You are on page 1of 12

Subsidence owing to tunnelling. I.

Estimating the gap parameter


K. M. LEE,' R. KERRYROWE,AND K . Y. LO
Geotechnical Research Centre, Faculty of Engineering Science, The University of Western Ontario,
London, Ont., Canada N6A 5B9
Received April 3, 1991
Accepted June 1, 1992

A simple, numerically based procedure for the estimation of the so-called gap parameter is described. The gap parameter
represents the vertical displacement above the crown of the tunnel and is a measure of ground loss owing to tunnelling
in soft ground. This parameter is a function of the three-dimensional elastoplastic deformation at the tunnel face, the
tunnelling machine shield and lining geometry, and workmanship. This parameter can then be used to predict the resulting
ground deformations using either two-dimensional finite element methods or empirical correlations.
Key words: tunnelling, settlement, subsidence, clays, soft ground, analysis, design.

Une procedure simple a base numerique pour estimer le paramktre nommC gap est dicrite. Le paramitre gap reprisente
le deplacement vertical au-dessus de la voiite du tunnel et est une mesure de la perte de sol due au creusage de tunnel
dans le sol mou. Ce paramktre est fonction de la deformation Clastoplastique tridimensionnelle a la face du tunnel,
de la geometric du bouclier du tunnellier et de la garniture, de m&meque de la qualite de I'exCcution. Ce paramktre
peut alors Ctre utilise pour pridire les deformations resultantes du sol au moyen soit de mithodes dlCICments finis bidimen-
sionnelles, soit de correlations empiriques.
Mots clPs : percement de tunnel, tassement, affaissement, argiles, sol mou, analyse, conception.
[Traduit par la redaction]

Can. Geotech. J. 29, 929-940 (1992)

I
Introduction rational design procedure for estimating the gap parameter
I
It is well recognized (Peck 1969) that the deformations is needed.
caused by tunnelling (and the consequent potential damage The purpose of this paper is to develop a simple design
to adjacent and overlying services and structures) will depend procedure for estimating the gap parameter for tunnels
I on (i) the ground and groundwater conditions, (ii) the excavated in soft clayey soils under undrained conditions.
tunnel depth and diameter, and most importantly (iii) the This improved procedure is based on the results of three-
I
construction details. Empirical procedures (Peck 1969) have dimensional (3D) elastoplastic finite element analysis (see
been widely used to assess potential ground movements Lee and Rowe 1990a, 1990b) and extends earlier work
owing to tunnelling. When applied with appropriate judge- reported by Lo et al. (1984). The procedure only involves
ment based on similar past experience, these procedures can simple equations and conventional soil properties, hence
yield adequate and economical designs. They are, never- these methods may be readily applied in design analysis of
theless, subject to some important limitations; first, in their tunnels in clays. This gap parameter can then be used in con-
applicability to different tunnel geometries, ground condi- junction with two-dimensional (2D) finite element analyses
tions, and construction techniques, and secondly, in the (e.g., see Rowe et al. 1983) to predict the resulting undrained
limited information they provide concerning the distribu- ground deformations. A companion paper (Rowe and Lee
tion of settlement other than at the surface. 1992) evaluates the validity of the proposed design guideline
A theoretically based method for the prediction of settle- by comparing the calculated and measured ground displace-
ments at the surface and at various depths has been sug- ments for several case histories.
gested by Lo and Rowe (1982) and Rowe et al. (1983). An
important aspect of this approach is the introduction of a Simulation of loss of ground: the gap parameter
parameter, called the gap parameter, which takes into
account the ground loss as a function of strength and defor- Excavation of the tunnel provides an opening into which
mation behaviour in the elastic and plastic state, physical the soil can deform and the constraint to soil movement is
clearance between the excavated diameter and lining, and primarily a function of the machine characteristics,
workmanship. It has been found that the method yields workmanship, lining geometry, and lining flexibility. The
settlement profiles that are in reasonable agreement with movement of the soil into the opening can be related to the
field measurements in several well-documented case histories concept of "loss of ground," which is defined as volume
(Rowe and Kack 1983; Ng et al. 1986), provided that the of material (whether through the face or radial encroach-
gap parameter is correctly chosen. It should be noted that ment over and around or behind the shield) that has been
in the previous investigations the so-called gap parameter excavated in excess of the theoretical design volume of
was estimated largely based on engineering judgement. To excavation. Field studies (Peck 1969; Cording and Hansmire
readily apply this approach in engineering applications, a 1975) have highlighted the 3D nature of the problem and
the effect of 3D ground loss on the subsequent deforma-
'present address: Department of Civil and Structural Engineer- tions. Based on field case histories, the loss of ground can
ing, Hong Kong University of Science and Technology, be considered to occur in three stages as the tunnel advances
Hong Kong. in the soil mass: (1) ahead of the face, (2) over the shield,
Printed in Canada / lmprimt au Canada
CAN. GEOTECH. J. VOL. 29, 1992
1
G
C GAP=Gp

*
SHIELD LINING

Case ( i ) Tunnel advances in perfect alignment and fully supported at the face
GAP=G +u*
P 30
GAP

Case ( i i ) Tunnel advances in perfect alignment but allowing full stress releases
at the face

GAP=G +u* + w
3D
GAP
I

Case ( i i i ) Tunnel advancement is subjected to all possible sources of "ground


loss" including overexcavation due to workmanship problem
FIG. 1. Simulation of loss of ground. The total gap parameter.

