You are on page 1of 1

APPENDIX E-1

MANPOWER LIST

Contractor:

Project Title: BM-1 Project


Project Address: Pangkalan Kerinci, Pelalawan, Riau, Sumatera, Indonesia
Developer: PT. Riau Andalan Paperboard International
Work Package: Floor Screeds on Existing Concrete Slab for Making Very Flat Floor Surface of IRS Building

Revision Date: 18 November 2022

A1. Managerial and Supervisory Staffs (Indirect Manpower)


No. Name of Staff Age Position / Latest Number of Number of Years of Remarks
Job Title Education Years of Employment with
Experience the Present Employer

1 (Name of person) Project Manager / 1 Mandatory


Project Coordinator
2 (Name of person) Site Manager 1 Mandatory
3 (Name of person) Scheduler
4 (Name of person) QA/QC Manager /
Coordinator
5 (Name of person) QA/QC Engineer 1 Mandatory
6 (Name of person) HSE Manager
7 (Name of person) HSE Engineer / 1 Mandatory
Inspector / Officer
8 (Name of person) Rigging Manager /
Coordinator
9 (Name of person) Quantity Surveyor
10 (Name of person) Site Civil Supervisor 1 Mandatory
11 (Name of person) Land Surveyor Manager
/ Coordinator / Leader
12 (Name of person) Land Surveyor 1 Mandatory
13 (Name of person) Drafter / Draughtsman
14 (Name of person) Logistics Head
15 (Name of person) Logistics Officer/Staff 1 Mandatory
16 (Name of person) Project Administrator 1 Mandatory

Note:
- The Contractor shall enter above the particulars of the managerial and supervisory staff whom he intends to utilize full time on this project
- During construction, if any additional direct workers are required to meet the construction schedule, the Contractor shall mobilize and execute te work without any
additional cost to RAPI.
- Mobilization of equipment and manpower shall be started after the Contractor receives Letter of Intent, and shall be completed within one month.