Plain Concrete
FOUNDATION
FOOTING NO. Length (m) Width (m) Depth (m) Volume (m) Quantity Cement (bag) Sand (m^3) Gravel (m^3)
FD1 1.4 1.4 0.4 0.78 5 29.40 1.96 3.92
FD2 1.2 1.2 0.35 0.50 4 15.12 1.01 2.02
FD3 1 1 0.35 0.35 3 7.88 0.53 1.05
FOOTING SUMMARY
CEMENT (Bags) 52.40
SAND (cu.m.) 3.49 m^3
GRAVEL (cu.m.) 6.99 m^3
COLUMN
COLUMN NO. Length (m) Width (m) Depth (m) Volume (m) Quantity Cement (bag) Sand (m^3) Gravel (m^3)
CD1 0.45 0.3 11.5 1.55 11 128.08 8.54 17.08
CD2 0.45 0.3 11.5 1.55 1 11.64 0.78 1.55
COLUMN SUMMARY
CEMENT (Bags) 139.73
SAND (cu.m.) 9.32 m^3
GRAVEL (cu.m.) 18.63 m^3
BEAM
BEAM NO. Length (m) Width (m) Depth (m) Volume (m) Quantity Cement (bag) Sand (m^3) Gravel (m^3)
BD1 13 0.4 0.6 3.12 6 140.40 9.36 18.72
BD2 7.6 0.4 0.6 1.82 12 164.16 10.94 21.89
BD3 13 0.4 0.6 3.12 3 70.20 4.68 9.36
BD4 7.6 0.4 0.6 1.82 6 82.08 5.47 10.94
BD5 13 0.4 0.6 3.12 3 70.20 4.68 9.36
BD6 7.6 0.4 0.6 1.82 6 82.08 5.47 10.94
BEAM SUMMARY
CEMENT (Bags) 609.12
SAND (cu.m.) 40.61 m^3
GRAVEL (cu.m.) 81.22 m^3
SLAB
SLAB NO. Length (m) Width (m) Depth (m) Volume (m) Quantity Cement (bag) Sand (m^3) Gravel (m^3)
S1 3.05 2.800 0.125 1.07 3.000 24.02 1.60 3.20
S2 4.55 2.800 0.125 1.59 3.000 35.83 2.39 4.78
S3 3.05 3.000 0.125 1.14 3.000 25.73 1.72 3.43
S4 4.55 3.000 0.125 1.71 3.000 38.39 2.56 5.12
S5 3.05 3.000 0.125 1.14 3.000 25.73 1.72 3.43
S6 4.55 3.000 0.125 1.71 3.000 38.39 2.56 5.12
S7 3.05 2.050 0.125 0.78 3.000 17.59 1.17 2.34
S8 4.55 2.050 0.125 1.17 3.000 26.23 1.75 3.50
S9 3.05 2.150 0.125 0.82 3.000 18.44 1.23 2.46
S10 4.55 2.150 0.125 1.22 3.000 27.51 1.83 3.67
SLAB SUMMARY
CEMENT (Bags) 277.88
SAND (cu.m.) 18.53 m^3
GRAVEL (cu.m.) 37.05 m^3
Masonry
Plastering
CEMENT BAGS (CLASS B)
TYPE OF WALL TOTAL AREA 40 KG 50 KG Sand
EXTERIOR 377.33 144.90 114.71 12.07 m^3
INTERIOR 234.75 90.15 71.36 7.51 m^3
CHB Reinforcement
BARS LENGTH (EXTERIOR PART)
Vertical Reinforcement Horizontal Reinforcement
163 pcs 10 mm x 5 mm and 4 pcs of 10 mm x 6 mm 164 pcs of 10 mm x 5 mm, 1 pc of 10 mm x 6 mm, and 2 pcs of 10 mm x 7.5 mm
17 pcs. / 25 cm
Metal Reinforcement
1. One Way Slab
Short Span (m) Long Span (m) Floor Area (m^2)
S8 2.05 4.25 8.7125
S10 1.85 4.25 7.8625
6. Columns - stirrups
HEIGHT (m) No. of Columns Base of Column Width of column No. of lateral ties per colum Length of lateral tie per column Total no. of lateral ties Total length of lateral ties
Footing to Ground floor spacing at 30 cm
CD1 w/ FD1 2.4 m 4 - 0.3 m 0.45 m 8.00 - 1.33 m 32 43 m
CD1 w/ FD2 2.35 m 4 - 0.3 m 0.45 m 8.00 - 1.33 m 32 43 m
CD1 w/ FD3 2.35 m 3 - 0.3 m 0.45 m 8.00 - 1.33 m 24 32 m
CD2 w/ FD1 2.4 m 1 - 0.3 m 0.45 m 8.00 - 1.37 m 8 11 m
Ground floor to 2nd floor
CD1 3.05 m 11 - 0.3 m 0.45 m 11.00 - 1.33 m 121 161 m
CD2 3.05 m 1 - 0.3 m 0.45 m 11.00 - 1.37 m 11 16 m