and (3) upon the erection of the lining. It is further con- air is used to minimize stress changes and deformations into
sidered that additional loss of ground may result from creep, the face, and the tunnel is advanced under perfect alignment,
consolidation, and (or) a long-term change in hydraulic the gap parameter is equivalent to the physical gap (G,),
conditions. which is defined as the vertical distance between the crown
Three-dimensional finite element analysis such as that of the tunnel lining and the crown of the excavated surface
described by Lee and Rowe (1990a, 1990b, 1991) can be used prior to removal of the tunnel tractions (schematically rep-
to predict the spatial 3D ground displacements within the resented as the term G , in case i of Fig. 1). If less conser-
soil mass. However, because of the high cost and process- vative construction procedures are adopted, 3D movements
ing time associated with this analysis, simplified 2D proce- ahead of the tunnel heading may be significant (represented
dures are usually adopted. For the purpose of performing as u * in~ case~ ii of Fig. 1). Similarly, construction dif-
a two-dimensional plane strain analysis, the components of ficulties such as steering and alignment problems with the
loss of ground discussed above may be represented quan- tunnelling shield can cause over-excavation and (or)
titatively in terms of the so-called gap parameter. Thus the remoulding of the soil adjacent to the tunnel (represented
gap parameter is a measure of various components of lost as workmanship parameter w in case iii of Fig. 1). These
ground into the tunnel as illustrated in Fig. 1. Under movements can be approximately incorporated in the 2D
idealized construction conditions in which the tunnelling plane strain model by assuming a slightly larger excavated
machine is kept hard against the face and (or) compressed tunnel diameter, with an additional volume corresponding
r
I n i t i a l P o s i t i o n o f P o i n t s on What W i l l
Become t h e Crown A f t e r E x c a v a t i o n
A = Thickness of$ Ta1 l p ~ e c e

ection o f Lining

S i m u l a t e d Tunnel
I
I
I
I
Tunnel Heading
2D Plane S t r a i n
Representation o f
Tunnel Heading

FIG. 2. Definition of GAP (modified from Lo et al. 1984). The gap parameter is given in [I].

to the volume of ground lost through the heading and over described by Lee and Rowe (1990a) and will not be repeated
the shield (as shown in Fig. 2). Thus, the gap parameter herein.
(GAP) can be considered as the maximum settlement at the In this study, the effect of plasticity, for a given geometry,
tunnel crown, and it may be expressed as is examined by considering a number of values of undrained
shear strength c,. The elastic Young's modulus profile with
[I] GAP = G, + +w depth (E") adopted in the analysis is similar to that adopted
where G , = 2A + 6.The physical gap (G, = 2A + 6) by Lee and Rowe (1990b) and involves a Eu/cu ratio in the
represents the geometric clearance between the outer skin range of 200-800. The vertical initial stress is assumed to
of the shield and the lining, and it is composed of the be due to the weight of the overburden with a unit weight
thickness of the tailpiece (A) and the clearance required for of soil of 20 k ~ / m and ~ , the in situ initial stress ratio is
erection of the lining (6). The term represents the assumed to be unity. Since only the undrained behaviour
equivalent 3D elastoplastic deformation at the tunnel face. of the soil mass is considered, there is no plastic volume
The term w takes into account the quality of workmanship. change.
Analyses were performed to study the 3D behaviour of
Method of analysis and principal assumptions the soil mass due to excavation of a tunnel of diameter D
at tunnel cover depths, H (distance from ground surface to
In the present study, 3D elastoplastic finite element anal- tunnel springline), of 1.5 to 4.5 D. In this paper, only sum-
ysis is used as a tool to develop a simple design procedure marized results will be presented; detailed results of anal-
for estimating the gap Parameter for tunnels excavated in yses for various geometric and ground conditions were given
cohesive soils. The finite element mesh adopted in the pres- elsewhere (Lee 1989).
ent study consisted of about 4800-6000 elements d e ~ e n d -
ing on the geometry of the problem. Eleven-noded, noicon-
forming brick elements were used to discretize the soil. This Excavation simulation
nonconforming element is very similar to the 8-noded linear The method of excavation and support that is usually
Lagrangian element, except it has three auxiliary internal employed in soft ground consists of mechanical excavation
incompatible displacement nodes to improve the field vari- followed by immediate erection of a tunnel lining within the
able representation within an element (see Lee and Rowe tailpiece of a protective shield. In finite element analysis,
1990a, for details). this construction process can be simulated by deducing the
It should be noted that the proposed design procedure is tractions that would be acting around the surface of the tun-
only applicable for predicting settlement owing to various nel (prior to excavation) and then removing those tractions.
sources of ground loss in an undrained state for saturated This approach is valid for all values of the coefficient of
cohesive soils; it does not consider consolidation resulting earth pressure at rest (KO) (e.g., see Kulhawy 1974) and is
from the stress changes around the tunnel or reconsolida- considered to provide a reasonable approximation of the
tion of any remolded zone that results from the tunnelling change in stress that occurs with the advance of the tunnel-
process. These effects have been discussed briefly by Ng ling machine.
et al. (1986). Once the soil clears the tailpiece of the tunnel shield, soil
The soil is assumed to have an elastic - perfectly plastic would invade the tail void behind the shield and the weight
constitutive relationship which (for undrained conditions) of the lining will cause it to rest on the excavated surface
was defined by a Tresca failure criterion and a flow rule of (as shown in Fig. 2), while the lining will limit the possible
the form proposed by Davis (1968). Details regarding this deformations of the soil. The tail void left behind the tail
form of the soil model, the choice of finite element, the con- skin can be represented by a diameter of the circular open-
struction simulation, and the solution technique have been ing in the finite element mesh slightly larger than the diam-
932 CAN. GEOTECH. J. VOL. 29, 1992

