TABLES  

Table 1: Summary of Tests .................................................................................................................................................. 2 

Table 2: Summary of Permeability Test Results .................................................................................................................. 2 

Table 3: Pad Footing Allowable Bearing Pressures and Estimated Settlements ................................................................. 4 

Table 4: Strip Footing Allowable Bearing Pressures and Estimated Settlements ............................................................... 4 

Table 5: Design Parameters for CFA Piles (ultimate) .......................................................................................................... 5 

FIGURES 

Figure 1: Site and Location Plan 

APPENDICES 

APPENDIX A:  SITE PHOTOGRAPHS 

APPENDIX B:  CONE PENETRATION TEST RESULTS 

APPENDIX C:  PERMEABILITY TEST RESULTS 

APPENDIX D:  UNDERSTANDING YOUR GEOTECHNICAL ENGINEERING REPORT 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | ii  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014 
 
J1501056 001 R Rev0        
10 April 2015     

1. INTRODUCTION 

This report presents the outcomes of Galt Geotechnics Pty Ltd’s (Galt’s) geotechnical study for the proposed Prowse 
Street Apartments at 14 Prowse Street, West Perth (the “site”).  The location of the site relative to the surrounding 
area is shown on Figure 1, Site and Location Plan. 

The investigation was authorised by Chris Hazebroek of A‐Lijn Built Forms in a signed Client Authorisation Form dated 
24 March 2015. 

2. SITE DESCRIPTION AND PROPOSED DEVELOPMENT 

Based on the supplied information, the site is roughly triangular in plan and covers 645 m2.  The provided plan shows 
that the surface elevation ranges from RL 29 m AHD along the northern edge to RL 31 m AHD at the southwest corner.   

The site is bounded by Totterdell Park to the north, a two storey rendered brick building (with undercroft car parking) 
to  the  east,  Prowse  Street  to  the  south  and  by  an  access  road  to  the  west.    Based  on  a  review  of  historical  aerial 
imagery, a single residence has remained on site since prior to 1953.  This has had various additions over the years and 
was  used  as  offices  until  recently.    Localised  trees  are  present  in  the  south  east  corner  and  along  the  northern 
boundary of the site.  No signs of settlement related distress were noted in the exterior of the house. 

Photographs of the site are presented in Appendix A, Site Photographs. 

We  understand  that  the  proposed  development  will  comprise  a  7  level  apartment  building  with  2  basement/sub‐
basement levels.  Based on supplied drawings (02‐08 Rev 3), the lower basement (FFL: RL 25.6 m AHD) will comprise 8 
parking bays, 18 store rooms, 2 water tanks and areas for access via lift, stairs and ramp.  The upper basement (RL 
28.3 m AHD) will comprise 10 parking bays, 9 store rooms, 2 locations for bins and areas for access via lift, stairs and 
ramp.  Above the ground floor (RL 31.0 m AHD), the proposed development comprises 7 levels with 2 to 3 apartments 
per level.   

3. PROJECT OBJECTIVES 

The objectives of the study were to: 

assess subsurface soil and groundwater conditions across the site; 
provide recommendations on suitable footing systems for the proposed development; 
provide allowable bearing pressures and settlement estimates for shallow foundations; 
provide pile design parameters (if required); 
provide a site classification(s) in accordance with AS 2870‐2011 “Residential Slabs and Footings”; 
provide recommendations and geotechnical design parameters for earth retaining structures; 
assess the appropriate site subsoil class for the site in accordance with AS 1170.4‐2007;  
recommend appropriate site preparation procedures including compaction criteria; 
assess the permeability of the soils at the site for potential on‐site disposal of stormwater by infiltration; and 
provide a subgrade California bearing ratio (CBR) value for pavement thickness design by others. 

   

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 1  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     

4. FIELDWORK 

The fieldwork was carried out on 30 March 2015 and comprised: 

clearing the test locations for buried services; 
cone  penetration  testing  (CPTs)  at  2  locations  (CPT01  and  CPT02),  extending  to  a  depth  of  15 m  in  each 
instance; 
installation  of  a  ground  water  monitoring  well  at  one  of  the  CPT  locations  (CPT01)  at  a  depth  of  6  m  (i.e. 
below proposed basement level) for permeability testing; and 
infiltration tests using the ‘inverse auger hole’ technique in the well, at a depth of about 6 m below ground. 

General 

A  geotechnical  engineer  from  Galt  located  the  test  positions,  supervised  the  service  clearance,  observed  the  CPT 
testing and well installation, and performed the permeability testing. 

The test locations are shown on Figure 1, Site and Location Plan and details are summarised in Table 1, Summary of 
Tests.  Photographs of the site are presented in Appendix A, Site Photographs. 

Table 1: Summary of Tests 
Test  Test Depth  Depth to  Reason for 
Stratigraphy1 
Names  (m)  Groundwater (m)  Termination 
CPT01  15.0  D (13.9)2  Target depth  SAND, medium dense becoming dense to 
CPT02  15.0  ‐  Target depth  very dense below 7.0 m 

Notes  1.  Stratigraphy from CPTs is inferred from the Robertson et al (1986) CPT interpretation 


  2.  Dry to recorded depth – hole collapse occurred below this depth following removal of probe 

Cone Penetration Tests 

CPTs  were  undertaken  using  a  22  tonne  truck‐mounted  CPT  rig  supplied  and  operated  by  Probedrill  Pty  Ltd.    The 
results of the CPTs are provided in Appendix B, Cone Penetration Test Results along with a method of interpretation 
proposed by Robertson et al (1986). 

