Professional Documents
Culture Documents
Ads by
Send feedback Why this ad?
PerkinElmer®
Facebook Twitter
Instagram Linkedin
• Excavation.
• Subgrade.
Main Tags
• Subbase.
The purpose of this document is to ensure that the standards and speci cation of the School CE Tips Checklist Circular Slab
Project and that of "Company Name" is effectively implemented during the process of Road and
Civil Engineering
paving work. This method statement provides the necessary support to the team with relevant
information regarding the speci c project requirement and a guideline for a procedure to work Civil Engineering and Const Tips
safely.
Civil Engineering Basic Knowledge
signatures shall be taken on the approved method statement as a matter of record. Daily (at
Civil Engineering Tips Concrete
the start of each shift) the Works Supervisor and HSEO will complete a Pre-works brie ng with
ALL labor based on the activities to be complete in the shift (pre-works brie ng will be signed Concrete Embedded Elements.
by ALL labor to demonstrate that they have understood the activities and associated controls.
Download the Free Guide
They will then complete a site walk to ensure and verify that all the controls are in place. Both
Concrete WorksLearnConstruction
More
Construction Surveying
File upload line VECTOR icon What is Non Conformance
Report (NCR) in Construction |
Two main categories of NCRs
in a Construction Site
by QA QC Civil Engineering - August 20, 2017
Understanding About
Inspection and Test Plan
(ITP) | Inspection Records |
Inspection Levels
August 19, 2017
Recent Posts
Scope:
Pdf document note icon in at…
This method statement describes the activities and process of Road and paving work for
Download
School Project works include preparation, installation and protection as per the project
requirement.
The purpose of this method statement is to conduct a systematic work execution for the Road Comments
and paving work for that will produce and deliver a safe execution procedure in accordance with
the approved Standards/Speci cations and Lifting procedure. Anonymous
Big data is a term that describes the large
volume...
It is the Policy of "Company Name" to provide a safe and healthy place of employment. In areas
where scaffolding is to be erected, dismantled, altered, moved or accessed for any purpose, the
following procedure shall be utilized.
Anonymous
• MIR / reports shall be submitted along with relevant documents prior to proceeding.
Asphalt (1)
Bar Bending Schedule (6)
Building (1)
Civil Engineering (25)
Civil Engineering Interview Questions (2)
2. Excavation for Road Construction:
Concrete (3)
Construction (18)
• Common Excavation shall consist of the excavation and satisfactory disposal of all soils, Costing and Estimation (3)
certain strata, and individual rock boulders less than 1 cubic meter in volume as instructed by Inspection and Test Plan (ITP) (1)
Land Surveying (4)
the Engineer. Strata which are altered and weathered and are in place, but which are not rm
Method Statement (4)
enough, or in the opinion of the Engineer are not rigid enough to have all the characteristics of QA QC Civil Engineering (16)
rock excavation shall be classi ed as common excavation.
• Rock Excavation shall consist of the excavation and satisfactory disposal of all unaltered and
un weathered rm and rigid igneous, metamorphic, and sedimentary solid rock and boulders
exceeding one cubic meter in volume that in the opinion of the Engineer are impracticable to
remove by heavy mechanical excavating equipment or by heavy duty hydraulic ripper, or by
approved pneumatic tools.
• Roadway excavation shall be sub classi ed as Common Excavation and Rock Excavation.
• All material removed from an excavation shall be used in the formation of the embankment,
shoulders and at such other places in storage yard.
• No excavated material shall be disposed without written permission from the consultant and
clients.
Download the Free Guide Learn More
the RAMS and Pre-works brie ng will be located on site with the Works Supervisor for reference Cost Estimation
and review.
Costing and Estimation
• Subgrade samples for Soil classi cation, laboratory moisture density relationship tests and
Is QA QC a Good Career ITP
CBR tests shall be taken prior to use, from any proposed source of material.
Land Surveying Land Surveyor
• Each sample shall represent not more than 3,000 Cu.m of stockpiled material.
Method Statement NCR
QA QC Civil Engineering
QC Inspector
QC Means in Construction
PerkinElmer®
Quality Control
• Sub-Base One sample every 3000-cu m of stockpiled material shall be tested for Grading,
Download the Free Guide
Plasticity Index, Maximum Dry Density, and Los Angeles Abrasion.
ReinforcementLearnRoad
More
Role of QC Inspector
3. Subgrade – Roads:
• Excavation shall be for the full construction width down to subgrade level. For a further depth
of 15 cm the existing material shall be scari ed, watered as necessary, mixed and compacted
to not less than 95% of maximum dry density.
• Fill and embankments, an 'improved subgrade layer', using speci ed material in accordance
with project speci cation.
• The improved subgrade layer shall be compacted to not less than 95% maximum dry density.
• CBR of the subgrade is satisfying the minimum requirements, a further depth of 15cm of the
existing subgrade shall be scari ed, watered, mixed as necessary and compacted to not less
than 95% of maximum dry density.