eter of the lining. The tail void itself is nonuniform in shape tions of soil parameters and tunnel geometries. Results from
(Fig. 2), with a zero thickness at the tunnel invert. By defini- these analyses indicate that the kl paraheter is generally in
tion, the difference between these two diameters is repre- the range of 0.7-0.9. It should be noted that analyses per-
sented by the so-called gap parameter as described by [I]. formed by Lee (1989) did not consider the shoving forces
In the present analysis, tractions to simulate the excava- generated by the advancing shield. Peck (1969) indicated that
tion process are determined by the procedure proposed by the frictional forces between the skin of the shield and the
Brown and Booker (1985). This approach ensures that total surrounding soil caused by the shoving action of the shield
equilibrium is always satisfied and, depending on the can develop longitudinal tensile stresses in the clay that may
magnitude of in situ initial stresses, nonuniform tractions tend to cause failure and plastic flow of the clay into the
around the tunnel periphery will generally result. These tunnel face and the annular void between the tail skin. These
deduced tractions are then removed from the tunnel open- frictional forces were not simulated in the analysis; how-
ing periphery in increments. The displacements at all nodes ever, if this effect was simulated, a more uniform soil intru-
on the periphery are monitored; if the displacement of a sion across the tunnel face would be expected. In design
node indicates that the gap has closed at that point, then situations, a value of kl = 1 would appear to be reason-
the soil-lining interaction proposed by Rowe el ul. (1983) able. Therefore, [2] can be simplified as
is activated. It should be noted that once the soil comes into
contact with the lining, its movements are constrained by
the lining and lining pressures will develop. Construction
simulation is completed when all boundary tractions are The displacement 6, can be represented in a nondimen-
removed. The gap parameter may be considered as the max- sional form, viz,
imum settlement at the tunnel crown when interpreting field
measurements such as the vertical displacement near the
crown level as determined from extensometer or deep set-
tlement probe. Furthermore, the surface settlement at the where
centreline of the tunnel can be empirically correlated with
the crown settlement by the relationship such as that estab-
lished by Lo et ul. (1984) and Ng (1991). where E is the elastic (Young's) modulus at the tunnel
The following sections will describe the approximate tech- springline (typically the undrained Young's modulus in
nique for estimating various components of the gap extension, i.e., E = E,); a is the tunnel radius, Po is the
parameter. total stress removal at the tunnel face, K O fis the effective
coefficient of earth pressure at rest, Pvfis the vertical effec-
Ground losses ahead of the tunnel faces tive stress at the tunnel springline, Pw is the pore pressure
Removal of the in situ stresses ahead of the tunnel face at the tunnel springline (prior to construction of the tun-
resulting from the excavation of the tunnel will cause the nel), and Piis the tunnel supporting pressure (if the tunnel
soil to intrude into the tunnel face. Therefore, a volume of is fully excavated, Pi= 0; the presence of compressed air
lost ground is developed equal to the amount of over- at the tunnel face would cause Pi> 0).
excavated or displaced material at the face. Based on the Another nondimensional parameter frequently used in
results of 3D finite element analyses (Lee 1989), it is found soft-ground tunnels is the stability ratio N, which can be
that the progressive development of 3D "face loss" owing considered as a measure of the available shear strength to
to the continuous advance of a tunnelling shield can be the average boundary stress removed, and is defined as
approximately simulated in a plane strain finite element anal-
ysis (at a transverse section) by increasing the maximum
allowable radial displacement at the tunnel crown. This 3D
effect can then be incorporated in the gap parameter in terms where c, is the undrained shear strength.
of u*,,. By representing a 3D configuration into an Based on the result of 3D elastoplastic finite element anal-
equivalent 2D approximation (see Appendix for detail), it ysis, the development of axial displacement ahead of the tun-
is found that can be given approximately by nel face (in terms of the dimensionless parameter a ) with
stability ratio N is shown in Fig. 3 for H / D of 1.5 and 4.5.
Two soil profiles were considered: (1) the undrained modulus
and shear strength (E,, c,) are assumed to be constant with
where k l is a factor taking account of the doming effect depth; (2) the undrained strength is assumed to increase
across the tunnel face and can be expressed as: linearly with depth. The elastic modulus is assumed to be
volume of nonuniform axial intrusion across proportional to the undrained strength (i.e., with a constant
the tunnel face determined by 3D analysis ratio E,/c,). In both cases, the vertical initial stress
[31 kl = increases linearly with depth because of the weight of the
volume assuming uniform axial intrusion overburden. As shown in Fig. 3 (for the case of K O f= I),
(i.e., 0 < kl < 1; kl = 1 represents an uniform intrusion the behaviour of axial displacement 6,, if calculated in
at the tunnel face); and 6, is the magnitude of maximum terms of the dimensionless displacement Q , is quite insen-
axial intrusion at the tunnel face. Thus, the 3D soil sitive to the tunnel depth (H/D) or the distribution of soil
movements ahead of the tunnel face can be represented by properties. For stability ratio Nless than about 2.5, a con-
~ * 3 provided
, that the values of k l and 6, are determined. stant dimensionless displacement 0 of 1.I2 is obtained for
The parameter kl has been examined by Lee (1989) using all the variables considered, and the soil mass ahead of the
3D elastoplastic finite element analyses on various combina- face remains largely elastic. It may be seen that deforma-
LEE ET AL.

Y ti- Pi
STABILITY RATIO N=
C
D 1 2 3 4 5 6

L4
0
n
-4
W
3: 1.12
-4

!2

Iwx1
;;3*
tn
H
n II
d C:
u
H
X
4
U
w
r n -4
tn L 4
W
c7 d
Z W
0 Z
H Z
zs
W

FIG. 3. Dimensionless axial displacement ahead of the tunnel face. -, constant soil parameters; ---,soil parameters increase linearly
with depth.
YH - p i
STASILITY RATIO N =-
C
.U

UNDRAINED CONDITION
v = 0.49
U

FIG. 4. Dimensionless axial displacement ahead of the tunnel face with various KO conditions.

tion increases rapidly as Nexceeds a value of about 3. This The effect of KO' not equal to unity is shown in Fig. 4
increase in displacement is due to an increase in the extent for the case of KO' of 0.6, 1, and 1.4. The results shown
of the plastic zone. It is of interest to note that the develop- in Fig. 4 are plotted in terms of !J as defined by [5] (Po as
ment !J versus N is quite insensitive to the tunnel depth to defined by [6] with corresponding KO' values). It is found
diameter ratio (H/D). that the dimensionless displacement (a) is quite insensitive
CAN. GEOTECH. J. VOL. 29, 1992

r I n c r e a s e d Void Due t o P i t c h i n g

A c t u a l Grade

Liner Segments
L P i t c h i n g of S h i e l d

FIG. 5. ( a ) Ground loss owing to pitching of tunnel shield, given as V,,,,, = 27raL/2. ( b ) Equivalent transverse section, where
V,,,,, = n[a + (w/2)l2 - a2.

