CONCRETE
CLASS AA (4000psi) - CONCRETE MIXTURE
FORMULA:
1ST-2ND 2ND-3RD MID-LANDING
WIDTH (m) 2.4 2.4 2.4
RISE (m) 0.2 0.2 0.2
THREAD (m) 0.3 0.3 1.2
NO. OF STEPS 18 15 1
VOLUME OF CONCRETE (cu.m) 2.592 2.16 0.576
TOTAL VOLUME OF CONCRETE (cu.m) 4.752
12 - NO. OF CEMENT (bags) 57.024
0.5 - VOL. OF SAND (cu.m) 2.376
1- VOL. OF GRAVEL (cu.m) 4.752
0.6 - VOL. OF WATER (cu.m) 2.8512
TOTAL GF SF
VOLUME OF CONCRETE (cu.m) 3.168 2.736
12 - NO. OF CEMENT (bags) 38.016 32.832
0.5 - VOL. OF SAND (cu.m) 1.584 1.368
1 - VOL. OF GRAVEL (cu.m) 3.168 2.736
0.6 - VOL. OF WATER (cu.m) 1.9008 1.6416
TOTAL GF SF TF
VOLUME OF CONCRETE (cu.m) 2.34 2.07 2.07
12 - NO. OF CEMENT (bags) 28.08 24.84 24.84
0.5 - VOL. OF SAND (cu.m) 1.17 1.035 1.035
1 - VOL. OF GRAVEL (cu.m) 2.34 2.07 2.07
0.6 - VOL. OF WATER (cu.m) 1.404 1.242 1.242
STAIRS (OUTSIDE)
CONCRETE
CLASS AA (4000psi) - CONCRETE MIXTURE
FORMULA:
LEFT RIGHT REAR MID-LANDING
WIDTH (m) 2 2 2 2
RISE (m) 0.1 0.1 0.1 0.1
THREAD (m) 0.3 0.3 0.3 0.5
NO. OF STEPS 2 2 2 1
VOLUME OF CONCRETE (cu.m) 0.12 0.12 0.12 0.1
TOTAL VOLUME OF CONCRETE (cu.m) 0.46
12 - NO. OF CEMENT (bags) 5.52
0.5 - VOL. OF SAND (cu.m) 0.23
1- VOL. OF GRAVEL (cu.m) 0.46
0.6 - VOL. OF WATER (cu.m) 0.276
RAMPS (OUTSIDE)
CONCRETE
CLASS AA (4000psi) - CONCRETE MIXTURE
FORMULA: LEFT RIGHT MID-LANDING
WIDTH (m) 3 3 3
RISE (m) 0.3 0.3 0.3
THREAD (m) 1.4 1.4 0.8
NO. OF STEPS 1 1 1
VOLUME OF CONCRETE (cu.m) 1.26 1.26 0.72
TOTAL VOLUME OF CONCRETE (cu.m) 2.52
12 - NO. OF CEMENT (bags) 30.24
0.5 - VOL. OF SAND (cu.m) 1.26
1- VOL. OF GRAVEL (cu.m) 2.52
0.6 - VOL. OF WATER (cu.m) 1.512
RAMPS (OUTSIDE)
CONCRETE
CLASS AA (4000psi) - CONCRETE MIXTURE
FORMULA:
REAR MID-LANDING
WIDTH (m) 2 2
RISE (m) 0.3 0.3
THREAD (m) 1.4 1.4
NO. OF STEPS 1 1
VOLUME OF CONCRETE (cu.m) 0.84 0.84
TOTAL VOLUME OF CONCRETE (cu.m) 1.68
12 - NO. OF CEMENT (bags) 20.16
0.5 - VOL. OF SAND (cu.m) 0.84
1- VOL. OF GRAVEL (cu.m) 1.68
0.6 - VOL. OF WATER (cu.m) 1.008
SF-MID
HORIZONTAL/VERTICAL cc=15mm dleng=65mm Steps = 9
STAIRS W Spacing R T No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP TOP) 2.4 0.26 0.4 0.6 10.2308 0.01 0.38 0.58 0.4450 0.6450 1.0900 6 5.5046 5 1.8586 0.174
TOTAL 16.7273 3.1271
PARALLEL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP BOT1) 2.4 0.26 5.6 22.5385 0.01 3.363 6 1.7841 1 12.6328 0.383
(TEMP BOT2) 2.4 0.26 4.7 19.0769 0.01 3.363 6 1.7841 1 10.6926 0.324
GF STEP 2.4 9 0.01 3.363 6 1.7841 1 5.0445 0.153
TOTAL 28.3699 0.860
DIAGONAL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
TOP 2.4 0.17 6.2 15.1176 0.012 6.2 6 1.0667 1 15.6216 0.257
BOT 2.4 0.17 5 15.1176 0.012 5 6 1.2000 1 12.5980 0.257
TOTAL 28.2196 0.513
MID-(SF&TF)
HORIZONTAL/VERTICAL cc=15mm dleng=65mm Steps = 8
STAIRS W Spacing R T No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP TOP) 2.4 0.26 0.4 0.6 10.2308 0.01 0.38 0.58 0.4450 0.6450 1.0900 6 5.5046 5 1.8586 0.174
