Project Planning phase

Prepare Milestone and Activity List

Date 31 October 2022


Team ID PNT2022TMID23203
Project Name Traffic and Capacity Analytics
for Major Ports
Maximum Marks 4 Marks
DATE MILESTONE ASSIGNEE STATUS DESCRIPTION

31/08 Data Collection-Download dataset Sudharsan R Completed The dataset for Traffic and Capacity
Aravinth P Analytics is to be collected.The dataset
Arun Sundar K which is considered will have the port
Mohith Veereshwar K information

7/09 Data Pre-processing Sudharsan R Completed Preprocessing involves renaming the


1.Renaming the coloumn names Aravinth P existing coloumn names into meaningful
2.Preparing calculations Arun Sundar K one,preparing calculations such as
3.Checking for NULL values Mohith Veereshwar K calculating traffic percent,checking for
4.Checking for ouliers NULL values in the dataset.
5.Summarization of dataset
6.Label Encoding
14/09 Visualizing the dataset Sudharsan R In-Progress Visulaizing the dataset involves plotting the
Aravinth P dataset using various plots and doing
Arun Sundar K analysis on that.
Mohith Veereshwar K

21/09 Model Building Sudharsan R In -Progress Using certain algorithms to build the model.
1.Building the model using suitable machine Aravinth P Those algorithms include
learning algorithm Arun Sundar K 1.Linear regression
2.Training and testing the model Mohith Veereshwar K
28/09 Dashboard Creation Sudharsan R In-progress Dashboard for visualizing the port status
Aravinth P will be developed.
Arun Sundar K
Mohith Veereshwar K

7/10 Ideation Phase Sudharsan R Completed Start the ideation process


1. Litreature survey on the selected project and Aravinth P
information gathering. Arun Sundar K
2. Prepare the empathy map. Mohith Veereshwar K
3. Ideation

10/10 Project Design Phase -1 Sudharsan R Completed Prepare the proposed solution document,
1. Proposed solution. Aravinth P which includes the novelty, feasibility of
2. Prepared fit solution Arun Sundar K idea, business model, social impact,
3. Solution Architecture Mohith Veereshwar K scalability of solution, etc.

12/10 Project Design Phase -2 Sudharsan R Completed Prepare the customer journey maps to
1. Customer journey. Aravinth P understand the user interactions &
2. Functional requirements Arun Sundar K experiences with the application (entry to
3. Data flow diagram. Mohith Veereshwar K exit) ,Functional requirements and construct
4. Technology architecture architecture

31/10 Project Planning Phase Sudharsan R Completed Prepare milestone activity list and sprint
1.Milestone Activity List Aravinth P delivery plan for outline of work flow
2.Sprint Delivery plan Arun Sundar K
Mohith Veereshwar K

02/11 Project Development Phase Sudharsan R In-Progress Plan of each task sprint to be developed.
1.Sprint -1 Aravinth P
2.Sprint-2 Arun Sundar K
3.Sprint-3 Mohith Veereshwar K
4.Sprint-4
Milestone 1
31/08 Milestone 7
10/10
Milestone 3
Milestone 9
14/9
31/10
Milestone 5 Project
28/09 Complete
05/11

Milestone
10 02/11

Milestone 2 Milestone 6
07/09 7/10

Milestone 4 Milestone 8
21/9 12/10