Professional Documents
Culture Documents
ABSTRACT: When a project includes two parallel tunnels, cross passages linking both tunnels are
normally constructed for safety reasons during tunnel exercise. Design and construction of the cross
passages is a challenging issue in tunnelling design. Excavating cross passages through rock, soft
ground, and mixed face conditions presents very different challenges as well as handling
groundwater creates additional difficulties. Excavation of the main running tunnels, having a
relatively larger dimension compared to the cross-passages, usually involves in the use of full-face
mechanized excavation to mitigate the impacts of difficult subsurface conditions. For cross passages,
access is usually limited, excavation is implemented through traditional methods preceded by
treatments if required. Different scenarios were selected and afterwards by changing the geometrical
data of main tunnels, cross-passage, overburden and geotechnical parameters, a series of three-
dimensional numerical analyses (FLAC 3D) were performed. The aim of this ongoing parametric
study is to obtain some abacuses useful in engineering practice.
2 NUMERICAL MODELLING
2.1 Model specifications and excavation
procedure Segmental
To evaluate the influence of the cross cut lining
excavation on the external environment, a fully
parametric model was developed using
FLAC3D (Itasca, 2006) to study displacements TBM
and stresses around twin tunnels and cross shield
passage. Parametric analysis was carried out
assuming Mohr-Coulomb criterion and total
stress approach with focus on short-term
stability, using a frictionless material (=0) with Backfilling
the undrained shear strength (cu)wich cohesion injection pressure
and elasticity modulus are changing with depth Face
as well as frictional soil with constant both pressure
friction angle and elasticity modulus. The tunnel
intersection geometry involves two parallel Figure 3. The used step-by-step pressure method for
main tunnels connected by a smaller cross shield tunnelling advancement.
passage obtained with a service tunnel, as
shown in Figure 2. All three tunnels are of Cross passages excavation procedure was
circular shape and the main tunnels have the simulated following open face tunnelling step-
same diameter (D). by-step method (Hanafy and emery, 1980). In
this method, at all the calculation steps, ground
elements inside the cross passage are removed
to simulate an unsupported excavation with a
particular round length, with diameter of 4m,
and in the same phase a ring of new lining
L=100m elements is installed to support the previous
excavation phase. These calculation phases are
repeated in steps until the excavation of cross
passage is completed (Floria el al., 2009;
Daneshmand et al., 2013).
H=5D
2
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Figure 6. Effect of cross passage advancement on z- Figure 9.Surface settlement for different geologies,
displacement above its centerline for cohesive soil frictional soils, geometry base data: H=2d, D=2d.
(case C=40+3z) , geometry base data: H=2d, D=2d.
Effect of different geologies and geometries
on surface settlement is summarized in the some
figures. As an example, Figure 10 presents the
maximum surface settlement for cohesive soil,
above main tunnels at cross passage cross
section before and after cross passage
excavation are presented.
1 1
k , a , (2)
x y
cu cu
Where cu is soil cohesion [kPa], x and y are
constant values function of soil cohesion that
can be calculated with equations (3).
75 c u 81 c u
x 1.380 , y 1.236 , (3)
105 105
Figure 12.Surface settlement above cross passage
As it is shown in Figure. 10, obtained trend centerline for different geometries and cohesive soils
lines for induced surface settlement before and before and after cross passage excavation, D=5d.
after cross passage excavation above main tun-
Following the same approach, effect of
nels are practically parallel. Therefore it is pos-
different geologies and geometries on surface
sible to obtain a formula providing the surface
settlement for frictional soil was studied and the
settlement increment due to cross passage exca- same graphs for frictional soils are presented in
vation as a function of soil cohesion as present- Figures 13 and 14. As shown in these figures,
ed in equation (4): obtained trend lines for frictional soils behave
2.81 0.02cu , (4) similar to those of cohesive soils.
