You are on page 1of 8

ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project

in Beit Safafa - Jerusalem


Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Supply, install, test, commission, maintain, and manufacturer


warranty (full package electrical lift), compliance on EN - 81.1 and Required
New Israeli Taken specially for the residential building.

The supplier should be direct agent for the mother company or exclusive
distributer, not be broker, the supplier should present official written
Required
documentation duly endorsed from the Manufacturer and/or the main
importer

All lift major components including motor , controller, all safety


Preamble devices, ropes, car, doors, should be manufactured by the mother
company with indicating certificates and component list showing all
Required
manufactured by the same mother company (factory) from which lift is
finally shipped. Price shall include all related material and electrical
works related to lift with the following specifications:

The contractor is obliged to execute the works according to the Israeli


laws & Standards that is enforced in this domain as well to secure all
Required
relevant documentations required including the TAKEN code, TOFES 4
certification and the Jerusalem Municipality approval certificates.

Type: Electric elevator - Passenger lift Required


Quantity: Unit 9
Code: En81.1 and New Israeli Taken Required
Capacity: Kg / persons 450 kg/6
Velocity: Mt. / sec. 1
Drive: VVVF - Closed Loop Required
Leveling Accuracy: Mm. +/- 5mm
No. of Car entrance: Number 1
No. of Stops: Number 5
No. of Doors: Number 5 in line
Floor Numbering: Number 1, 2, 3, 4, 5
Travel Height: Mt. 18 mt. approximately
Shaft Size (WxD): (W)Mm. x (D)mm. 1600 x 1600

Page 1 / 8
ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project
in Beit Safafa - Jerusalem
Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Shaft way construction: Material Concrete


Overhead: Mm. 3400 mm
Pit Depth: Mm. 1060 mm, on solid slab
Use (minimum) Starts / hours 180
Machine room location: Roomless - above the shaft Required
Roping: 2:1

AC - 3 phase, 400/230 V, 50 Hz with neutral and ground wires (for


Power supply: power). AC - 1 phase, 230 V, 50 Hz (lighting). Power consumption no Required
more than 3 KW.

Supply and install sub-electric panel for each elevator including the
supply of the required quality of cables to connect to the Main Power
Power supply Connection of individual supply. The quoted price shall include any required paperwork’s for
Required
Elevator to the Existing Main Power Supply Power source official providers in Jerusalem to secure the safe
connection and operation of each elevator; all in accordance to the
enforced power standards of Jerusalem City

Basic control drive & operation


function:
Basic Control: Simplex Required

Control system: Fully computerized - based on low-energy multiprocessor technology Required

Closed loop - Variable Voltage Variable Frequency (VVVF) system -


Permanent magnet gearless machine with double coil braking system
Motor drive: Required
oilless type with 25 years life time certified by the manufacturer
according to EN-81

A microprocessor system with full options to arrange the registration of


Selector: Required
the call respect to the priorities and direction of the car

Overload function Required


Fire emergency return control Required
Re-leveling Required

Page 2 / 8
ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project
in Beit Safafa - Jerusalem
Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Noise and thermal protection Required


Earth leakage protection Required
Voltage drop protection Required
Over speed protection Required
Phase failure and phase reversal protection Required
Safeties in the control:
Full load bypass Required
Automatic return to main floor Required
Independent operation Required
Anti-stall timer Required
Intercom between car and controller box Required

Compliance with handicapped options as EN81-70 for Automatic


Evacuation : Whenever there is a power failure, the lift will take Required
passengers safely to the next floor and open doors.

Position of the main control unit: Integrated in the door frame on the upper floor Required
A single speed, AC - 3 phase gearless motor, especially made to
Motor data: compromise the VVVF drive control system at: 400 volts and 50 Hz. - Required
Insulation class "F" - Protection IP 21"
Fully automatic - Collective/Selective control in up and down direction
Mode of operation: Required
with automatic floor leveling
Ride comfort:
Acceleration/ Decelaration : Mt / s2 0.8
Max Jerk: Mt / s2 1.2

Page 3 / 8
ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project
in Beit Safafa - Jerusalem
Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Max vertical vibrations in car : Cm / s2 17-25


Lateral Quaking in car: Min/Max : Cm / s2 10-15
Noise in car: Mean with Fan: dBa 50
Noise in shaft : dBa 60

Car specifications:
Special steel structure frame and platform holding the cage through a
Car construction: Required
rubber vibration isolators.
Clear width in mm. 1200
Clear depth in mm. 1250
Car inside dimension: Clear height in mm. 2135
Door width in mm. 800
Door height in mm. 2000
Hairline Steel sheet fabricated to sustain the load of 2000 N with
Car ceiling: Required
indirect lighting
Car side walls: Hairline Stainless Steel Required
artificial granite of 100 kg. weight (to be selected and approved by the
Car flooring: Required
site engineer)
Car handrail: Rear side of circular section of Hairline Stainless Steel Required
Car internal decoration: Rear side clear mirror above the handrail Required
Car ventilation: Exhaust fan of 270 m3/hr. capacity - Auto exhaust fan shut-off Required
Car lighting: LED lighting - Auto light shut-off Required

