MATERIAL TRANSPORTATION
1010500 Material Transportation PLAN 4.08% 0.82% 0.82% 0.82% 0.82% 0.82%
ACT 0.17 0.30 0.29 0.29 0.44
CONSTRUCTION
1010000 PREPARATION & CLEANING WORK
1010100 Direction Kit PLAN 0.37% 0.19% 0.19%
ACT 0.28
1010200 Area Prep. Survey & Line M PLAN 0.58% 0.29% 0.29%
ACT 0.17
1010300 Mobilization and Demobilization PLAN 1.84% 0.00% 0.61% 0.61% 0.61%
ACT 0.83
1010400 Stockyard PLAN 0.40% 0.20% 0.20%
ACT 0.28
1010600 Safety Equipment on Si te PLAN 0.75% 0.00% 0.38% 0.38%
ACT 0.19
PIPELINE INSTALLATION
1030000 PIPING WORKS
1030100 Pipe Stringing PLAN 6.01% 0.42% 0.42% 0.44% 0.42% 0.42% 0.44% 0.42% 0.44% 0.42% 0.44% 0.42% 0.43% 0.42% 0.44% 0.00% 0.00%
ACT 0.20 0.78 0.60 0.37 0.36
1030300 Welding (Cuting, Bevel & Fi ting ) PLAN 32.22% 0.00% 0.00% 1.17% 1.14% 2.73% 3.94% 3.22% 2.79% 3.42% 3.48% 2.30% 2.67% 2.27% 1.56% 1.52% 0.00%
ACT 2.21 2.85 2.60 1.69
1040100 NDE Test PLAN 7.31% 0.00% 0.00% 0.49% 0.49% 0.49% 0.73% 0.73% 0.73% 0.73% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
104.1 Non Destructive Test (100%) 7.31% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
ACT 0.15 0.26 0.19 0.74
1031400 Joint Coating (Heat Shrink Sl ive) PLAN 4.38% 0.00% 0.00% 0.31% 0.31% 0.31% 0.40% 0.40% 0.40% 0.40% 0.31% 0.31% 0.31% 0.31% 0.31% 0.27%
ACT 0.00 0.07 0.08 7.72% 7.72% 7.72% 7.72% 7.72% 7.72% 7.72%
1020000 Trenching (Open Cut) Incl Backfi ll PLAN 10.57% 0.00% 0.45% 0.66% 0.69% 0.90% 0.66% 0.93% 1.21% 1.24% 0.90% 0.66% 0.68% 0.66% 0.90% 0.03%
ACT 0.027 1.07 3.04
1030200 Pipe Lowering In PLAN 6.87% 0.00% 0.00% 0.48% 0.51% 0.48% 0.48% 0.67% 0.64% 0.66% 0.48% 0.48% 0.51% 0.48% 0.50% 0.48%
ACT 0.10 0.06
1030500 Installation Valves PLAN 5.82% 0.00% 0.00% 0.37% 0.60% 0.30% 0.39% 0.58% 0.64% 0.57% 0.55% 0.32% 0.60% 0.28% 0.30% 0.32%
ACT
1020000 CIVIL WORKS & REINSTATEMENT
1020400 Repair Works PLAN 14.32% 0.00% 0.50% 0.76% 0.76% 1.49% 1.01% 1.49% 0.76% 1.26% 1.99% 1.26% 0.76% 0.76% 1.49% 0.07%
ACT
1020500 Si gn Marker Installation PLAN 1.32% 0.00% 0.06% 0.07% 0.12% 0.12% 0.12% 0.12% 0.10% 0.14% 0.10% 0.07% 0.06% 0.07% 0.19%
ACT
1020600 Block Valve Box Installation PLAN 3.16% 0.19% 0.64% 0.19% 0.35% 0.14% 0.50% 0.49% 0.15% 0.49%
ACT
WEEKLY PROGRES 100.00% 0.68% 2.53% 2.68% 5.66% 5.80% 7.33% 8.84% 8.73% 8.66% 8.66% 8.19% 7.58% 7.51% 5.89% 5.32% 5.28% 0.68%
PLAN
PROGRES ACUMMULATIVE 0.68% 3.20% 5.88% 11.54% 17.34% 24.68% 33.52% 42.25% 50.91% 59.56% 67.75% 75.33% 82.84% 88.73% 94.04% 99.32% 100.00%
WEEKLY PROGRES 1.31% 1.34% 3.44% 3.95% 4.70% 6.40%
ACTUAL
PROGRES ACUMMULATIVE 0.00% 0.00% 1.31% 2.65% 6.09% 10.04% 14.75% 21.15%
Approved by ; Prepared by ;
NOTES : Client Company
PIC PIC
0 Issued for approval Date:__________ CONSTRUCTION MANAGER SITE MANAGER
PERIOD PROGRESS WEEK 8th
FROM 22 UP TO 28
CLIENT :_______________________________________________
OWNER :_______________________________________________ WEEKLY PROGRESS
PROJECT :_______________________________________________
:_______________________________________________
LOCATION :______________________________________________
PROJECT NAME : ….................................................................