Permeability Test Results 

The permeability testing was undertaken using the inverse auger hole method described by Cocks1.  The results of the 
permeability testing are presented in Appendix C, Permeability Test Results and the results are summarised in Table 2: 
Summary of Permeability Test Results. 

Table 2: Summary of Permeability Test Results 
Minimum Unsaturated Permeability, k (m/day) 
Test No.  Soil Description  Test Depth (m) 
Test 1  Test 2  Test 3 
CPT01  SAND  6.0  12.9  13.7  15.0 
Note:  The  minimum  unsaturated  permeabilities  were  recorded  towards  the  end  of  the  test,  with  pressure  head  varying 
between 0.087 m and 0.09 m 

                                                                 
1
Cocks,  G  (2007),  “Disposal  of  Stormwater  Runoff  by  Soakage  in  Perth  Western  Australia”,  Journal  and  News  of  the  Australian 
Geomechanics Society, Volume 42 No. 3, pp 101‐114 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 2  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     

5. SITE CONDITIONS 

5.1 Geology 

The Perth sheet of the 1:50,000 scale Environmental Geology series map indicates that the area is underlain by sand 
derived  from  the  weathering  of  Tamala  Limestone.    This  is  described  as  “SAND  ‐  pale  and  olive  yellow,  medium  to 
coarse‐grained, sub‐angular to sub‐rounded quartz, trace of feldspar, moderately sorted.” 

The findings of our investigation are in accordance with the geological mapping. 

5.2 Sub‐surface Conditions 

Based  on  the  materials  inferred  from  the  CPTs,  the  soils  are  relatively  consistent  across  the  site  and  general 
subsurface conditions can be summarised as comprising: 

SAND (SP): medium dense, becoming dense below about 7.0 m, becoming dense to very dense below about 
8.0 m  to  9.0 m,  present  below  the  existing  paving,  extending  to  the  maximum  depth  of  investigation  of 
15.0 m. 

Notes  1.  Soil  conditions  are  inferred  from  CPT  data  using  Robertson,  P.K.,  Campanella,  R.G.,  Gillespie,  D.  and 
Grieg, J. (1986) “Use of Piezometer Cone Data” 
  2.  An old layer of asphaltic concrete and basecourse material was encountered within CPT02 at depths of 
about  0.2 m  to  0.5 m.    Dummy  probing  was  conducted  through  these  layers  to  enable  the  CPT  to 
continue to target depth. 

5.3 Groundwater 

The  Perth  Groundwater  Atlas  (1997)  shows  the  maximum  historical  groundwater  level  to  be  around  RL  12 m AHD.  
This is about 17 m below the current ground surface. 

Groundwater  was  not  encountered  in  the  CPT  holes  left  following  extraction  of  the  probe  to  a  depth  of  13  m  (the 
holes  collapsed  below  this  depth).    We  do  not  consider  the  presence  of  groundwater  will  influence  the  proposed 
development. 

6. GEOTECHNICAL ASSESSMENT 

6.1 Site Classification 

We consider that the site is geotechnically capable of supporting the proposed Prowse Street Apartments. 

We have assessed the site in accordance with AS2870 (2011) “Residential Slabs and Footings”.  We consider that a site 
classification of “Class A” is appropriate provided the site preparation measures outlined in Section 6.5 are followed. 

Note:  AS2870 is limited to single and double storey residential buildings and is not strictly applicable for the proposed 
development.  This must be taken into account by the structural designers. 

6.2 Site Subsoil Class 

We  have  assessed  the  site  subsoil  class  in  accordance  with  AS1170.4‐2007,  “Earthquake  Design  Actions  – 
Australia”.  We consider that a site subsoil class of ‘Ce’ is appropriate for the site given the presence of medium dense 
to dense sands and the expected depth to rock being less than 45 m.  

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 3  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     

6.3 Footings 

6.3.1 Shallow Footings 

We  consider  the  proposed  structure  may  be  founded  on  shallow  pad  and  strip  footings  placed  within  the  sand 
encountered  across  the  site,  provided  the  site  preparation  recommendations  outlined  in  Section  6.5  are  followed.  
Table 3 and Table 4 give allowable bearing pressures and estimated settlements for various sizes of pad footings and 
strip footings founded at embedment depths of 0.5 m and 1.0 m below ground surface level and below the basement 
level.   