linings for cohesive and frictional soils were improving the soil characteristics, induced
studied. According to this study, Induced bending moment increases while axial force
bending moment and axial force at the wall of decreases as well as with increasing main
first main tunnel lining at conjunction with cross tunnels interval, the induced bending moment
passage increases with increasing the decreases while axial force increases. The
overburden and main tunnels interval. With percentage of these changes depends on the
improving the soil characteristics, induced amount of changes on those parameters. Since
bending moment decreases while axial force these effects are more significant at tunnel
increases. Induced bending moment and axial crown, related graphs for tunnel crown for
force at the crown of this cross section, cohesive soils are presented in Figure 15.
increases with increasing the overburden. With
Figure 15. Comparison of bending moments, left side, and axial forces, right side, for model with different cohesive soils
and geometries at main tunnel crown after cross passage excavation
6
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Figure 16. Comparison of bending moments, left side, and axial forces, right side, for model with different frictional soils
and geometries at main tunnel crown after cross passage excavation
The effect of cross passage excavation on Table 1.Variations of induced stresses inside first main
induced bending moment and axial force at the tunnel lining due to cross passage excavation.
wall of main tunnel lining at conjunction with Parameter Soil Main tunnel Main tunnel
cross passage for the same geology was condition wall crown
evaluated. By excavating the cross passage, the Cohesive Decrease Increase 20-
Bending soil 8% 40%
induced bending moment decreases and this Frictional Increase Negligible
moment
reduction value is decreased as the main tunnel soil 11% variations
interval increases for both frictional and
cohesive soils. Furthermore, the effect of cross Cohesive Increase Decrease
Axial force soil 11% 7%
passage excavation on induced bending moment Frictional Increase Decrease
and axial force at the crown of this cross section soil 13% 20%
for the same geology, for both frictional and
cohesive soils, was evaluated. The percentage of Since these effects are more significant at
induced stresses variations inside the first main tunnel crown, Related graphs for tunnel crown
tunnel lining at conjunction with cross passage are presented in Figure 17 for cohesive soils and
is presented in Table 1. Figure 18 for frictional soils.
7
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Figure 17. Bending moments, left side, and axial forces, right side, at the crown of first main tunnel lining for different
geometries, before and after cross passage excavation, Case C=90+3Z.
8
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Figure 18. Bending moments, left side, and axial forces, right side, at the crown of first main tunnel lining for different
geometries, before and after cross passage excavation, Case =40˚.
Figure 19. Effect of cross passage advancement on stress distribution inside first ring of cross passage lining for cohesive
soil, C=40+3Z, and frictional soil, =40˚.
9
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
The induced bending moment and axial force axial force increases. The percentage of these
of the second main tunnel lining at conjunction variations is presented in Table 3.
with cross passage were also studied. The in-
duced bending moment and axial force at the Table 3.Variations of induced stresses inside second main
tunnel lining due to terminal steps of cross passage
crown of this cross section do not show any sig- excavation.
nificant changes during primary steps of cross
passage excavation while as the cross passage Parameter Soil Main tunnel Main tunnel
condition wall crown
excavation advances and cross passage becomes Cohesive Increase 13 Increase
closer to the second main tunnel, the bending Bending soil times 83%
moment at tunnel crown increases during termi- moment Frictional Increase Increase
soil 62% 20%
nal steps of cross passage excavation while the
axial force decreases as shown in Figure 19. Cohesive Increase Decrease
This effect on the left wall of second main tun- Axial force soil 23% 11%
nel lining which is adjacent to cross passage and Frictional Increase Decrease
soil 25% 5%
is demolished during the last step of cross pas-
sage excavation was evaluated: during primary The induced bending moment and axial force
steps of cross passage excavation does not show at the right wall of the second main tunnel lining
any effect on stress distribution while as the at conjunction with cross passage which is at the
cross passage excavation advances and during opposite side of cross passage conjunction with
terminal steps of cross passage excavation, the main tunnel, do not change significantly during
bending moment and axial force inside left wall the advancement of cross passage excavation.
of tunnel lining increases significantly while the
Figure 20: Effect of cross passage advancement on stress distribution inside second main tunnel lining at conjunction
with cross passage for cohesive soil, C=40+3Z, and frictional soil, =40˚.
REFERENCES
11