to various KO1values, especially when N is less than about Ground losses over the shield
2.5. This indicates that results obtained from the condition The loss of ground that occurs over the shield corresponds
of KO1 = 1 and given in Fig. 3 can be approximately used to the volume of soil that is displaced or mined in excess
for other initial in situ stresses conditions provided that Po of the diameter of the cutting shield. Causes of such loss
is as defined in [6] and KO1does not vary substantially in ground are primarily due to alignment problems
from the range considered (0.6 I KO1 I 1.4). encountered when steering the shield. One of the common
alignment problems is due to the fact that it is a common
practice for the tunnel operators to advance the shield at
Application of equation [4] a slightly upward pitch relative t o the actual design grade
Equation [4] can be used to estimate the equivalent soil to avoid the diving tendency of the shield. This excessive
movement at the crown ( u * ~due ~ ) to 3D movements ahead pitch will cause overcutting of the ground near the crown
of the face. The parameter 6, can be determined by of the tunnel. As suggested by Cording and Hansmire
estimating the nondimensional displacement fl from Fig. 3 (1975), this type of ground loss can be estimated by assum-
for a given stability ratio N a n d back-calculating 6, from ing that, over the length of the shield, a point above the
[5]. If compressed air is used at the tunnel face, the term crown will settle an amount equal to the length of shield
Pi in [6] and [7] corresponds to the compressed air times the pitch of the shield in excess of the actual grade
pressure. as shown in Fig. 5. The volume of lost ground (Vshield) over
Closed-face tunnelling machines may be equipped with the shield owing to deviations from design grade can be
rotary excavators that support the face during excavation. estimated as
The rate of intrusion of spoil through the machine head can
be controlled by the size of the openings in the face. If the [81 vshield = 2naL x (excess pitch)
-
size of these openings is controlled in such a way that the 2
rate of advance of the machine is consistent with the volume where a is the tunnel radius and L is the length of the shield.
of soil excavated, then the amount of 3D face loss would The unit dimension of Vshieldis equal to volume of over-
be smaller than that calculated using [4]. excavation per unit length of tunnel advance. An equivalent
Face-supported tunnelling machines (e.g., slurry shield, amount of loss of ground at the transverse section in terms
earth and water pressure balance machines) were found to of the workmanship parameter w can be obtained by
be capable of providing positive outward pressure ahead of equating Vshieldwith the volume as defined in Fig. 5, viz,
the face (Kitamura et al. 1981; Fujita 1985; Finno 1983).
Thus, ground loss owing to 3D inward movement of soil [91 2naL x (excess pitch)
Vshield = -
into the tunnel face can be virtually eliminated by employ- 2
ing these types of machines. However, the exact ground-
supporting mechanism and reconsolidation of the remoulded
soil resulting from the use of these types of machines requires Ignoring the secondary term, [9] becomes
further investigation.
In [4], u * is~ determined
~ by assuming the machine is [lo] w = L x (excess pitch)
advanced in perfect alignment. This implies that the 3D lost This equation can be used as a guide to estimate the possi-
ground is primarily due to the deformation of soil ahead ble value of workmanship parameter w, if the maximum
of the tunnel face. If the machine is pitched upward or allowable "excess pitch" is specified by tunnel engineers
downward, additional material will be excavated. This quan- before the construction, or this equation can be used to back-
tity is related to workmanship and is denoted by w in [I]. figure the volume of lost ground (and hence the workman-
An approximate method to estimate the maximum value of ship parameter) if the record of excess pitch was made avail-
w will be discussed in the following section. able after construction.
LEE ET AL.

Final Radial Deformation (6


I PS i

1 30 Radial Deformation *face

Advance ' Shield


-
Unlined Tunnel
*
FIG.6. Three-dimensional radial movement at the tunnel crown; unrestrained deformation.

LONGITUDINAL DISTANCE X/D

-4 -3 -2 -1 FACE 1 2 3 4
I I I I I I I

FIG.7. Normalized displacement profiles along the longitudinal crown axis. Mode i deformation: unrestrained displacement.

Additional lost ground can arise due to the irregular ward, point A will move to A ' . The total 3D radial defor-
upward or downward pitching motion of the shield at an mation of the soil just ahead of the tunnel face would be
inclination other than the tunnel design grade. Loss of 6faCe.Consider the situation where the over-excavation
ground in a similar fashion occurs owing to yawing, when owing to intermittent alignment problem of the shield creates
the shield is allowed to move irregularly from side to side. an annular void of the size such that the soil is allowed to
The occurence of this irregular motion is generally intermit- deform freely into the tunnel opening without the influence
tent and highly dependent on the experience of the workmen of the tunnel shield and lining, then an unlined tunnel situa-
controlling the advance of the shield. This irregular motion tion will be created temporarily. As the face advances far-
will cause the shield to over-excavate additional material. ther, point A ' will move to point A " , as in the case of an
This overcutting problem is primarily related to workman- unlined tunnel. However, the unlined condition is only
ship and cannot be precisely determined prior to created temporarily because of intermittent alignment dif-
construction. ficulty of the shield. Construction control in soft-ground
With good tunnelling technique, the radial deformation tunnelling (i.e., the presence of tunnelling shield and lin-
of the ground is largely restrainted by the stiff structural ing) seldom allows the full unlined tunnelling condition to
support of the tunnelling machine and therefore the radial develop. The maximum possible radial deformation of the
ground loss over the shield is usually quite small. However, ground at the tunnel face would be the magnitude of
intermittent alignment and steering problems will tem- In practice, this amount of radial intrusion of soil &face will
porarily create an over-excavated zone around the tunnel- be over-excavated at the tunnel face by the tunnelling
ling machine. This will allow more radial ground movement machine, and this will represent the amount of radial ground
into the annular void created by the over-excavation. To esti- loss over the shield owing to alignment difficulty. An
mate the radial ground loss induced by these construction approximate technique to estimate the magnitude is to
problems, the following two idealized ground-deformation apply a factor to the plane strain radial displacement at the
modes were examined. crown (i.e., 6,,). This factor can be determined from the
(1) The 3D ground deformations and boundary condi- results of 3D analyses of unlined tunnels (details have been
tions around a tunnel heading are illustrated in Fig. 6. Con- given by Lee and Rowe 1990a). Typical results of the radial
sider the movements of a point A located along the crown deformations of the soil along the crown axis of an unlined
level of the tunnel opening. As the tunnel face advances for- tunnel are shown in Fig. 7. For the elastic case, the ratio
936 CAN. GEOTECH. J. VOL. 29, 1992
I
Physical Gap ( G )
P
I 7 3 D Radial Def ormatian P
'face