Table 3: Pad Footing Allowable Bearing Pressures and Estimated Settlements 
Footings below
Shallow Footings 
Minimum  Basement Level (~6 m deep) 
Min. Footing 
Footing  Allowable  Estimated  Allowable  Estimated 
Embedment (m) 
Dimension (m)  Bearing Pressure  Settlement  Bearing Pressure  Settlement 
(kPa)  (mm)  (kPa)  (mm) 
0.5  18  <5  220  <5 
1.0  200  5‐10  240  <5 
1.5  240  10‐15  250  <5 
0.5 
2.0  250  15‐20  250  5‐10 
3.0  250  25‐30  250  5‐10 
4.0  250  30‐40  250  5‐10 
0.5  200  <5  250  <5 
1.0  220  5‐10  250  <5 
2.0  250  10‐15  250  <5 
1.0 
3.0  250  20‐25  250  <5 
4.0  250  25‐30  250  <5 
5.0  250  30‐40  250  5‐10 

Table 4: Strip Footing Allowable Bearing Pressures and Estimated Settlements 
Footings below
Shallow Footings 
Min. Footing  Footing Width  Basement Level (~6 m deep) 
Allowable  Estimated  Allowable  Estimated 
Embedment (m)  (m) 
Bearing Pressure  Settlement  Bearing Pressure  Settlement 
(kPa)  (mm)  (kPa)  (mm) 
0.5  160  <5  170  <5 
1.0  200  10‐15  210  <5 
0.5  1.5  240  20‐25  250  <5 
2.0  250  25‐30  250  5‐10 
3.0  250  30‐40  250  5‐10 
0.5  250  5‐10  250  <5 
1.0  250  10‐15  250  <5 
1.0  1.5  250  20‐25  250  <5 
2.0  250  20‐25  250  <5 
3.0  250  30‐40  250  5‐10 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 4  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     
Allowable  bearing  pressures  for  footings  of  intermediate  plan  dimensions  to  those  tabulated  can  be  interpolated.  
Footings that have a plan dimension either smaller or larger than those covered by the tables above will need to be 
considered  individually  along  with  other  embedment  depths.    An  allowable  working  bearing  pressure  of  250  kPa  is 
considered  to  be  an  upper  limit  for  shallow  footings  at  this  site  to  limit  total  and  differential  settlements. 
Footings carrying significant eccentric loading, such as below retaining walls, must be assessed separately. 

The  settlement  of  the  proposed  structure  will  depend  upon  a  number  of  factors  including  the  applied  pressures, 
footing  size  and  base  preparation.    The  estimates  of  settlement  provided  above  assume  that  the  site  preparation 
measures detailed in Section 6.5 have been completed.  Differential settlements of up to half of the total estimated 
settlement values are likely between footings of similar sizes, loads and elevations.  About 70% of the settlement is 
expected to occur during construction. 

We  note  that  significant  differential  settlements  are  likely  to  occur  between  shallow  footings  and  footings  below 
basement level. 

The estimated settlements indicated in the above tables do not include interaction effects from footings founded near 
other  footings.    Interaction  effects  will  need  to  be  considered  if  the  spacing  between  adjacent  footings  are  smaller 
than the dimension of the footings (i.e. the centre‐to‐centre spacing of footings are less than twice the width of the 
footings).  This could act to double the nominated settlements, dependent on the footing configuration. 

All foundation excavations should be assessed by a competent person prior to blinding. 

6.3.2 Piled Foundations 

The structural designers may consider the use of piles to limit the total and differential settlements of the structure 
and to avoid settlement of adjacent structures.  In general, we consider the use of continuous flight auger (CFA) piles 
to be the most suitable pile type for founding the structure.  However, other pile types may also be considered. 

CFA pile design parameters have been adopted from the Bustamante and Gianeselli (1982) 2 pile design method which 
is based on CPT data.  Pile design parameters for other pile types can be provided if required. 

The  soil  profile  and  assumed  parameters  are  presented in  Table  5:  Design  Parameters  for  CFA  Piles  (ultimate).    For 
piles  founded  below  the  basement  level  (about  6  m  below  current  ground  level),  the  upper  sand  layers  are  not 
relevant  for  pile  design  and  must  be  ignored.    Furthermore,  the  top  1  m  of  any  pile  should  not  be  considered  to 
contribute to pile shaft resistance. 

Table 5: Design Parameters for CFA Piles (ultimate) 
Depth  Layer Description  qc1  qc design Rf  ’3 ’4   fm,s5  fb6 
2
(mbgl)  (MPa) (MPa) (%)   (°) (kN/m3)  (kPa)  (kPa) 
0 to 2.0  Loose to medium dense 1‐10  ignore ‐  ‐  ‐  ‐  ‐ 
2.0 to 7.0 Medium dense sand  5‐12  7  0.5 ‐ 1 34 17  70  2,800 
7.0 – 9.0  Dense sand  12‐20 15  0.5 ‐ 1 36 18  100  4,500 
9.0 – 15.0 Very dense sand  20‐30 20  0.5 ‐ 1 38 18  120  6,000 

NOTES: 
1. qc   – Cone Tip Resistance      2. Rf   – CPT Friction ratio 
3. ’  – Friction angle (effective)    4. ’  – Effective unit weight (above water table) 
5. fm,s   – unit shaft resistance (ultimate)  6. fb   – unit base resistance (ultimate) 

                                                                 
2  Bustamante, M. and Gianeselli, L., Pile bearing capacity prediction by means of static penetrometer CPT, Proc. 2nd European Symp. 

on Penetration Testing, Amsterdam, 1982, pp 493‐500 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 5  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     
Individual piles must be designed such that the toe extends into the dense or very dense sand. 

