ASSIGNMENT NO.

2 –CENTRELINE METHOD OF ESTIMATION


QUESTION NO. 1 CENTRELINE METHOD FOR TWO ROOMED BUILDING NAME – NAKUL V. KORDE
SEMESTER – VI
ESTIMATION AND COSTING

SR. NO. ITEM DESCRIPTION NUMBERS LENGTH BREADTH HEIGHT QUANTITY NOTE

1. EXCAVATION IN FOUNDATION
1 39 1.1 1 42.9 CU. MT. TOTAL CENTRE LENGTH = 10.6X2+6.3X3
= 40.1 M
TOTAL LENGTH = 40.1-(2X1/2 OF BREADTH)
= 40.1-(2X1/2X1.1)
=39 M
2. CONCRETE IN FOUNDATION
1 39 1.1 0.3 12.87 CU. MT.
3. BRICK IN FOUNDATION AND LINTH
1ST FOOTING 1 39 0.8 0.2 6.24
2ND FOOTING 1 39 0.7 0.1 2.73
3RD FOOTING 1 39 0.6 0.1 2.34
4TH FOOTING 1 39 0.5 0.1 1.95
PLINTH WALL 1 39 0.4 0.8 12.48
TOTAL 25.74 CU.MT.
4. DAMP PROOF COURSE 2.5CM THK
1 39 0.4 - 15.6 LENGTH SAME AS FOR PLINTH WALL
DEDUCT DOOR SILLS
2 1.2 0.4 - 0.96
TOTAL 15.6-0.96 =
14.64 CU. MT.