Professional Documents
Culture Documents
Location
Zhengzhou East High-
Status &
Operation
Speed Rail (HSR) Station
China Railway High-speed trains, which move at a top speed of roughly 350
km/h, reduce the journey from Zhengzhou to Xi'an from more than 6 hours to under 2
hours. The Chinese government is constructing eight separate passenger railway
systems, the first of which is this new and innovative railway system. Under the
projected east plaza, Zhengzhou Metro Line No. 1's two 6-m-diameter shield tunnels
were built near the Zhengzhou East High-Speed Rail (HSR) Station. The fragile soil on
the Loess Plateau in northwestern China must be strengthened to install the train lines
Slide 3
Project
Name
Western China (Zhengzhou & Xian)
Location China China China
Status &
Province of passes through high-speed
Operation
Zhengzhou and ten railway railway
Xian stations signaling and
communications
Project
Name
ZHENGZHOU EAST HIGH-SPEED RAIL (HSR) STATION
Location
The project constructed a new railway network that started in September 2005, was
completed in December 2009 and transferred to the trial run stage. The initial trial
operation is scheduled to be carried out from February 2010 to February 2011.
Slide 5
Excavation close to the existing shield tunnel often leads to impacts on the
stability of the tunnel. However, interventions committed to mitigating the impacts may
not be effective in preventing tunnel movement or deformation from occurring.
Many facilities, including the subway system and standard underground facility
tunnels, were developed in China's crowded megacities, claimed Shen et al. (2017).
Several underground structures need to be done above or close to already-existing
tunnels. Around existing tunnels, weak soil restoration techniques like jet grouting may
also be performed. When groundwater pumping is done close to tunnels, it concerns the
stability of the tunnels is at risk because these surrounding projects will induce the uplift
and deformation of the tunnels (Cheng et al., 2018). Liao and his colleagues' research
looked at the structural stresses and asymmetrical deformations caused by nearby
excavations on existing metro stations. They observed that the bending moments in
significant parts measured with the proportion of the range from the established railway
station to the excavation depth could be altered. They also discovered that the rotation
and shear effects of an existing railway station influenced by the nearby digging could
also vary and be reversed (Liao et al., 2016).
Slide 6
The objective of this work is on the uplift and deformation attributes of two shield
tunnels of Zhengzhou Metro Line No. 1. The geological analysis enables one to convey
the outcome of two shield tunnels to surface-dumped soil, disposal of discarded soil,
and two neighboring excavations, to conduct a study and understand their effects on the
tunnel uplift and deformation, and to evaluate the effectiveness of the rectifications
adopted and choose the best construction strategy.
Slide 7
Implications REMEDIAL
GROUTING
MINIMIZE RISKS
Possible NUMERICAL
Ways
SIMULATION
In order to help the decision-making process during construction, the tunnel uplift
and deformation were described following the field measurements and numerical
modeling based on the project's geological, construction, and environmental
information. Ballast separation, joint leakage, and lining cracking were caused by the
elevation and deformation of the tunnel. Gaps or cavities were then created beneath
due to the ballast separation. To ensure the water tightness of the tunnel lining, epoxy
resin and polyurethane were used to repair lining cracks and joint leaking, respectively.
The holes or voids created by the separation of the ballast had to be filled with cement
mortar. The corrections successfully kept the tunnel functioning without any subsequent
disruptions.
Slide 9
Measures
Two shield tunnels connect between two digging holes that are part of the east
square of the current Zhengzhou East High-Speed Rail (HSR) station, and a case study
showing how to characterize shield tunnel uplift and deformation to prevent tunnel
movement and deformation was addressed:
First, three rows of tieback are subsequently dug in each excavation pit before
the diaphragm wall restrains the peripheral top-down pit. The center down-top pit is then
placed and uses a sequence of bored piles. The tunnels' total uplift and lateral
deformation measurements were 22.9 mm and 77.9 mm, respectively, as the two
excavations descended to their full depth of 19.3 m.
Second, ballast separation, lining cracks, and joint leaking were also identified in
the tunnels. The analysis is done on how each step of construction affected the
elevation and deformation of the tunnel. The feasibility of the corrective measures is
evaluated, and the lessons learned are compiled to prevent a future occurrence of the
same incident.
Slide 10
Measures
1) The east square construction has greatly raised the shield tunnels by 22.9 mm and
warped them by 77.9 mm. The installation of bored piles fixed to wale bands and the
building of soil mixing piles (SMP) were the primary causes of tunnel deformation. In
contrast, removing dumped soil and pit excavations were the critical factors in tunnel
uplift.
(2) In addition to limiting grout movement, quick-setting grout was used to minimize the
formation of extra excess pore water pressure during injections. It was observed that
the two rows of sleeve pipe, for which the injection pressure was set at 0.1-0.15 MPa for
the inner pipes and 0.25-0.3 MPa for the outer pipes, and the quick-setting grout were
efficient in restraining the tunnel deformation from escalating.
In order to evaluate these incidences among various construction options and reduce
the danger of tunnel movement, two shield tunnels that impacted geological tunnels are
analyzed for their contributions from each stage of development to the tunnel elevation
and deformation. Impact minimization has been deemed crucial, particularly for the
operation of metro tunnels. With the help of this risk assessment framework, planners
and engineers can effectively evaluate and reduce the inherent risks connected to the
rotation and shear effects of an existing metro station caused by the excavation nearby.
These risks vary with the distance from the existing subway station to the tunnel
construction.
Slide 12
Lessons
Photos
References
The two photos above are of the railway system of Zhengzhou East High-Speed Rail
(HSR) station. The two photos below are the processes of pit excavation, remedial
grouting, and surface reloading, and tunnel stabilization.
Slide 13
REFERENCES
Lessons
Cheng, W., Song, Z., Tian, W., & Wang, Z. (2018). Shield tunnel uplift and deformation
characterisation: A case study from Zhengzhou metro. Tunnelling and Underground Space
Technology, 79, 83-95. https://doi.org/10.1016/j.tust.2018.05.002
Photos
Environmental Monitoring Report. (2011). Environment Monitoring Report. Upon Zhengzhou-Xian
Railway of Passenger Special Line Newly Built by Using Asia Development Bank Environment
Monitoring Report upon Zhengzhou-Xian Railway of Passenger Special Line in 2010 (pp. 1-38). The
Third Railway Survey and Design Institute Group Corporation.
References
Liao, S. M., Wei, S. F., & Shen, S. L. (2016). Structural responses of existing metro stations to adjacent
deep excavations in Suzhou, China. Journal of Performance of Constructed Facilities, 30(4), 04015089.
Shen, S. L., Wang, Z. F., & Cheng, W. C. (2017). Estimation of lateral displacement induced by jet
grouting in clayey soils. Gé otechnique, 67(7), 621–630. doi:10.1680/jgeot.16.p.159
Slide 14
Thankyou,
Any Question?