PROJECT CONTROL
PIC
COMPANY NAME_____________
SITE MANAGER
PIC
PROJECT CONTROL
PIC
CLIENT NAME________________
SITE MANAGER
PIC
50 DAYS CALENDAR RE-SCHEDULE (RECOVERY SCHEDULE)
CLIENT :_______________________________________________
OWNER :_______________________________________________ WORK PROGRESS & " S " C U R V E
PROJECT :_______________________________________________
:_______________________________________________
THE PROJECT NAME : ….................................................................... Rev. 01.
LOCATION :______________________________________________
MATERIAL TRANSPORTATION
100%
1010500 Material Transportation Plan 4.08% 0.82% 0.82% 0.82% 0.82% 0.82% 1.04% 1.04% 0.52%
Act. 0.17 0.30 0.29 0.29 0.44 0.36 0.75 0.61
CONSTRUCTION
1010000 PREPARATION & CLEANING WORK 90%
1010100 Direction Kit Plan 0.37% 0.19% 0.19% 0.05% 0.05%
Act. 0.28 0.05 0.05 0.003
1010200 Area Prep. Survey & Line M Plan 0.58% 0.29% 0.29% 0.21% 0.21%
Act. 0.17 0.21 0.21 0.004
80%
1010300 Mobilization and Demobilization Plan 1.84% 0.00% 0.61% 0.61% 0.34% 0.34% 0.34%
Act. 0.83 0.34 0.63
1010400 Stockyard Plan 0.40% 0.20% 0.20% 0.12% 0.12% 70%
Act. 0.28 0.12 0.02 0.06
1010600 Safety Equipment on Site Plan 0.75% 0.00% 0.38% 0.38% 0.19% 0.38%
Act. 0.19 0.19 0.38 0.04
PIPELINE INSTALLATION 60%
1030000 PIPING WORKS
1030100 Pipe Stringing Plan 6.01% 0.42% 0.42% 0.44% 0.42% 0.42% 0.44% 0.42% 0.75% 0.76% 0.76% 0.75%
Act. 0.20 0.78 0.60 0.37 0.36 0.44 0.41 0.22
50%
1030300 Welding (Cuting, Bevel & Fiting ) Plan 32.22% 0.00% 0.00% 1.17% 1.14% 2.73% 3.94% 3.22% 2.60% 5.63% 5.59% 3.81% 2.38%
Act. 2.21 2.85 2.60 1.69 1.34 3.17 0.98
1040100 NDE Test Plan 7.31% 0.00% 0.00% 0.49% 0.49% 0.49% 0.73% 0.73% 1.20% 1.20% 0.80% 0.70% 0.48%
Act. 0.15 0.26 0.19 0.74 0.72 0.48 0.42 40%
1031400 Joint Coating (Heat Shrink Slive) Plan 4.38% 0.00% 0.00% 0.31% 0.31% 0.31% 0.40% 0.40% 0.66% 1.08% 1.10% 0.51% 0.51% 0.51%
Act. 0.00 0.07 0.08 0.11 0.04 0.06
1020000 Trenching (Open Cut) Incl Backfill Plan 10.57% 0.00% 0.45% 0.66% 0.69% 0.90% 0.66% 0.93% 1.99% 3.11% 2.64% 1.34% 1.37% 0.12%
Act. 0.03 1.07 3.04 0.16 0.00 0.09
30%
1030200 Pipe Lowering In Plan 6.87% 0.00% 0.00% 0.48% 0.51% 0.48% 0.48% 0.67% 1.06% 1.09% 0.79% 0.79% 0.84% 1.77% 0.53%
Act. 0.10 0.06 0.18 0.04 0.09
1030500 Valves Installation Plan 5.82% 0.00% 0.00% 0.37% 0.60% 0.30% 0.39% 0.58% 1.05% 1.11% 0.99% 0.93% 0.91% 0.52% 0.31% 20%
Act.