Car external opening: Hairline Stainless steel frame to cover the full width of the wall opening Required

Car Operating Panel:

One COP of Hairline Stainless Steel, stylish,


full height . Electromechnical push buttons at Required
side wall panel. Composed of:

Page 4 / 8
ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project
in Beit Safafa - Jerusalem
Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Electromechanical push buttons for landing (floor designations), Braille


Required
lettering
Alarm button Required
Open door button Required
Close door button Required
Digital position indicator Required
Intercom with two way call. Required
Direction arrows Required
Instruction plate Required
Man machine function box including many operational devices Required
Fan switch Required
Full load indication signal Required
Overload protection device with audible and visible signal
Emergency lighting and sounding system enclosed in COP
Car Doors:
Car door: Fully automatic side 2 panels, heavy Door width in mm. 800
duty Door height in mm. 2000
Car door drive: Regulated with AC-VVVF Required
Opening: Telescopic opening 2 panels Required
Door sill: Hard anodized aluminum sill Required
Panels finish: Hairline Stainless Steel Required
Include full height photocell with safety edge device Required
Accessories:
Door open/close time is adjustable Required
Landing Doors:
Door width in mm. 800
Door:
Door height in mm. 2000

Page 5 / 8
ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project
in Beit Safafa - Jerusalem
Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Door panels finish: Hairline stainless steel at all floors Required


Door frame: Box frame in Hairline Stainless Steel at all floors Required
Fire resistance: Class F-120 (Landing doors are 120 minutes fire resistance) Required
Landing operation and indication panels: All floors Required
Position indicator, direction arrows: Above the doors in all floors Required
Push buttons: Electromechanical push buttons , Braille lettering Required

Shaft equipment:
Buffers Required
Counter weight Required
Suspension ropes (steel cables not belts) - Safety factor >12 Required
Guide rails - "T" section with self lubricated heavy guide shoes Required
Safety features:
Fireman key switch at the Main Floor with complete system Required
Safety gear - Progressive type CE certified Required
Ascending safety protection according to the international directives Required
Limit and final limit switch Required
Outside door latch Required
Door lock switch Required
Semi Automatic brake release by means of push button outside the shaft
Required
to evacuate trapped people
Emergency evacuation battery charger system to evacuate trapped
Required
people in case of Power failure
Readiness to connect to generator Required
Nudging feature Required
Home landing feature Required
False calls cancellation Required

Documentations:
Certificate of origin (original copy) Required
Bill of lading (original copy) Required

Page 6 / 8
ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project
in Beit Safafa - Jerusalem
Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Compliance certificate from third party, European notified body for the
lift model with European norms En.81, including all safety components
which also should be of the same original manufacturer : Doors locking Required
devices, Submit EURO 1 certificate, where applicable safety gear,
overspeed governor.

Delivery time: Calendar Days effective date of contract acceptance 60

Maintenance and guarantee:


Maintenance directly resulting from the civil
Calendar Year effective date of substantial completion certificate 1
works contracturalship
Minimum Calendar Years effective date of installation & initial
Guarantee granted by the main manufacturer 2
Operational test

Supply, delivery to site, install & operate of


Passenger Elevators strictly in accordance to
the aforementioned detailed preamble and
including all preliminary required works for the
proper , safe and successful installation like
cleaning the Elevator concrete shafts, prepare
1 o. 9
shafts surfaces to properly accommodate the
elevator parts including scaffolding material
and structure erecting services, as well any
other structural works required by the
manufacturer for the proper and safe
installation of the elevators.

Provisional: Annual maintenance service rate


upon the expiry of duration item 12.1 ; with To start 1 year after self service. Provide a separate cost estimate not
2 Required Job 1
minimum validity period of 24 calendar included in this offer.
months

Page 7 / 8
ITB-2011-008 Supply and installation of nine elevators for Sharafat Social Housing Project
in Beit Safafa - Jerusalem
Bill of Quantities

Unit Rate US$


Item Category General specification Required specification Unit Quantity Total amount US$
(umbers)

Provisional: Proposed list of Spare-parts that


is subject to ware & tare directly attributed to
individual
3 daily operating the elevators. The Quoted price Provide a separate cost estimate of spare parts not included in this offer. Required list
shall not exceed the 10% of the Elevator
package CIF value.

GRAD TOTAL (Excluding Value Added Tax - VAT)

The sum of (in words):

Contractor Name:

Authorized Signatory Name & Title:

Signature / stamp:

Date and place:

Page 8 / 8