2nd floor to 3rd floor
CD1 2.85 m 11 - 0.3 m 0.45 m 10.00 - 1.33 m 110 147 m
CD2 2.85 m 1 - 0.3 m 0.45 m 10.00 - 1.37 m 10 14 m
3rd floor to Roof deck
CD1 2.85 m 11 - 0.3 m 0.45 m 10.00 - 1.33 m 110 147 m
CD2 2.85 m 1 - 0.3 m 0.45 m 10.00 - 1.37 m 10 14 m
Roof deck
CD1 2.75 m 10 - 0.3 m 0.45 m 10.00 - 1.33 m 100 133 m
CD2 2.75 m 1 - 0.3 m 0.45 m 10.00 - 1.37 m 10 14 m
129.166667 m
7. Beam - Stirrups
Clear span (m) Spacing of stirrups (cm) Length of stirrups (m) No. of stirrups per beam (pcs.) total length of stirrups (m) Quantity
BD1
Type 1 1.35 m 20 cm 1.792 m 7.00 pcs 38 m 3
Type 2 1.65 m 20 cm 1.792 m 8.25 pcs 45 m 3
Type 3 2.6 m 20 cm 1.792 m 13.00 pcs 70 m 3
Type 4 2.6 m 20 cm 1.792 m 13.00 pcs 70 m 3
Type 5 2.4 m 20 cm 1.792 m 12.00 pcs 65 m 3
BD2
Type 1 2.65 m 15 cm 1.792 m 17.67 pcs 190 m 6
Type 2 3.75 m 15 cm 1.792 m 25.00 pcs 269 m 6
BD3
Type 1 1.35 m 30 cm 1.792 m 4.50 pcs 25 m 3
Type 2 1.65 m 30 cm 1.792 m 5.50 pcs 30 m 3
Type 3 2.6 m 30 cm 1.792 m 8.67 pcs 47 m 3
Type 4 2.6 m 30 cm 1.792 m 8.67 pcs 47 m 3
Type 5 2.4 m 30 cm 1.792 m 8.00 pcs 44 m 3
BD4
Type 1 2.65 m 50 cm 1.792 m 5.30 pcs 57 m 6
Type 2 3.75 m 50 cm 1.792 m 7.50 pcs 81 m 6
BD5
Type 1 1.35 m 30 cm 1.792 m 4.50 pcs 25 m 3
Type 2 1.65 m 30 cm 1.792 m 5.50 pcs 30 m 3
Type 3 2.6 m 30 cm 1.792 m 8.67 pcs 47 m 3
Type 4 2.6 m 30 cm 1.792 m 8.67 pcs 47 m 3
Type 5 2.4 m 30 cm 1.792 m 8.00 pcs 44 m 3
BD6
Type 1 2.65 m 40 cm 1.792 m 6.63 pcs 72 m 6
Type 2 3.75 m 40 cm 1.792 m 9.38 pcs 101 m 6
Lumber
Ceiling board AREA (hollow parts removed)
1st floor 90.34 m^2
2nd floor 88.47 m^2
3rd floor 90.87 m^2
roof deck 26.78 m^2
Ceiling joist
1st floor 90.34 m^2
2nd floor 88.47 m^2
3rd floor 90.87 m^2
roof deck 26.78 m^2
Tilework
Floor Area Mosaic Tiles (12''x12'') Tile Adhesive (5sq.m./25kg bag) Tile Grout (8 sq.m./2kg bag)
Ground Floor 57.63 m^2 620.07 pcs 11.53 bags 14.41 bags
Second Floor 99.08 m^2 1066.07 pcs 19.82 bags 24.77 bags
Third Floor 99.08 m^2 1066.07 pcs 19.82 bags 24.77 bags
Roof Deck 91.59 m^2 985.46 pcs 18.32 bags 22.90 bags
3738.00 pcs 70.00 bags 87.00 bags
Paint
Area (doors and windows removed) Water for Concrete Neutralizer Latex Paint (35sq.m./4 liters, 2 coats,
Neutralizer (1 pint/2.5gal of water)
(per 30sq.m.) additional 10%)
1. Outer Walls
1st floor 97.71 m^2 3.26 gal 1.30 pint 6.14 cans
2nd floor 98.83 m^2 3.29 gal 1.32 pint 6.21 cans
3rd floor 109.99 m^2 3.67 gal 1.47 pint 6.91 cans
Roof Deck 56.76 m^2 1.89 gal 0.76 pint 3.57 cans
363.29 m^2 12.11 gal 5.00 pint 23.00 cans
Area (doors and windows removed)
2. Inner Walls
1st floor 55.30 m^2 1.84 gal 0.74 pint 3.48 cans
2nd floor 45.17 m^2 1.51 gal 0.60 pint 2.84 cans
3rd floor 88.17 m^2 2.94 gal 1.18 pint 5.54 cans
Roof Deck 34.42 m^2 1.15 gal 0.46 pint 2.16 cans