Professional Documents
Culture Documents
Estimation
Objectives
1
Where we are?
Bidders
-Cash Flow
2
Price/Cost Anatomy
Bid Price
Cost Markup
Profit
Risk contingency
Direct Cost Indirect Cost
Labor
Equipment Project General
Material Overhead Overhead
…
3
The Final Touches
Approximate range
of contribution to Relative Variations
70-90% total cost among estimators
5-20%
3-10%
0-10%
4
The Challenge
5
Profitability vs. Chance of Winning
Winning Requirements
6
Required Information
Information we have:
Our cost estimate (C = direct + indirect) for any past
bid is known for us.
Since we cannot know the cost estimate of other
competitors, let’s assume that the cost estimate for
all bidders are the same. This assumption is not true
but can be realistic if we assume that all bidders
have access to the same subcontractors, suppliers,
and follow standard construction technology.
The bid prices of competitors in past bids are known
to us as a public information published by most
owners after the bid is let.
7
Bid Price, Cost, & Markup
For Example, in a past bid that we lost, our cost estimate
was $1,000,000. For that project, we submitted a total bid
of $1,150,000 while our key competitor “Company A” bid
was $1,100,000.
Assuming cost estimate is constant:
We used a markup of [(1,150,000/1,000,000) -1] = 15%
“Company A” used a markup of [1,100,000/1,000,000) -1] = 10%
8
7
6 6 No. of past bids against
the competitor
3 3
Below 2 2
cost
1 1
9
Answer the following Questions
10
Assume Normal Distribution
(m, s)
Probability table for Probability of winning
standard normal using markup (m) =
distribution shaded area
B/C
11
12
Estimating Optimum Markup
What is to Optimize?
We have two conflicting objectives: to reduce
markup to improve the probability of winning,
and to increase markup to improve profitability.
The probability of winning is unit-less and profit
is in dollars.
We multiply the two components to get the
Expected Profit that is to be used as a measure
for optimality.
13
The Expected Profit
14
Winning a Single Competitor
Solution:
a) At 20% markup, B/C = 1 + markup = 1.2
Using the standard normal distribution table,
B/C
z = (X-µ) / σ = (1.2-1.1)/0.1 =1.0 1.1 1.2
From the table (provides left side area), Probability = 0.8413, then the
probability of winning “Company B” at 20% markup = 1 - 0.8413 =
0.1587 (the shaded area)
b) Expected profit = Probability of winning x Profit
= Probability of winning x Cost x markup
= 0.1587 x $1,000,000 x 0.2 = $31,740
15
Winning All Competitors
Simultaneously
How to combine: Pwin(A), Pwin(B), Pwin(C), … @ a certain
markup level, to get Pwin(All), at that markup
Two models are available:
Friedman (1956): The basic assumption is that different
competitors’ probability distributions are mutually independent.
Accordingly, he suggested a multiplicative model to combine the
probabilities; i.e., Pwin(All)= Pwin(A) x Pwin(B) x Pwin(C) x …
Gates (1967): criticized the independence of Friedman and offered
his model as follows: 1
Pwin(All)=
1 - Pwin(A) + 1 - Pwin(B) + 1 - Pwin(C) + …+[1]
Pwin(A) Pwin(B) Pwin(C)
16
Optimum Markup Estimation
Expected
Profit
1% 3% 5% 7% 9% markup
Optimum markup
17
Example
A contractor wants to determine the optimal bid to
submit for a job with estimated cost $1,000,000,
bidding against 3 key competitors with the following
historical data.
Solution
At markup = 1%
Probability of winning the 1st competitor, “A”
X = B/C = 1+markup = 1+0.01 = 1.01
ZA = (X-µA)/σA = (1.01 -1.081)/0.052 = -1.365
From normal Distribution table - value = 0.086
Then Probability P win A =1 – 0.086 = 0.914
Probability of winning the 2nd competitor, “B”
X = B/C = 1+markup = 1+0.01 = 1.01
ZB = (X-µB)/σB = (1.01 -1.032)/0.044 = -0.500
From normal Distribution table - value = 0.309
then Probability P win B = 0.691
Probability of winning the 3rd competitor, “C”
X = B/C = 1+markup = 1+0.01 = 1.01
ZB = (X-µC)/σC = (1.01 -1.067)/0.061 = -0.934
From normal Distribution table - value = 0.175
then Probability P win C = 0.825
18
Solution
Probability to win All @ 1% markup:
Friedman Model:
P win All-F = 0.914 x 0.691 x 0.825 = 0.521
EP-F (expected profit) = $1,000,000 x 0.01 x 0.521
= $5,213.3
Gates Model:
P win All-G = 0.571
EP-G (expected profit) = $1,000,000 x 0.01 x
0.571 = $5,705.9
19
Solution
14000 4.2%
12000
3.2%
10000
8000 EP-F
6000 EP-G
4000
2000
0
0.0% 1.0% 2.0% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0%
20
Important Bidding Relationships
When σ of B/C ratio of a competitor is small, it indicates
this competitor uses a consistent markup policy (easy to
win)
in case of high project risk, it is wise to use higher
markup as an allowance for unforeseen conditions. The
use of Gates model in this case is more advisable.
When the level of competition is high (large number of
bidders) and the economic conditions are not favorable,
winning bids becomes difficult and bidders reduce their
bids.
21
Important Bidding Relationships
The correlation between markup and number of
competitors and between markup and project size has
been studied and results are as follows (can be used
in negotiations):
m2/m1 = (n1/n2)0.7
m2/m1 = (s1/s2)0.2
22