Furthermore, we note that the end‐bearing capacity of a CFA pile is highly dependent on the condition of the base and 
any disturbance of soil below the pile toe.  We therefore advise that the piles need to be designed to take the full 
working load in shear on the pile shaft. 

Pile design must be done in accordance with AS2159‐2009, including selection of an appropriate testing regime and 
associated geotechnical strength reduction factor. 

A suitably experienced contractor must be appointed to design, install and test the piles. 

6.4 Earth Retaining Structures 

6.4.1 Retaining Options 

Given  the  proximity  of  the  proposed  building  to  the  site  boundaries,  adjacent  buildings  close  to  these  boundaries 
must be taken into account when designing and constructing basement retaining walls.  We do not consider that the 
basement  excavation  can  be  undertaken  without  retention  (temporary  or  permanent)  being  installed  prior  to 
excavation as there is insufficient space to form safe batters. 

Any  retention  system  used  must  be  designed  to  minimise  vertical  and  horizontal  movements  and  the  associated 
potential for damage to adjacent structures. 

The  designer  of  the  retaining  structure  must  assess  the  likely  ground  movement  and  the  influence  on  adjacent 
structures.  We can assist with such design if required.  The amount of ground movement is largely controlled by the 
stiffness of the retaining structure, the anchoring or strutting system and the construction method. 

Temporary supports may be needed to provide adequate strutting.  The excavation should also be scheduled in such a 
way that the necessary support of the retaining system is available throughout the whole construction process prior to 
the permanent lateral support being provided by the structure. 

This  information  is  provided  for  guidance  only  and  the  designer  of  the  retaining  structure  must  assess  the  likely 
ground movement and the influence on adjacent structures.  Further advice and detailed design can be provided if 
necessary.    Irrespective  of  the  above,  a  dilapidation  survey  of  adjacent  properties  should  be  conducted  prior  to 
construction. 

The  type  of  retaining  system  must  be  carefully  selected  to  avoid  noise  and  vibration  disturbance.    Given  the 
requirements, we consider a contiguous pile wall system to be the most appropriate system for this site. 

6.4.2 Retaining Wall Design Parameters 

Retaining structures may be designed in accordance with AS 4678‐2002 “Earth‐Retaining Structures”.   

We recommend that all retaining walls at the site be backfilled with free‐draining fill, e.g. sand (either site‐derived or 
imported free draining sand fill with less than 5% fines). 

For the design of retaining structures, the following parameters are considered appropriate for in situ medium dense 
sand and compacted sand backfill: 

angle of internal friction,  = 36°; 
coefficient of active earth pressure Ka = 0.26; 
coefficient of passive earth pressure Kp = 3.85; 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 6  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     
at rest coefficient of earth pressure K0 = 0.41; 
bulk density: 18 kN/m3; and 

Compaction  plant  can  augment  the  lateral  earth  pressure  acting  on  retaining  walls.    Hand  operated  compaction 
equipment is recommended within 2 m of any retaining walls to minimise compaction pressures. 

It  is  important  to  note  that  some  ground  movement  is  to  be  expected  behind  any  soil  retaining  system,  including 
gravity retaining walls. 

6.5 Site Preparation 

The  site  preparation  measures  outlined  below  are  aimed  at  preparation  of  the  site  prior  to  construction  of  the 
building and pavement subgrades.  Landscaped areas (if any) will not require this preparation. 

The following site preparation measures must be followed: 

Demolish  existing  buildings  as  required  and  remove  demolition  debris  and  any  other  deleterious  material 
from site including old footings, slabs, soak wells, buried services, paved areas and building rubble. 
Strip  uncontrolled  fill  from  the  site  (where  encountered)  and  if  suitable,  stockpile  it for  potential  re‐use  as 
non‐structural fill.  If contaminated, dispose of it off site.  We did not encounter uncontrolled fill during the 
investigation. 
Construct  temporary/permanent  retaining  walls  (see  Section  6.4)  around  the  periphery  of  the  basement 
excavation. 
Excavate to basement level and dispose of material off site.  The excavated material is considered suitable for 
re‐use as structural fill if required, however there will be a surplus of spoil on the site. 
Compact the exposed base of the basement to achieve the level of compaction specified in Section 6.6 to a 
depth of at least 0.9 m below the base of the excavation. 
Any areas of loose sand or unsuitable material must be removed and replaced with approved fill as outlined 
in Section 6.7. 
Where fill is required to build up levels, use approved fill (see Section 6.7), placed and compacted in layers no 
greater than 300 mm loose thickness. 
Excavate  for  pad  and  strip  footings  and  compact  the  exposed  bases  to  achieve  the  level  of  compaction 
specified in Section 6.6 to a depth of at least 0.9 m below the underside of all footings.  Remove, replace and 
compact as required with approved fill any zone not achieving the level of compaction specified in Section 
6.6. 

6.6 Compaction 

In situ sand and granular fill must be compacted using suitable compaction equipment to achieve a dry density ratio 
(DDR) of at least 95% of maximum modified dry density (MMDD) as determined in accordance with AS 1289 5.2.1 at a 
moisture content within 2% of optimum moisture content (OMC). 