\
Overcutting

-
Direction of
Tunnel Advance
I
ShieldI-
I
Lining
FIG. 8. Three-dimensional radial movement at the tunnei crown; constrained deformation.
b

of the radial deformation at the face to the maximum deformation at B, then the full unlined tunnel condition will
plane strain displacement (A,,) is approximately 1/3. develop. This case will then be identical to case 1. If G, is
A similar ratio was suggested by Lo et al. (1984) for elastic small, then the radial displacement behind the tunnel shield
deep tunnels. If plasticity is allowed to develop around the will be restricted by the lining, and the maximum possible
tunnel heading, this ratio is reduced t o about 0.24-0.26 radial displacement (6,,,) is equal t o the physical gap G,.
(depending on the amount of plasticity and H / D ratio, see With this deformation mode and boundary conditions, the
Lee and Rowe 1990b for details). Here, a conservative esti- maximum possible radial deformation of the ground at the
mate for the correction factor of 1/3 (regardless of the tunnel face would be the magnitude of 6f,ce. This amount
amount of plasticity) is suggested. Thus the maximum possi- of radial intrusion will be excavated at the tunnel face by
ble effective ground loss over the shield, under this defor- the tunnelling machine. The ratio of to the maximum
mation mode and boundary conditions, can be written as radial deformation behind the tunnel face (6,,,, which is
equal to the physical gap G,) can be determined by 3D
finite element analysis of a lined tunnel. Figure 9 shows the
where uiis the elastoplastic plane strain displacement at the typical displacement profiles along the crown axis as
crown (equivalent to 6,, as defined in Fig. 6). As suggested predicted by finite element analyses for an elastic and an
by Lo et al. (1984), for elastoplastic conditions (N > I), elastoplastic case. The ratio lifaCe/Gp(or 6face/6max)
is found
the radial crown displacement ui is approximately given by to be 0.42 and 0.56 for the elastic and elastoplastic cases,
respectively. Results from a number of analyses on different
tunnel geometry (H/D ratios) indicate that the ratios
6face/Gpare generally in the range of 0.5-0.6 (see Lee 1989
for details). For simplicity of calculation, a correction fac-
tor of 0.6 is suggested. Therefore, under this deformation
mode, for typical sizes of physical gap (usually in the range
where E, and v, are the undrained modulus and Poisson's of about 60-200 mm), the maximum possible ground loss
ratio, respectively; a is the radius of the excavated opening; over the tunnel shield can be expressed as
and N is the stability number as defined by [7].
(2) The second scenario of radial deformation around the
tunnel shield is illustrated in Fig. 8. Consider the movement
where G, is the physical gap of the tunnel system and is
of a point B located along the crown level of the opening.
equivalent to (2A + 6) as defined by [I].
As the face advances forward, point B will move to B'. In
Since the extent of overcutting owing to alignment and
this scenario, the tunnel is assumed to be lined, and the
steering problems is primarily related to quality of workman-
amount of ground displacement will eventually be limited
ship and cannot be precisely determined prior to construc-
by the presence of the lining. However, just before the actual
contact between the soil and the lining, the ground is allowed tion, it is suggested that the two proposed equations (i.e.,
to deform freely into the tail void, which is the distance [ l l ] and [13]) could be used to establish a possible range
between the crown of the tunnel and the top of the lining of workmanship parameter w . For most of the soft-ground
(or the so-called physical gap G,). Consider the situation tunnelling situations, the radial displacement of the soil
that an intermittent alignment problem creates an annular along the tunnel shield will usually be restricted by the pres-
void around the shield, so the soil is temporarily allowed ence of the lining. Under most circumstances, [13] (i.e.,
w = 0.6Gp) will govern the amount of lost ground over the
to deform into the physical gap. Assuming point B' lies on
the surface of the temporarily created annular void, it will shield. However, if the physical gap size is greater than the
deform into the opening until it comes in contact with the possible unrestrainted deformation at the crown, then full
lining at B" . The presence of the lining will arrest the defor- plane strain conditions may be allowed to develop. Thus,
mation of the soil and transfer all the load into the struc- the maximum possible ground loss over the tunnel shield
ture components of the lining. In that case, there will be may be estimated as
no further ground movement, and the final deformation [14] w = 0.6Gp provided that w 1
I-ui
BB" is denoted by 6,. If G, is greater than the final 3
LEE E T AL.
I
LONGITUDINAL DISTANCE X/D
-4 -3 -2 -1 FACE 1 2 3 4
I I I I I I I I I I I 1 I I

FIG. 9. Normalized displacement profiles along the longitudinal crown axis. Mode ii deformation: constrained displacement.

