Scheduling/Leveling Report - 2022-11-13 18:59:53 - PM.

EXE
=========================================================

Default Project..................................................SA-5
Use scheduling options from......................................SA-5

Projects:
SA-5............................................................Shell
GTL Mettio Tank Demolision-option1 Roof Progress update

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................Yes
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................Yes
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
Consider assignments in other projects,
with priority equal/higher than..................................5
Preserve scheduled early and late dates..........................Yes
Level resources only within activity Total Float.................Yes
Preserve minimum float when leveling.............................0
Max percent to over-allocate resources...........................25
Level Priority 1.................................................Activity
Leveling Priority - Ascending
Level all resources..............................................Yes

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................42
# Not Started....................................................31
# In Progress....................................................10
# Completed......................................................1
# Relationships..................................................44
# Activities with Constraint.....................................1
Project: SA-5 Activity: A1000 Start

Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: SA-5 Activity: A1000 Start

Activities without successors....................................1


Project: SA-5 Activity: A1010 Finish

Out-of-sequence activities.......................................4
Project: SA-5 Activity: A1070 RLIC Gate pass Application
Project: SA-5 Activity: A1080 Mandatory Third Party Trainning
Project: SA-5 Activity: A1090 QSGTL Clinc FTW Clearance
Project: SA-5 Activity: A1130 PRPH Authorization

Activities with Actual Dates > Data Date.........................0

Milestone Activities with invalid relationships..................0

Finish milestone and predecessors have different calendars.......0

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................42
# Relationships with other projects..............................0
Data Date........................................................13-Nov-22
Earliest Early Start Date........................................13-Nov-22
Latest Early Finish Date.........................................06-Feb-23
Exceptions:
-----------
Critical Activities..............................................35
Project: SA-5 Activity: A1010 Finish
Project: SA-5 Activity: A1020 Submission of manpower Details &
Lifting Plan
Project: SA-5 Activity: A1030 Submission Method statement
Project: SA-5 Activity: A1040 Approval of MS from Client
Project: SA-5 Activity: A1050 QSGTL Online Induction
Project: SA-5 Activity: A1060 FIT to work medical
Project: SA-5 Activity: A1070 RLIC Gate pass Application
Project: SA-5 Activity: A1080 Mandatory Third Party Trainning
Project: SA-5 Activity: A1090 QSGTL Clinc FTW Clearance
Project: SA-5 Activity: A1100 Site Onboard & Camp Mobilization
Project: SA-5 Activity: A1110 Equipment Inspection & Clearance
Project: SA-5 Activity: A1120 Scaffolding Materials mobilization
Project: SA-5 Activity: A1130 PRPH Authorization
Project: SA-5 Activity: A1140 Submission of supporting Documents
for EPTW Approvals
Project: SA-5 Activity: A1150 Permit process and approvals
Project: SA-5 Activity: A1160 Preparation of for Crane
Mobilization
Project: SA-5 Activity: A1170 Preparation of Execution Zone
Project: SA-5 Activity: A1180 Blinding and Isolation of the
Supply
Project: SA-5 Activity: A1200 Removal Manway blind
Project: SA-5 Activity: A1210 Gas testing & Removal of Sluge and
water Below Manway
Project: SA-5 Activity: A1220 Cleanning and ventiliation in side
the tank
Project: SA-5 Activity: A1230 Shifting & Erection of Scaffolding
Outside the tank (External+Utility area)
Project: SA-5 Activity: A1240 Erection of Movable internal
scaffolding for Removal of Roof 1st Layer
Project: SA-5 Activity: A1250 Placing the Cane on position
Project: SA-5 Activity: A1260 Roof Top 1st layer removal with
Crane
Project: SA-5 Activity: A1270 Installation of internal
scaffolding to support & access the roof
Project: SA-5 Activity: A1280 Dismantling the roof segments and
Support structure one by one
Project: SA-5 Activity: A1290 Dismantling Wind and Top Stiffer
Plates:
Project: SA-5 Activity: A1310 Dismantling of Tank shell plates
(Top to bottom)
Project: SA-5 Activity: A1340 Removal Bottom Civil Structure /
Concrete Base
Project: SA-5 Activity: A1350 Leveling the Ground
Project: SA-5 Activity: A1360 Shifting the Waste to Laydown
Project: SA-5 Activity: A1370 Request for Inspection
Project: SA-5 Activity: A1380 Submittion of Final Hanover
Documents
Project: SA-5 Activity: A1390 Job Completion approval from Client

Activities with unsatisfied constraints..........................0

Activities with unsatisfied relationships........................0

Activities with external dates...................................0

Activities delayed due to predecessor delay......................0

Activities delayed due to resource leveling......................0

Activities that cannot be leveled................................13


Project: SA-5 Activity: A1170 Preparation of Execution Zone
Project: SA-5 Activity: A1180 Blinding and Isolation of the
Supply
Project: SA-5 Activity: A1200 Removal Manway blind
Project: SA-5 Activity: A1240 Erection of Movable internal
scaffolding for Removal of Roof 1st Layer
Project: SA-5 Activity: A1250 Placing the Cane on position
Project: SA-5 Activity: A1260 Roof Top 1st layer removal with
Crane
Project: SA-5 Activity: A1270 Installation of internal
scaffolding to support & access the roof
Project: SA-5 Activity: A1300 Barricating the area for Excavation
and Lifting
Project: SA-5 Activity: A1340 Removal Bottom Civil Structure /
Concrete Base
Project: SA-5 Activity: A1360 Shifting the Waste to Laydown
Project: SA-5 Activity: A1370 Request for Inspection
Project: SA-5 Activity: A1380 Submittion of Final Hanover
Documents
Project: SA-5 Activity: A1390 Job Completion approval from Client

Activities overallocated within float............................16


Project: SA-5 Activity: A1170 Preparation of Execution Zone
Project: SA-5 Activity: A1180 Blinding and Isolation of the
Supply
Project: SA-5 Activity: A1200 Removal Manway blind
Project: SA-5 Activity: A1210 Gas testing & Removal of Sluge and
water Below Manway
Project: SA-5 Activity: A1230 Shifting & Erection of Scaffolding
Outside the tank (External+Utility area)
Project: SA-5 Activity: A1240 Erection of Movable internal
scaffolding for Removal of Roof 1st Layer
Project: SA-5 Activity: A1250 Placing the Cane on position
Project: SA-5 Activity: A1260 Roof Top 1st layer removal with
Crane
Project: SA-5 Activity: A1270 Installation of internal
scaffolding to support & access the roof
Project: SA-5 Activity: A1290 Dismantling Wind and Top Stiffer
Plates:
Project: SA-5 Activity: A1300 Barricating the area for Excavation
and Lifting
Project: SA-5 Activity: A1340 Removal Bottom Civil Structure /
Concrete Base
Project: SA-5 Activity: A1360 Shifting the Waste to Laydown
Project: SA-5 Activity: A1370 Request for Inspection
Project: SA-5 Activity: A1380 Submittion of Final Hanover
Documents
Project: SA-5 Activity: A1390 Job Completion approval from Client