Where  sand  (containing  less  than  5%  fines)  is  used  as  fill,  a  Perth  sand  penetrometer  (PSP)  may  be  used  for 
compaction control.  The following minimum PSP blow counts are considered to correlate to the required DDR: 

150 mm‐450 mm: 8 
450 mm‐750 mm: 10 
750 mm‐900 mm: 12 

If difficulties are experienced in achieving the required blow count, an on‐site PSP calibration should be undertaken to 
determine the site‐specific PSP blow count required to achieve the required dry density ratio. 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 7  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     
Over‐excavation  and  replacement  of  loose  materials  may  be  required  where  the  minimum  density  cannot  be 
achieved. 

Fill must be placed in horizontal layers of not greater than 300 mm loose thickness.  Each layer must be compacted by 
suitable compaction equipment, and carefully controlled to ensure even compaction over the full area and depth of 
each layer. 

Care  will  need  to  be  taken  when  compacting  in  the  vicinity  of  existing  structures.    This  is  particularly  important  if 
vibratory  compaction  is  being  carried  out.    Tynan  (1973)3 provides  assistance  with  the  selection  of  compaction 
equipment for use adjacent to structures.  Of particular concern are the existing buildings to the east and west. 

After compaction, verify that the level of compaction has been achieved by testing to a minimum depth of 0.9 m:  

On each lift of fill on a 10 m grid; 
At each spread footing location; 
At 5 m centres along strip footings; and 
On a grid of 7.5 m centres below on‐ground slabs and paved areas. 

6.7 Approved Fill 

Imported  granular  fill  must  comply  with  the  material  requirements  as  stated  in  AS 3798‐2007,  “Guidelines  on 
Earthworks for Commercial and Residential Developments”. 

Generally,  the  in  situ  sand  and  sand  fill  present  at  the  site  will  be  suitable  for  re‐use  as  inert  structural  fill.    Any 
organic‐rich sand or sand containing significant proportions of fines (material less than 0.075 mm in size) must not be 
used.   

Where  doubt  exists,  a  geotechnical  engineer  must  be  engaged  to  inspect  and  approve  the  use  of  potential  fill 
materials.  

6.8 Stormwater Disposal 

The results of permeability testing are presented in Appendix C, Permeability Test Results and summarised in Table 2: 
Summary of Permeability Test Results.  The minimum measured permeability was 12.9 m/day. 

We  assume  that  stormwater  will  be  disposed  of  using  soak‐wells  or  similar  below  the  lower  basement  level 
(RL 25.6 m AHD).  Permeability testing was conducted 6.0 m below the ground level at approximately RL 24 m AHD to 
RL 25 m AHD.  Notwithstanding the results of the permeability testing, we recommend a design value of permeability 
(k) not greater than 5 m/day be used for the sand fill to allow for the variability in materials and reduced permeability 
as a consequence of: 

densification of sand during site preparation works; 
natural variation in sands; and 
clogging of the sand around soakwells and soakage basins over time with fines. 

Soak wells should be placed outside a line of 1V:2H extending below the edge of the nearest footing (or at least 3 m of 
footings  or  on‐ground  slabs)  subject  to  local  council  regulations.    Discharge  from  soak  wells  has  been  known  to 
promote densification of loose sandy soils, leading to settlements of footings and slabs.  Soak wells should be carefully 
wrapped with geotextile to prevent migration of sand and fines into the soak well. 

                                                                 
3  Tynan (1973) Ground Vibration and Damage Effects on Buildings, Australia Road Research Board, Special Report No. 11. 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 8  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
J1501056 001 R Rev0        
10 April 2015     

6.9 Pavement Design 

Where pavement subgrades comprise the surficial sandy soil present across the site at the current surface level (or at 
basement  floor  level),  a  design  subgrade  CBR  of  12%  may  be  assumed  provided  the  site  preparation  measures 
identified in Section 6.5 are followed. 

7. CLOSURE 

We  draw  your  attention  to  Appendix  D  of  this  report,  Understanding  your  Geotechnical  Engineering  Report.    The 
information provided within is intended to inform you as to what your realistic expectations of this report should be.  
Guidance is also provided on how to minimise risks associated with groundworks for this project.  This information is 
provided  not  to  reduce  the  level  of  responsibility  accepted  by  Galt,  but  to  ensure  that  all  parties  who  rely  on  this 
report are aware of the responsibilities each assumes in so doing. 

GALT GEOTECHNICS PTY LTD 

 
Rick Piovesan CPEng  James Harris 

Geotechnical Engineer  Geotechnical Engineer 
O:\Jobs\2015\J1501056 ‐ Alijn Built SI West Perth\03 Correspondence\J1501056 001 R Rev0.docx 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | 9  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014    
   

Figures 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au    ABN: 73 292 586 155 
2/39 Flynn St, WEMBLEY  WA  6014    
Rail
wa y Pd
e

Colin Pl
Subiaco Rd Ra
ilw
a yS
t
Art

St
hur
St

as
om
Th
Wes St
t St Prowse

Cam pbel
l
wP

v
kno

ro P

eA
Luc

l
enc
Dou

St
r
Well )
Delhi St (a

Law
in gto
n St

St

St
tram

in
Col
Ou
Legend
Site Boundary

Cone Penetration Test


I
#
CPT01
I
#

±
6,465,100

6,465,100
0 4 8 12 16 20

Meters

SCALE 1:250 (A3)