Otherwise, w = %ui. It should be noted that [Ill-[14] are Once the soil comes into contact with the tunnel lining,
used to estimate the workmanship factor and are quite the lining will deflect under the applied loading. It has been
distinct from the previous estimates of the component of observed that the crown of the tunne1,usually will compress
GAP owing to face displacement (eq. [4]). under this loading, whereas the springline will expand (Ward
1969; Peck et al. 1972). This may be considered directly by
Radial loss due to overcutting bead using the lining flexibility in the finite element analysis or
The construction details of the shield tend to control the alternatively, if a rigid lining is used in the analysis, the
total volume of ground lost. A particular source of loss arises deflected shape (see Peck et al. 1972) may be represented
from the bead, or similar device, welded on the leading edge as an additional component of lost ground; however, for
of the hood and shield to overcut the ground, reduce fric- most cases, the magnitude of this component will not be as
tion during shield advance, and allow the shield to be steered significant as the other sources described.
more easily.
There are three usual cases: no bead, the bead spans the
upper 180" of hood, and the bead covers the full cir- Procedure for estimating the gap parameter
cumference (360") of hood and shield. In each case, the total The proposed numerically based approach described in
thickness of the bead should be included in the parameter the preceding paragraphs is developed under idealized con-
W , i.e., ditions. In applying the proposed solution technique to prac-
tical situations, each case must be carefully considered to
[15] o = (value of w from [14]) + n x evaluate whether the fundamental assumptions are satisfied.
(thickness of the bead) In summary, the gap parameter is given by
where n = 1 when the bead spans only the upper 180" of El] GAP = G, + u * +~ w ~
the hood and n = 2 for the full 360" bead.
where G, = 2A + 6 (see Fig. 2), A is thickness of the tail-
Ground losses upon the erection of the lining piece, 6 is clearance required for erection of the tailpiece,
The loss of ground, which occurs upon erection of the u * is~3D~elastoplastic deformation ( 5 0.56,, from [4]),
tunnel lining, results because the tunnel lining usually insuf- 6, is given in Figs. 3 and 4 (see also [5]-[7]), and o is
ficiently replaces the cross-sectional area of the tail of the workmanship factor and is the minimum of 0.6Gp and %ui,
shield. Tunnel liners are frequently required to be erected i.e., s 0 . 6 G p (as defined above) and s %ui (where ui is
under the protection of a shield tail with certain clearance. given by [12]).
As the shield moves forward, the change in stress state The following comments may be helpful in using the pro-
induced in the clay by the excavation causes the ground to posed method in tunnelling projects in clays.
squeeze into the void left by the combination of the thickness (1) The physical gap G,, which is equal to the difference
of the tail skin (A) and the clearance (6). In most tunnelling between the diameter of the cut surface (based on the dimen-
situations, the size of this tail void remains a significant fac- sions of the tunnelling machine) and the external diameter
tor contributing to the overall settlement. This source of lost of the lining, can be evaluated based on geometry of the
ground is represented by the physical gap G,, which is com- tunnelling machine (TBM) and lining system.
posed of (2) If the physical gap is small and support follows closely
behind the tail of the shield (e.g., the Extruded Concrete
Lining Method and the "Injectoshield" technique recently
This component of loss of ground may reduce if an developed in Europe and Japan), or an expanded lining is
expanded lining is used. Some reduction in ground sub- used, in these cases, the radial crown displacement cannot
sidence has been obtained by backfilling the void with grout develop and the main sources of ground loss will be largely
upon advance of the shield, thereby decreasing possible restricted to the 3D movement at the tunnel face and
ground loss. However, the effectiveness of grouting depends workmanship problems. For this case, 0 s G, 5 2A + 6
on the rate of soil movement into the void. and will approach 0 if well implemented.
938 CAN. GEOTECH. J. VOL. 29, 1992
1