TOTAL 14.8687 3.1271
PARALLEL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP BOT1) 2.4 0.26 4 16.3846 0.01 3.363 6 1.7841 1 9.1836 0.278
(TEMP BOT2) 2.4 0.26 4.6 18.6923 0.01 3.363 6 1.7841 1 18.6923 0.317
GF STEP 2.4 8 0.01 3.363 6 1.7841 1 8.0000 0.136
TOTAL 35.8759 0.731
DIAGONAL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
TOP 2.4 0.17 6 15.1176 0.012 6 6 1.0333 1 15.1176 0.257
BOT 2.4 0.17 5.5 15.1176 0.012 5.5 6 1.0909 1 13.8578 0.257
TOTAL 28.9755 0.513
FIRE EXIT
GF-MID
HORIZONTAL/VERTICAL cc=15mm dleng=65mm Steps = 12
STAIRS W Spacing R T No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP TOP) 2.4 0.26 0.4 0.6 10.2308 0.01 0.38 0.58 0.4450 0.6450 1.0900 6 5.5046 5 1.8586 0.174
TOTAL 22.3031 3.1271
PARALLEL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP BOT1) 2.4 0.26 5.5 22.1538 0.01 3.363 6 1.7841 1 12.4172 0.376
(TEMP BOT2) 2.4 0.26 4.8 19.4615 0.01 3.363 6 1.7841 1 10.9082 0.330
GF STEP 2.4 12 0.01 3.363 6 1.7841 1 6.7260 0.204
TOTAL 30.0514 0.910
DIAGONAL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
TOP 2.4 0.15 6.6 17.0000 0.012 6.6 6 1.1333 1 18.7000 0.289
BOT 2.4 0.15 5.5 17.0000 0.012 5.5 6 1.0909 1 15.5833 0.289
TOTAL 34.2833 0.577
(SF&TF)-MID
HORIZONTAL/VERTICAL cc=15mm dleng=65mm Steps = 9
STAIRS W Spacing R T No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP TOP) 2.4 0.26 0.4 0.6 10.2308 0.01 0.38 0.58 0.4450 0.6450 1.0900 6 5.5046 5 1.8586 0.174
TOTAL 16.7273 3.1271
PARALLEL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP BOT1) 2.4 0.26 4.9 19.8462 0.01 3.363 6 1.7841 1 11.1238 0.337
(TEMP BOT2) 2.4 0.26 6.8 27.1538 0.01 3.363 6 1.7841 1 15.2197 0.461
GF STEP 2.4 9 0.01 3.363 6 1.7841 1 5.0445 0.153
TOTAL 31.3880 0.951
DIAGONAL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
TOP 2.4 0.17 5.5 15.1176 0.012 5.5 6 1.0909 1 13.8578 0.257
BOT 2.4 0.17 7.1 15.1176 0.012 7.1 6 0.8451 0 17.8892 0.257
TOTAL 31.7471 0.513
MID-(SF&TF&RD)
HORIZONTAL/VERTICAL cc=15mm dleng=65mm Steps = 8
STAIRS W Spacing R T No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP TOP) 2.4 0.26 0.4 0.6 10.2308 0.01 0.38 0.58 0.4450 0.6450 1.0900 6 5.5046 5 1.8586 0.174
TOTAL 14.8687 3.1271
PARALLEL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
(TEMP BOT1) 2.4 0.26 5.7 22.9231 0.01 3.363 6 1.7841 1 12.8484 0.389
(TEMP BOT2) 2.4 0.26 4.9 19.8462 0.01 3.363 6 1.7841 1 11.1238 0.337
GF STEP 2.4 8 0.01 3.363 6 1.7841 1 4.4840 0.136
TOTAL 28.4562 0.862
DIAGONAL
STAIRS W Spacing L No. of Bars ø Bar Length R Length T Total Length R Total Length T Total Length RL Com. Length (m) Cuts of 6m Say No. of Steel Bars #16 G.I. wire (kg)
TOP 2.4 0.17 6.3 15.1176 0.012 6.3 6 1.0833 1 15.8735 0.257
BOT 2.4 0.17 5.2 15.1176 0.012 5.2 6 1.1538 1 13.1020 0.257
TOTAL 28.9755 0.513