DRAWN DAC

DATE DRAWN 31/03/2015


CPT02 SITE LOCATION PERTH
I
# CHECKED JH

DATE CHECKED 10/04/2015

PROJECTION GDA 1994 MGA Zone 50

Galt Geotechnics Pty Ltd


ACN : 138 490 865
Tel : +61 (0)8 6272-0200
Fax : +61 (0)8 9285 8444
Address : U2, 39 Flynn Street,
_Wembley, WA, 6014

COPYRIGHT 2015 THIS FIGURE AND ITS CONTENTS REMAINS THE PROPERTY OF GALT
©

GEOTECHNICS PTY LTD AND MAY NOT BE REPRODUCED WITHOUT PRIOR APPROVAL.
l
ro P

THIS FIGURE SHOULD BE READ IN CONJUNCTION WITH THE ACCOMPANYING REPORT.


Dou

Prowse St CLIENT
A-LIJN BUILT FORMS
PROJECT PROWSE STREET APARTMENTS
LOCATION 14 PROWSE STREET
WEST PERTH
TITLE SITE & LOCATION PLAN
J1501056 FIGURE 1 A
Job No Fig No Rev

O:\Jobs\2015\J1501056 - Alijn Built SI West Perth\09 GIS\04 MXD\J1501056-001.mxd (DamonClark) 31/03/2015 1:30:50 PM
   

Appendix A:  Site Photographs

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au    ABN: 73 292 586 155 
2/39 Flynn St, WEMBLEY  WA  6014 
 
J1501056 001 R Rev0        
10 April 2015     

Photograph 1: CPT rig at CPT02 location

Photograph 2: Locating services at CPT02

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | A1  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014 
 
J1501056 001 R Rev0        
10 April 2015     

Photograph 3: Looking northwest towards CPT01

Photograph 4: Looking north from Prowse Street towards CPT02 location 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au  Page | A2  ABN: 73 292 586 155 


2/39 Flynn St, WEMBLEY  WA  6014 
 
   

Appendix B:  Cone Penetration Test Results

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au    ABN: 73 292 586 155 
2/39 Flynn St, WEMBLEY  WA  6014 
 
Cone Resistance, qt

Friction Ratio (%)
DEFINITIONS
qt : Cone tip resistance corrected for pore water pressure
St : Sensitivity
e : Void ratio
Dr : Relative density
OCR : Overconsolidation ratio
OC : Overconsolidated

SOIL BEHAVIOUR TYPE ZONES
1. Sensitive fine grained 7. Silty sand to sandy silt
2. Organic material 8. Sand to silty sand
3. Clay 9. Sand
4. Silty clay to clay 10. Gravelly sand to sand
5. Clayey silt to silty clay 11. Very stiff fine grained material (OC/cemented)
6. Sandy silt to clayey silt 12. Sand to clayey sand (OC/cemented)

NOTES
A. Some overlap in type zones is expected
B. Local correlations are preferred and may indicate soil type boundaries that are different 
from those shown above
Reference: Robertson, P.K., Campanella, R.G., Gillespie, D. and Grieg, J. (1986) "Use of Piezometer Cone Data".  Proceedings of the ASCE Speciality 
Conference In Situ '86: Use of In Situ Tests in Geotechnical Engineering, Blacksburg, pp 1263‐80, American Society of Civil Engineers (ASCE)

CONE PENETRATION TESTING (CPT) 
SOIL TYPE INTERPRETATION

Galt Form PMP18
O:\Administration\Standard Forms and Documents\PMP18 CPT Interpretation.xlsx RL 0 October 2009
ELECTRIC FRICTION-CONE PENETROMETER
CLIENT: A-Lijn Built Forms Date: Monday, 30 March 2015

PROJECT: Proposed Prowse Street Apartments Probe No.: All Data

LOCATION: 14 Prowse Street, West Perth Job Number: J1501056


RL (m): Co-ordinates:

Tip Resistance qc (MPa) Friction Sleeve fs (kPa) Friction Ratio Rf (%)

100

200

300

400

500
10
15
20
25
30
35
40
45
50
0
5

5
0
0

0
0
1

1
1
2

2
2
3

3
3
4

4
4
5

5
5
CPT 2A
6

6
6
7

7
7
CPT 2

Depth (m)

Depth (m)
Depth (m)

8
8
CPT 1
9

9
9
10

10
10
11

11
11
12

12
12
13

13
13
14

14
14
15

15
15
16

16
16

Water (m): Tested in accordance with AS 1289.6.5.1 - 1999


and IRTP 2001 for friction reducer
Refusal:

File: Cone I.D. : Dummy probe to (m): 22 tonne truck mounted CPT Rig (Track Truck)
ELECTRIC FRICTION-CONE PENETROMETER
CLIENT: A-Lijn Built Forms Date: Monday, 30 March 2015
PROJECT: Proposed Prowse Street Apartments Probe No.: CPT 1
LOCATION: 14 Prowse Street, West Perth Job Number: J1501056
RL (m): Co-ordinates:

Tip Resistance qc (MPa) Friction Sleeve fs (kPa) Friction Ratio Rf (%)

100

200

300

400

500
10
15
20
25
30
35
40
45
50

0
0
5

5
0
0

0
1
1

1
2
2

2
3
3

3
4

4
4

5
5

6
6

7
7

Depth (m)