(3) The 3D movement ahead of the tunnel face can soil surrounding the tunnel during excavation. However, for
be estimated by [4], where the value of 6, can be estimated the approximate analysis describkd herein, it is often ade-
from the design charts given by Figs. 3 and 4. It should be quate to employ vane strength for soft clays and
noted that these results are based on the assumption that anisotropically consolidated undrained triaxial extension
the horizontal in situ stress ahead of the tunnel face is fully tests, on good quality samples, for the determination of
released. For the condition where compressed air is used at modulus. If conventional tube samples are used, a correc-
the tunnel face, the term Pi in [6] and [7] should corre- tion for sample disturbance must be applied. A more
spond to the value of the compressed air pressure. Three- detailed discussion about the selection of soil parameters rel-
dimensional movement ahead of the face can be virtually evant to tunnelling analysis has been given by Ng and Lo
eliminated by the use of appropriate construction technique (1985) and Rowe and Lee (1989).
(e.g., appropriate use of an earth pressure balance machine,
slurry mole). In these cases, 0 r < 0.56, and will Concluding remarks
approach 0 if there is no release of pressure at the face. The components of loss of ground induced by tunnelling
(4) With good tunnelling technique, the radial ground loss in cohesive soils are represented quantitatively by the so-
over the shield is usually quite small. However, if the qual- called gap parameter. The gap is the sum of the 3D
ity of workmanship is in doubt, or during the early phase elastoplastic deformation at the tunnel face, over-excavation
of the construction process where the tunnel crew is not suf- of soil around the periphery of the tunnel shield due to poor
ficiently familiar with the construction technique, the max- workmanship, and the physical gap that is related to the
imum value of the workmanship parameter (w) can be machine, shield, and lining geometry. Methods for
estimated by the following conditions: w = 0.6Gp provided calculating the 3D deformation and approximate methods
that w I %ui; otherwise, w = %ui, where ui is the elasto- for estimating the maximum value of the workmanship
plastic plane strain displacement at the crown and can be parameter are described. The physical gap is determinable
determined by the closed-form solution given by [12], and once the machine-support system is chosen. This gap param-
G, is the physical gap of the tunnel system (i.e., G, = eter can then be used in conjunction with plane strain finite
2A + 6). element analysis (e.g., see Rowe et al. 1983) to predict the
(5) If an overcutting bead or any similar device is attached resulting ground deformations.
to the leading edge of the machine, the total thickness of Following the steps outlined in the present paper, a rea-
the bead should be included in the workmanship parameter w. sonable estimate of the gap and consequent expected set-
(6) The effectiveness of grouting the tailpiece voids tlements may be made prior to construction. Where signifi-
depends on the rate of soil movement into the void. In most cant variations in soil and (or) construction conditions are
of the tunnelling cases in soft clays, the grout is injected after expected, a range of values of gap may also be determined
soil movements have occurred and hence is ineffective. How- to calculate the upper and lower bounds of surface
ever, if special care is taken to ensure that the grout is settlements.
injected before movements occur (e.g., by maintaining com- The application of these numerically based techniques will
pressed air pressure until grouting of the void is achieved, be discussed in a companion paper (Rowe and Lee 1992)
then the gap will be reduced). This reduction in gap may where the range of applicability will be assessed by refer-
be incorporated into the workmanship term w as a negative ence to case histories that encompass a wide range of soil
value. conditions and construction techniques.
(7) For stiff clays, since the rate of ground settlement near
the crown is usually much slower than the average rate of Acknowledgements
advance of the tunnel shield (Attewell and Farmer 1974; Lo Funding for this research has been provided by the
et al. 1984), grouting (or pea gravel) can usually be injected Natural Sciences and Engineering Research Council of
into the tailpiece voids without difficulty, and the grouting Canada by means of grant A1007 and a Steacie Fellowship
should be effective. Thus, G, = (2A + 6) = 0, provided awarded to R.K. Rowe and grant 0046681 to K.M. Lee.
that injection is conducted close behind the tunnel shield
so that the unsupported length of tunnel between the rear
of the tail and the last grouted portion is small. On the other Attewell, P.B., and Farmer, I.W. 1974. Ground disturbance caused
hand, if a grouting procedure is not adopted, the ground by shield tunnelling in a stiff, fissured, overconsolidated clay.
is allowed to deform freely into the tailpiece void. As sug- Canadian Geotechnical Journal, 11: 380-395.
gested by Peck (1969), the stability ratio N for stiff clay is Brown, P.T., and Booker, J.R. 1985. Finite element analysis of
usually less than 2 and the soil mass around the opening excavations. Computers and Geotechnics, 1: 207-220.
remains largely in elastic condition. An initial estimate of Cording, E.J., and Hansmire, W.H. 1975. Tunnels in soils-
the crown displacement ui can be obtained from the plane general report. Proceedings, 5th Pan American Conference of
strain solution, [12]. If the calculated crown displacement Soil Mechanics and Foundation Engineering, Session IV, Buenos
ui is less than the physical gap G,, plane strain conditions Aires, Argentina, pp. 571-632.
Davis, E.H. 1968. Theories of plasticity and the failure of soil
will be satisfied. For this special case, the gap parameter is
masses. In Soil mechanics selected topics. Edited by I.K. Lee.
given by Butterworths, Sydney, pp. 341-380.
GAP = ui if ui s G, Finno, R.J. 1983. Response of cohesive soil to advanced shield
tunnelling. Ph.D. thesis, Stanford University, Stanford, Calif.
GAP = G, if ui > G, Fujita, K. 1985. On the surface settlements caused by various
methods of shield tunnelling. Proceedings, 10th International
(8) Ideally, the elastic and strength parameters should be Conference on Soil Mechanics and Foundation Engineering,
determined in triaxial tests following the stress path of the Stockholm, vol. 4, pp. 609-610.
LEE ET AL.

