Pending Work PT.

ANUGRAH - November 2022


SP2
SCHEDULE
No Work Description Engineering Scope
First Schedule Forecase Date
1 Lighting Machine Area (Type-Weld support, Painting) As build DWG tray ladder,
2 Street Lighting Add cable pulling or update cable schedule and wiring termination,
3 Insect Killer 5 Nov'2022 25 Nov'2022
4 Cable Tag
5 Marking Tray Line & Convering
TM14.1
SCHEDULE
No Work Description Engineering Scope
First Schedule Forecase Date
1 Lighting Lt. 2 As build DWG tray ladder,
2 Exit Lamp, Insect Killer Add cable pulling or update cable schedule and wiring termination,
3 Cable Tag
4 Grounding Bonding Cable Tray 25 Nov'2022
5 Nov'2022
5 Fire Sealing
6 Marking Tray Line & Convering
7 Punch list Item
8 Electrical General Cleaning
CVT
SCHEDULE
No Work Description Engineering Scope
First Schedule Forecase Date
1 Pulling Cable North & South As build DWG tray ladder,
2 Termination Add cable pulling or update cable schedule and wiring termination,
3 Tray Ladder 200 battere room
4 Tray Ladder 200 CVT south (See Drawing cable tray lay out)
5 Lighting Raw Mill Not Termination With Permanent Power
6 Lighting Office, Stop Contact, Saklar North & South
7 Lighting Packaging Area Done 845 From 1452
8 Lighting Converting lt. 2 done 200 from 206
25 Nov'2022
9 Cable Tag
10 Grounding Site Equipment 05 November 2022
11 Convering Tray MV Cable North & South
12 Grounding Bonding Jumper Cable Ttray Installation
13 Fire Sealing
14 Closing Punch list item
15 Electrical General Cleaning
16 Marking Tray Line & Convering
17 Checker plate MCC North & South
18 18 Set Panel 500x400x150D
19 11 Set Panel Interfold operate
AWH
SCHEDULE
No Work Description Engineering Scope
First Schedule Forecase Date
1 Lighting Fixture Tissue Rack & Loading Bay As build DWG tray ladder,
2 Grounding Bonding Cable Tray Add cable pulling or update cable schedule and wiring termination,
3 Fire Sealing 25 Nov'2022
05 Nov'2022
4 Cable Tag
5 Checker Plate
6 Marking Tray Line & Convering

TM14.2
SCHEDULE
No Work Description Engineering Scope
First Schedule Forecase Date
1 Pulling Cable As build DWG tray ladder,
2 Termination Add cable pulling or update cable schedule and wiring termination,
3 Grounding System & Grounding Bonding
4 Lighting Fixture Cable room, Trafo room, Lt.2 & 3
15 Dec'2022
5 Stop Contact & Saklar
6 HVAC, Tray Lt. 2 & 3
7 Cable Tag
8 Marking Tray Line & Convering
9 Checker plate MCC North & South
10 Electrical General Cleaning
TM14.3 & TM 14.4
SCHEDULE
No Work Description Engineering Scope
First Schedule Forecase Date
1 4 PCS Trafo TM14.3
25 Oct'22
2 4 PCS Trafo TM14.4

MahesaHidayat_20nov22