Depth (m)
Depth (m)

8
8
8

9
9
9

10
10
10

11
11
11

12
12
12

13
13
13

14
14
14

15
15
15

16
16
16

Water (m): Dry to 13.9 Tested in accordance with AS 1289.6.5.1 - 1999


and IRTP 2001 for friction reducer
Refusal:

File: GL0343TT Cone I.D. : EC38 Install 32mm Standpipe to (m): 6.0 22 tonne truck mounted CPT Rig (Track Truck)
ELECTRIC FRICTION-CONE PENETROMETER
CLIENT: A-Lijn Built Forms Date: Monday, 30 March 2015
PROJECT: Proposed Prowse Street Apartments Probe No.: CPT 2A
LOCATION: 14 Prowse Street, West Perth Job Number: J1501056
RL (m): Co-ordinates:

Tip Resistance qc (MPa) Friction Sleeve fs (kPa) Friction Ratio Rf (%)

100

200

300

400

500
10
15
20
25
30
35
40
45
50

0
0
5

5
0
0

0
1
1

1
2
2

2
3
3

3
4

4
4

5
5

6
6

7
7

Depth (m)

Depth (m)
Depth (m)

8
8
8

9
9
9

10
10
10

11
11
11

12
12
12

13
13
13

14
14
14

15
15
15

16
16
16

Water (m): Dry to 15.2 Tested in accordance with AS 1289.6.5.1 - 1999


and IRTP 2001 for friction reducer
Install 32mm Standpipe to (m): 6.0

File: GL0345TT Cone I.D. : EC38 Dummy probe to (m): 0.5 22 tonne truck mounted CPT Rig (Track Truck)
   

Appendix C:  Permeability Test Results

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au    ABN: 73 292 586 155 
2/39 Flynn St, WEMBLEY  WA  6014 
 
Permeability Calculation - Inverse Auger Hole Method
Galt Geotechnics Spreadsheet author: ORW 17-Oct-09 REFERENCE: Cocks, G. Disposal of
Job No: J1501056 Stormwater Runoff by Soakage in Perth
Western Australia, Journal and News of
Client: A-Lijn Built Form 1 1 the Australian Geomechanics Society,
Site: 14 Prowse Street log10 (h0 + r ) − log10 (h t + r ) Volume 42 No 3 September 2007,
Location: West Perth K = 1.15r 2 2 pp101-114
Calc by: JH 30-Mar-15 t − t0
BH Name: CPT01 Parameter Description Value Units
Test Depth: 6 m K Permeability m/s
Spreadsheet Legend r radius of test hole 0.016 m
Required input t time since start of measurement s
Calculated field hr reference point height above base m
Comment field dt depth from reference point to water at time t m
Field not used ht Water column height at time t m
Fixed field h0 ht at t=0 m

Test 1 Test 2 Test 3


t (s) dw (m) ht (m) K (m/s) K (m/day) t (s) dw (m) ht (m) K (m/s) K (m/day) t (s) dw (m) ht (m) K (m/s) K (m/day)
0 1.277 0 1.866 0 1.662
10 0.691 4.9E-04 42.0 10 0.869 6.1E-04 52.4 10 0.826 5.5E-04 47.9
20 0.465 4.0E-04 34.5 20 0.618 4.4E-04 37.9 20 0.597 4.1E-04 35.1
30 0.314 3.7E-04 31.9 30 0.446 3.8E-04 32.7 30 0.434 3.5E-04 30.6
40 0.223 3.4E-04 29.6 40 0.326 3.4E-04 29.8 40 0.315 3.3E-04 28.4
50 0.169 3.2E-04 27.4 50 0.245 3.2E-04 27.6 50 0.234 3.1E-04 26.7
60 0.139 2.9E-04 25.0 60 0.194 3.0E-04 25.6 60 0.189 2.8E-04 24.6
70 0.122 2.6E-04 22.6 70 0.151 2.8E-04 24.3 70 0.151 2.7E-04 23.2
80 0.111 2.4E-04 20.5 80 0.135 2.6E-04 22.2 80 0.131 2.5E-04 21.4
90 0.101 2.2E-04 18.9 90 0.120 2.4E-04 20.6 90 0.116 2.3E-04 20.0
100 0.099 2.0E-04 17.2 100 0.113 2.2E-04 18.9 100 0.106 2.1E-04 18.5
110 0.093 1.8E-04 15.9 110 0.108 2.0E-04 17.5 110 0.099 2.0E-04 17.2
120 0.091 1.7E-04 14.8 120 0.104 1.9E-04 16.2 120 0.091 1.9E-04 16.3
130 0.086 1.6E-04 13.9 130 0.098 1.8E-04 15.2 130 0.090 1.7E-04 15.0
140 0.087 1.5E-04 12.9 140 0.095 1.7E-04 14.3
150 0.088 1.6E-04 13.7

AVERAGE 2.7E-04 23.4 AVERAGE 2.8E-04 24.6 AVERAGE 2.9E-04 25.0

O:\Jobs\2015\J1501056 - Alijn Built SI West Perth\08 Analysis\J1501056 Permeability Inverse Auger Hole Method
Permeability by Inverse Auger Hole Method
CPT01
60.0