Gibson, R.E. 1974. The analytical method in soil mechanics. List of symbols I

Giotechnique, 24: 115-140. a tunnel radius


Kack, G.J. 1981. The prediction of subsidence above shallow
tunnels in soft soil. M.E.Sc. thesis, Faculty of Engineering undrained shear strength of soil
Science, The University of Western Ontario, London, Ont. D tunnel diameter
Kitamura, M., Sumikicki, I., and Fugiwara, T. 1981. Shield E elastic (Young's) modulus of soil
tunnelling performance and behaviour of soft ground. ELI undrained elastic modulus of soil
Rapid Excavation and Tunnelling Conference Proceedings, GAP(G) gap parameter
San Francisco, vol. 1, pp. 201-220. G~ physical gap (G, = 2A +
6)
Kulhawy, F.H. 1974. Finite element modelling criteria for Gvh independent shear modulus
underground opening in rock. International Journal of Rock H height of soil cover from the ground surface
Mechanics and Mineral Sciences, 11: 465-472. t o the centre axis of the tunnel
Lee, K.M. 1989. Prediction of ground deformations resulting from total coefficient of earth pressure a t rest
shield tunnelling in soft clays. Ph.D. thesis, Faculty of Engineer- KO
KO' effective coefficient of earth pressure at rest
ing Science, The University of Western Ontario, London, Ont.
Lee, K.M., and Rowe, R.K. 19900. Finite element modelling of kl parameter to take into account the "doming"
the three-dimensional ground deformations due to tunnelling in effect across the tunnel face, 0 < k t < 1
soft cohesive soils. Part I. Methods of analysis. Computers and L length of the tunnel shield
Geotechnics, lO(2): 87-1 10. N stability ratio
Lee, K.M., and Rowe, R.K. 1990b. Finite element modelling of Po total stress release at the tunnel face
the three-dimensional ground deformations due to tunnelling in Pv' vertical effective stress at the tunnel springline
soft cohesive soils. Part 11. Results. Computers and Geotechnics, (prior t o tunnel construction)
lO(2): 111-138. pore pressure a t the tunnel springline (prior
Lee, K.M., and Rowe, R.K. 1991. An analysis of the 3-dimensional
PW
t o tunnel construction)
ground responses of the Thunder Bay tunnel. Canadian
tunnel supporting pressure (if the tunnel is
Geotechnical Journal, 28: 25-41. pi
Lo, K.Y., and Rowe, R.K. 1982. Prediction of ground subsidence fully excavated, Pi= 0; the presence of com-
due to tunnelling in clays. Research Report GEOT-10-82, Faculty pressed air a t the tunnel face would cause
of Engineering Science, The University of Western Ontario, Pi> 0)
London, Ont. ui radial crown displacement
Lo, K.Y., Ng, R.M.C., and Rowe, R.K. 1984. Predicting settle- u * ~ ~equivalent three-dimensional movement ahead
ment due to tunnelling in clays, Tunnelling in Soil and Rock, of the face
American Society of Civil Engineers, Geotech I11 Conference, VShield ground loss over the tunnel shield
Atlanta, Ga., pp. 48-76.
Ng, R.M.C. 1984. Ground reaction and behaviour of tunnels in
vf ground loss a t the tunnel face
vu undrained Poisson's ratio (v, = 0.5)
soft clay. Ph.D. thesis, Faculty of Engineering Science, The Uni-
6 loss of ground due t o the clearance required
versity of Western Ontario, London, Ont.
Ng, R.M.C. 1991. A procedure for prediction of settlement due for erection of the lining
to tunnels in clays. Proceedings, 9th Panarnerican Conference &face vertical displacement along the crown axis a t
on Soil Mechanics and Foundation Engineering, Vina Del Mar, the tunnel face
Chile, vol. 3, pp. 1413-1430. 6,a~ maximum vertical displacement along the
Ng, R.M.C., and Lo, K.Y. 1985. The measurements of soil crown axis
paramaeters relevant to tunnelling in clays. Canadian 6,, vertical displacement along the crown axis
Geotechnical Journal, 22: 375-391. under plane strain conditions
Ng, R.M.C., Lo, K.Y., and Rowe, R.K. 1986. Analysis of field maximum axial intrusion of soil a t the tunnel
6x
performance - the Thunder Bay tunnel. Canadian Geotechnical face
Journal, 23: 30-50.
A thickness of the tail piece
Peck, R.B. 1969. Deep excavations and tunnelling in soft ground.
Proceedings, 7th International Conference on Soil Mechanics 7 unit weight of soil
and Foundation Engineering, Mexico City, pp. 225-290. w workmanship factor
Peck, R.B., Hendron, A.J., Jr., and Mohraz, B. 1972. State of fl dimensionless displacement parameter
the art of soft ground tunnelling. Proceedings, 1st Rapid Excava-
tion Tunnelling Conference, Chicago, vol. 1, pp. 259-286.
Rowe, R.K., and Kack, G.J. 1983. A theoretical examination of
the settlements induced by tunnelling: four case histories. Cana- Appendix. Equation to estimate ground losses ahead of
dian Geotechnical Journal, 20: 299-314. the tunnel face
Rowe, R.K., and Lee, K.M. 1989. Parameters for predicting defor- The volume of soil that intrudes into the tunnel face owing
mations due to tunnelling. Proceedings, 12th International Con- t o pressure release a t the face will eventually be excavated.
ference on Soil Mechanics and Foundation Engineering, Rio de Thus, there is a volume o f lost ground equal t o the amount
Janeiro, pp. 793-796. of over-excavated material a t the face called t h e face loss,
Rowe, R.K.9 and Lee, K.M. 1992. Subsidence due to tunnelling. vf. The face loss can be represented by the product of the
11. Evaluation of a prediction technique. Canadian Geotechnical
area of the face (na2) and the soil intrusion distance per
Journal, 29: 941-954.
Rowe, R.K., Lo, K.Y., and Kack, G.J. 1983. A method of unit length advance (6x/ax), if soi1 intrusion is
estimating surface settlement above tunnels constructed in soft assumed take place Over the face area.
ground. Canadian Geotechnical Journal, 20: 11-22. I n practice, because of the geometric constraint provided
Ward, W.H. 1969. Panel discussion. Proceedings, 7th International around the heading and drag at the cutting end of the shield,
Conference on Soil Mechanics and Foundation Engineering, a clay soil will tend t o bulge a t the centre (Attewell a n d
Mexico City, vol. 3, pp. 320-325. Farmer 1974). A factor kl,where 0 < kl < 1, could be
940 CAN. GEOTECI3 . J . VOL. 29, 1992

is quite uniform; an assumption of kit = 1 should give a


conservative but reasonable approximation.
The unit dimension of Vfis equal to displaced volume
per unit length of tunnel advance. An equivalent amount
of loss of ground at the transverse section can be obtained
by equating Vf with the volume as defined in Fig. A l .
Therefore,

Ignoring the secondary term, [A21 becomes

Based on [A3], the 3D movements ahead of the face can


be approximately represented by if the value of ax/&
is determined.
Numerically, the ratio of 6,/Ax can be determined by a
step-by-step incremental excavation technique. However, the
selection of an appropriate step size (Ax) is a complex task,
since the real tunnelling situation is continuous and it is
highly dependent on the actual construction procedure and
the rate of tunnel advance (which in turn depends on the
condition of grounds, size of the tunnel, and the experience
of the workman controlling the tunnelling machine). A con-
FIG.Al. Approximate method to incorporate three-dimensional servative but realistic approach is to adopt the maximum
face loss into equivalent radial ground loss. ( a ) Tunnel heading; possible ratio of 6,/Ax that yould develop in an advanc-
face loss V, = na2k,(6,/k). ( 6 ) Equivalent transverse section; ing tunnel [A3]. Based on the results of 3D elastoplastic
equivalent face loss V, = n { [ a + (u*,,/2)]' - a'}. finite element analysis, Lee (1989) observed that the critical
step size (Ax) is approximately equal to one tunnel diameter
applied to take this doming effect into account, so Vfcan ahead of the face. Based on this result, it can be argued that
be expressed as for the case of single-step instantaneous tunnelling simula-
tion (since the initial stress ahead of the face is completely
removed in a single step), maximum 3D ground effect would
be approximately predicted if Ax in [A31 is assumed to be
where 6, is the maximum axial intrusion of soil at the tun- 1.OD (one tunnel diameter) (D = 2a). The ratio of 6,/Ax
nel face arising from a tunnel advance, Ax (i.e., Ax is the in [A31 can, therefore, be approximately obtained by a
distance of step size adopted in the step-by-step incremen- single-step excavation simulation to determine the maximum
tal finite element analysis). The factor kl is a measure of soil intrusion at the tunnel face (6,) and, assuming Ax to
the uniformity of the axial displacement that occurred along. be D, [A31 can be simplified as
the tunnel face. Theoretically, k l can be determined by
field measurement. However, as shown by the finite element
analysis, intrusion of soil near the centre of the tunnel face

You might also like