• All slopes, lines and grades shall be true, correct and accurate, and according to latest
approved shop Drawings.
• The subgrade level in cuts shall be accurate to the authorized pro le grade to plus or minus
two (2) centimeters and, for 'top of improved subgrade' level, plus or minus one (1) centimeter.
• During the construction of the roadway, the prepared formation shall be maintained in such
condition that it is well drained at all times.
• The material for improved subgrade shall be approved soil with a plasticity index not
exceeding 6 and liquid limit shall not exceed 40%.
• Dune sand if used shall not contain more than 2% organic matter and may contain up to 20%
of stone fragments or cobbles exceeding 20mm but not more than 63mm in size.
• For every completed layer of subgrade, three eld density tests shall be performed on each
unit of carriageway. (One unit being 1500 Sq.m).
4. Subbase Construction:
• Road sub-base material shall be delivered to the roadbed as uniform mixture and shall be
spread in layers.
• Segregation shall be avoided, and the sub-base shall be free from pockets of coarse or ne
materials.
• Each road sub-base layer shall be spread by nisher and or grader or other approved
mechanical methods, watered, shaped to a compacted thickness not exceeding 150 mm and
compacted to the required grade and cross- section.
• Compaction test requirements can be achieved in layers exceeding 150mm but not more than
170mm.
• Compaction shall be accomplished over the full width of each layer by compacting from the
sides to the center, parallel to the centerline of the road.
• Along curbs, headers, walls, and all places not accessible to the roller, compact the material
with approved vibratory rollers or compactors.
• At the time of compaction, the moisture content of the laid material shall not vary by more
than + 2 % from the optimum moisture content.
• The nished surfaces of the road sub-base shall not vary at any point more than 10 mm above
or below the grade.
• A minimum of four in-situ density tests shall be made in every lot (approximately 1500 sq.m)
of granular sub-base laid or as directed by the Engineer.
• This work shall consist of furnishing and placing one or more courses of aggregate, including
binder soil if required, on a prepared subgrade or sub-base conformity with the lines, grades
thickness and typical cross-section as per approved IFC drawing.
• All aggregate road base material shall be free from dirt, shale or other deleterious matter and
shall be of such quality that it will bind readily to form a stable aggregate road base.
• Aggregate road base shall be spread on subgrade or sub-base which has been approved.
• The material shall be spread using a motor grader operated with a mechanism which levels off
the material at an even depth and without delay.
• The road base aggregate course shall not be placed when the underlying surface is muddy, or
when it is raining or dusting.
• Aggregate road base shall be spread by nisher and or grader or other approved mechanical
methods, watered, shaped to a compacted thickness not exceeding 150 mm.
• The moisture content of the aggregate road base material shall be adjusted prior to
compaction, by watering with approved sprinkler trucks or by drying out.
• Aggregate road base shall be compacted to not less than ninety-eight (98) percent of the
maximum dry density.
• Rolling shall continue until the entire thickness of each layer is thoroughly and uniformly
compacted to the speci ed density.
• The surface of the material shall on completion of compaction be well closed, free from
movement under the compaction plant and free from compaction planes, ridges, cracks, or
loose material.
• The surface of the nished aggregate road base will be tested with a three-meter straightedge
by the Engineer at selected locations.
• The variations of the surface from the testing edge of the straight edge between any two (2)
contacts with the surface shall at no point exceed ten (10mm) when placed on or parallel to the
center line or ten (10mm) when placed perpendicular to the center line of the roadway.
• The aggregate cross section as shown on the Drawings shall not vary by more than ten (10)
millimeters from the required elevation.
• Protect all sections of newly compacted pavement from tra c until they have hardened
su ciently to the approval of the consultant and client.
Asphalt mix plant shall be approved by consultant and client and asphalt / bituminous Base
Course and surface course / wearing Course Job Mix shall meet the Project Speci cations, and
to be approved by consultant and client prior to starting the works.
8. Preparation:
• Ensure that the area to receive for asphalt surfacing shall be inspected approve by the
consultant and client.
9. Prime coat:
• A prime coat bitumen (MC-70) shall be applied over the Aggregate Road Base at a rate of
between 1.13 to 2.26 liters per square meter. At least 48 hours curing time shall be maintained
before starting asphalt works.
• Compaction of the bituminous material will be achieved using steel wheel tandem vibratory
rollers and pneumatic tire rollers.
• Initial compaction or breakdown rolling will be by a tandem vibratory roller operating in the
static mode.
• Subsequent compaction will be carried out using tandem vibratory rollers minimum 3 passes
(in the vibratory mode) and followed by pneumatic tire rollers until the material has been fully
compacted to achieve the required degree of compaction as per project speci cation.
• A nal ‘ nishing’ roll will be carried out using a tandem vibratory roller in the static mode to
remove any remaining roller marks.
