Develop the schedule and apply the resources and cost for the Plant Erection project by
creating the Organisation Breakdown Structure and Enterprise Project Structure for the XYZ
Company.
President
Prince
XYZ
Assign the OBS to the EPS elements and projects. For this Plant erection project create a six
day work week calendar with 9:00 AM to 6:00 PM and assign it as project calendar. Also create
a five day work week calendar with timing as 10:00 AM to 6:00 PM and assign this calendar for
two tasks. The start date of the project is May 2, 2009.
The activities are shown with WBS for two levels and the resources are given below. Analyse
the resources by using profile and table. The table given below shows the list of activities.
1 Start of project 0 -
101 Tendering
2 Preparation of Tender 20 1
5 Award of Contract 7 4
102 Procurement
6 Ordering of Equipment 4 5
8 Delivery of Equipment 60 6
13 On load Testing 7 12
14 Commissioning 1 13
15 Finish of project 0 14
Resource Definition
The table given below shows the list of resources that are available for the whole project.
Engineer 3 500/day
Supervisor 4 400/day
Electrician 1 250/day
Labour 20 100/day
Crane 1 450/day
Excavator 1 400/day
Assigning Resources
The table given below shows the list of resources that are needed for each and every activity.
Analyse the resources by using resource profile.
Report
1) Prepare the schedule and find the critical path and finish date of the project.
2) Assign the resources and find the total cost of the project.
3) Track the project after 15 days with some delay in the activities.
4) Prepare the following report
a. Resource Control – Detail by Activity
b. Monthly Project Cask Flow
c. Resource Units Loading – Daily organised by WBS
2) Select the level below which you want to add the level and select ADD.
3) If the newly created level wants to be inside the selected level, use SHIFT RIGHT.
To define Enterprise Project Structure
2) Select the level below which you want to add the level and select ADD.
3) If the newly created level wants to be inside the selected level, use the SHIFT RIGHT.
To create new project
1) Select ENTERPRISE Projects
2) Select the EPS node in which project has to be created. Then ADD.
3) Enter the details about the project in activity details. View Show on Bottom
Project Details.
4) Select
Adding Activities
1) Open project
Activity Sequencing
1) Open the project
2) View Show on Bottom Activity Details
3) Select Relationships
Use either Predecessor or Successor to link the activities and give relationship type and lag.
WBS
To define the WBS for the project
1) Project WBS
2) Click .
3) To add one level below the selected level.
5) Click
Resources
To define the resources
1) Enterprise Resources
To assign resources
1) Project Activities
2) View Show on bottom Activity Details
3) Select Resources
Resource Analysis
View Show on bottom Resource Usage Profile
Update Progress
1) Save the baseline. Project Maintain Baselines
1) Select each and every activity and for each activity, you need to specify the Actual
Start, Actual Finish and the percent complete and the remaining duration for the
activities in status tab
2) Then, you need to schedule the project by specifying the data date that is the status
date what you are going to set.
3) For comparing the actual progress and the baseline schedule go to View Bars and
display the baseline bar.
Report Generation
For taking tabular reports, Tools Reports Reports