50.0

40.0
Permeability, k (m/day)

Test 1
30.0 Test 2
Test 3

20.0

10.0

0.0
0 20 40 60 80 100 120 140 160
Test time, t (seconds)

O:\Jobs\2015\J1501056 - Alijn Built SI West Perth\08 Analysis\J1501056 Permeability Inverse Auger Hole Method
   

Appendix D:  Understanding Your 
Geotechnical Engineering Report 

Galt Geotechnics Pty Ltd 

www.galtgeo.com.au    ABN: 73 292 586 155 
2/39 Flynn St, WEMBLEY  WA  6014    
 
UNDERSTANDING YOUR GEOTECHNICAL
ENGINEERING REPORT
GALT FORM PMP11 Rev1

1. EXPECTATIONS OF A GEOTECHNICAL ENGINEERING REPORT

This document has been prepared to clarify what is and is not provided in your geotechnical report. It is intended to inform you
of what your realistic expectations of this report should be and how to manage your risks associated with geotechnical
conditions.

Geotechnical engineering is a less exact science than other engineering disciplines. We include this information to help you
understand where our responsibilities as geotechnical engineers begin and end, to help the client recognise his responsibilities
and risks. You should read and understand this information. Please contact us if you do not understand the report or this
explanation. We have extensive experience in a wide variety of geotechnical problems and we can help you to manage your risk.

2. THIS REPORT RELATES TO PROJECT-SPECIFIC CONDITIONS

This report was developed for a unique set of project-specific conditions to meet the needs of the nominated client. It took into
account the following :

The project objectives as we understood them and as described in this report;


the specific site mentioned in this report; and
the current and proposed development at the site.

It should not be used for any purpose other than that indicated in the report. You should not rely on this geotechnical report if
any of the following conditions apply:

the report was not written for you;


the report was not written for the site specific to your development;
the report was not written for your project (including a development at the correct site but other than that listed in the
report); or
the report was written before significant changes occurred at the site (such as a development or a change in ground
conditions).

You should always inform us of changes in the proposed project (including minor changes) and request an assessment of their
impact.

Where we are not informed of developments relevant to your geotechnical engineering report, we cannot be held responsible
or liable for problems that may arise as a consequence.

Where design is to be carried out by others using information provided by us, we recommend that we be involved in the design
process by being engaged for consultation with other members of the design team and by being able to review work produced
by other members of the design team which relies on geotechnical information provided in our report.

Galt Geotechnics Pty Ltd

www.galtgeo.com.au Page | 1 ABN: 73 292 586 155


2/39 Flynn St, WEMBLEY WA 6014
Form PMP11 Rev1
16 December 2009

3. GEOTECHNICAL ENGINEERING LOGS

Our reports often include logs of intrusive and non-intrusive geotechnical investigation techniques. These logs are based on our
interpretation of field data and laboratory results. The logs should only be read in conjunction with the report they were issued
with and should not be re-drawn for inclusion in other documents not prepared by us.

4. THIRD PARTY RELIANCE

We have prepared this report for use by the client. This report must be regarded as confidential to the client and the client’s
professional advisors. We do not accept any responsibility for contents of this document from any party other than the
nominated client. We take no responsibility for any damages suffered by a third party as a consequence of any decisions or
actions they may make based on this report. Any reliance or decisions made by a third party based on this report are the
responsibility of the third party and not of us.

5. CHANGE IN SUBSURFACE CONDITIONS

The geotechnical recommendations in this report are based on the ground conditions that existed at the time when the study
was undertaken. Changes in ground conditions can occur in numerous ways including as a result of anthropogenic events (such
as construction on or adjacent to the site) or natural events (such as floods, groundwater fluctuations or earthquakes). We
should be consulted prior to use of this report so that we can comment on its reliability. It is important to note that where
ground conditions have changed, additional sampling, testing or analysis may be required to fully assess the changed conditions.

6. SUBSURFACE CONDITIONS DURING CONSTRUCTION

Practical constraints mean that we cannot know every minute detail about the subsurface conditions at a particular site. We use
engineering judgement to form an opinion about the subsurface conditions at the site. Some variation to our evaluated
conditions is likely and significant variation is possible. Accordingly, our report should not be considered as final as it is
developed from engineering judgement and opinion.

The most effective means of dealing with unanticipated ground conditions is to engage us for construction support. We can only
finalise our recommendations by observing actual subsurface conditions encountered during construction. We cannot accept
liability for a report’s recommendations if we cannot observe construction.

7. ENVIRONMENTAL ISSUES

Unless specifically mentioned otherwise in our report, environmental considerations are not included. The investigation
techniques used by us in developing our report differ from those for an environmental investigation. Our report was not
prepared with environmental considerations in mind and it is the client’s responsibility to satisfy himself that environmental
considerations have been taken into account for the site. If you require guidance on how to proceed on evaluating
environmental risk at the site, we can provide further information and contacts.

O:\Administration\Standard Forms and Documents\PMP11 Understanding your Geotechnical Engineering Report.docx

Galt Geotechnics Pty Ltd

www.galtgeo.com.au Page | 2 ABN: 73 292 586 155


2/39 Flynn St, WEMBLEY WA 6014

You might also like