• Before laying surface / wearing course layer a tack coat of bitumen emulsion will be applied to
a clean surface at a rate of between 0.23 to 0.68 liters per m². The emulsion shall be allowed to
break prior to commencing surfacing.
• The compacted thickness of bituminous surface / wearing Course shall be as per approved
shop drawing and project speci cation.
Download the Free Guide Learn More
• The bituminous material will be laid using paver.
• Compaction of the bituminous material will be achieved using steel wheel tandem vibratory
rollers and pneumatic tire rollers.
• Initial compaction or breakdown rolling will be by a tandem vibratory roller operating in the
static mode.
• Subsequent compaction will be carried out using tandem vibratory rollers minimum 3 passes
(in the vibratory mode) and followed by pneumatic tire rollers until the material has been fully
compacted to achieve the required degree of compaction as per project speci cation.
• A nal ‘ nishing’ roll will be carried out using a tandem vibratory roller in the static mode to
remove any remaining roller marks.
• Where practicable the paving machine will be equipped with automatic level sensing
equipment and / or averaging beam (dependent upon location), referenced to dipped levels
obtained from steel pins kerbs or other suitable datum at no more than 10 meter longitudinal
intervals, and transversely at intervals commensurate with the required mat widths.
14. Testing:
• Bituminous materials will be delivered to site within the temperature range 139 to 163OC as
Download the Free Guide
per project speci cation. Material delivered to site outside range will not be incorporated within
Learn More
the works.
• Temperatures will be checked and recorded both at the depot mixing plant and the point of
laying by either electrical probes pyrometers or conventional thermometers.
• Bituminous materials will be sampled at site as per project speci cation and testing of
bituminous mixing for speci cation compliance with respect to aggregate gradation binder
content and Marshall Design properties as per project speci cation.
• Sections of completed pavement layers will be cored on site as soon as practicable for testing
for eld density compliance as per project speci cation.
• When all the activities are completed, the area will be cleaned thoroughly. Once the cleaning is
done and approved, a "Request for Inspection" will be raised for acceptance.
• Safety assistant are allocated all the site locations to maintain housekeeping.
All crane lift operations shall be provided with a crane lift plan prepared by a competent person
before commencing of lift and shall be communicated to all parties involved in the lift
operation. Generator for electricity shall be provided with drip tray to control any spillage. Upon
arrival SAB safety o cer shall conduct inspection for each equipment and document all the
inspections for records. Each equipment shall be arranged with complete le for all
certi cations. After approval the equipment shall be allowed to site for work. Following remain
outlined to focus:
• The capacity / size of the tools and equipment will be judged in accordance with site
conditions, requirements, and availability at the time of execution.
• Fuel shall be provided by mobile fuel tanker on daily basis for the equipment on site.
• The refueling and maintenance will be carried out in the designated location.
13. Hand Tools - Rakes, shovels, hand compactors, levelling and smoothing tools, Pavement
saw machines, heaters, cleaning tools, hand brooms, small vibratory compactors, liquid asphalt
painting, and all other tools that may be needed
Note: Above listed equipment shall be assigned as per requirements of each work during the
mobilization stage
The safe storage of hazardous chemicals is an essential part of an environmental, health, and
safety program. Chemical storage facilities must meet certain minimum standards to satisfy
Download the Free Guide
diverse regulations, store must observe several requirements that incorporate safe storage: Learn More
• Keeping an up-to-date chemical inventory
• Proper chemical labelling
Conclusion:
Full article on Method Statement for Road and Paving Works | Method Statement for Asphalt
Road Construction | Work Methodology for Road Construction | Method Statement for Asphalt
Road Construction | Work Method Statement for Road Construction | Method Statement for
Construction of Road | Road Construction Method Statement. Thank you for the full reading of
this article in "QA QC Civil Engineering" platform in English. If you nd this post helpful, then
help others by sharing it on social media.
Facebook Twitter
QA QC Civil Engineering
Hi I am a Civil Engineer by profession but I’ve specialized and taken the journey in the eld of
Quality Engineering, QA/QC Civil Engineering, Bar Bending Schedule, Quantity Surveying,
Construction, Concrete Works, Estimating & Costing and AutoCAD Civil 3D.
Download the Free Used Equipment for Roof Edge Pdf document note
Guide Sale Protection For Sale icon in at style. Pa
Solar Backup Battery Download Register for the Free Looking for
System PowerPoint Course inverter ?
Templates
Post a Comment
Enter Comment
Download the Free Guide Learn More
Previous Post Next Post
PerkinElmer®
ABOUT US
QA/QC Civil Engineering helps professionals from construction industry to get
regular feeds on Quality Control, Quality Ensure, Quantity Surveying, Estimation and
Costing, Land Surveying, Concrete, Bar Bending Schedule, AutoCAD Civil 3D and
information about global megaprojects, job opportunities industry insights as well as
events; conferences from Construction site.
Copyright © 2022 - QA/QC Civil Engineering | Quality in Construction Home About Us Privacy Disclaimer Terms and Conditions Contact Us