1020000 CIVIL WORKS & REINSTATEMENT
1020400 Repair Works Plan 14.32% 0.00% 0.50% 0.76% 0.76% 1.49% 1.01% 2.45% 1.24% 2.06% 3.28% 2.06% 1.98% 1.24%
Act. 10%
1020500 Sign Marker Installation Plan 1.32% 0.00% 0.06% 0.07% 0.12% 0.12% 0.12% 0.19% 0.21% 0.31% 0.25% 0.19% 0.16%
Act.
1020600 Block Valve Box Installation Plan 3.16% 0.00% 0.19% 0.64% 0.00% 0.19% 0.35% 0.23% 0.83% 1.38% 0.40% 0.20% 0.20%
0%
Act.
WEEKLY CUMMULATIVE ORIGINAL PLAN PROGRESS WEEK LY CUMMULATIVE RE COVERY PLAN PROGRES S
WEEKLY CUMMULATIVE ACTUAL PROGRESS
TOTAL 100.00%
WEEKLY ORIGINAL PLAN PROGRESS 0.00% 0.68% 2.53% 2.68% 5.85% 6.44% 7.33% 8.84% 8.44% 8.61% 8.81% 8.05% 7.08% 7.51% 5.89% 5.32% 5.28% 0.68%
WEEKLY RECOVERY PLAN PROGRESS 0.00% 0.68% 2.53% 2.68% 5.85% 6.44% 7.33% 8.84% 8.44% 13.58% 18.20% 17.67% 12.76% 8.95% 5.27% 2.09% 0.34%
PLAN
WEEKLY CUMMULATIVE ORIGINAL PLAN PROGRESS 0.00% 0.68% 3.20% 5.88% 11.73% 18.18% 25.51% 34.36% 42.79% 51.40% 60.21% 68.26% 75.33% 82.84% 88.73% 94.04% 99.32% 100.00%
WEEKLY CUMMULATIVE RECOVERY PLAN PROGRESS 0.00% 0.00% 0.00% 1.31% 2.65% 6.09% 10.04% 14.75% 21.15% 34.73% 52.93% 70.59% 83.36% 92.31% 97.58% 99.66% 100.00%
WEEKLY ACTUAL PROGRESS 0.00% 0.00% 0.00% 1.31% 1.34% 3.44% 3.95% 4.70% 6.40%
ACTUAL
WEEKLY CUMMULATIVE ACTUAL PROGRESS 0.00% 0.00% 0.00% 1.31% 2.65% 6.09% 10.04% 14.75% 21.15%
Approved by ; Prepared by ;
NOTES : The Client The Company
PIC PIC
Issued for approval Date____________ CONSTRUCTION MANAGER SITE MANAGER
50 DAYS CALENDAR RE-SCHEDULE (RECOVERY SCHEDULE)
CLIENT :_______________________________________________
OWNER :_______________________________________________ TABLE OF TARGET PROGRESS
PROJECT :_______________________________________________
:_______________________________________________
LOCATION :______________________________________________
THE PROJECT NAME : …...........................................................................