OWNER :_______________________________________________ WORK PROGRESS & " S " C U R V E


PROJECT :_______________________________________________
:_______________________________________________
PROJECT NAME : …............................................................
LOCATI ON :______________________________________________

PROGRESS PERIOD FROM_____________UP TO____________________


NO DESCRIPTION WEIGHT MONTH-YEAR MONTH-YEAR MONTH-YEAR MONTH-YEAR
5 - 10 11 - 17 18 - 24 25 - 01 02 - 08 09 - 15 16 - 22 23 - 29 30 - 5 06 - 12 13 - 19 20 - 26 27 - 02 03 - 09 10 - 16 17 - 23 24 - 30
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

MATERIAL TRANSPORTATION
1010500 Material Transportation PLAN 4.08% 0.82% 0.82% 0.82% 0.82% 0.82%
ACT 0.17 0.30 0.29 0.29 0.44
CONSTRUCTION
1010000 PREPARATION & CLEANING WORK
1010100 Direction Kit PLAN 0.37% 0.19% 0.19%
ACT 0.28
1010200 Area Prep. Survey & Line M PLAN 0.58% 0.29% 0.29%
ACT 0.17
1010300 Mobilization and Demobilization PLAN 1.84% 0.00% 0.61% 0.61% 0.61%
ACT 0.83
1010400 Stockyard PLAN 0.40% 0.20% 0.20%
ACT 0.28
1010600 Safety Equipment on Si te PLAN 0.75% 0.00% 0.38% 0.38%
ACT 0.19
PIPELINE INSTALLATION
1030000 PIPING WORKS
1030100 Pipe Stringing PLAN 6.01% 0.42% 0.42% 0.44% 0.42% 0.42% 0.44% 0.42% 0.44% 0.42% 0.44% 0.42% 0.43% 0.42% 0.44% 0.00% 0.00%
ACT 0.20 0.78 0.60 0.37 0.36
1030300 Welding (Cuting, Bevel & Fi ting ) PLAN 32.22% 0.00% 0.00% 1.17% 1.14% 2.73% 3.94% 3.22% 2.79% 3.42% 3.48% 2.30% 2.67% 2.27% 1.56% 1.52% 0.00%
ACT 2.21 2.85 2.60 1.69
1040100 NDE Test PLAN 7.31% 0.00% 0.00% 0.49% 0.49% 0.49% 0.73% 0.73% 0.73% 0.73% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
104.1 Non Destructive Test (100%) 7.31% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
ACT 0.15 0.26 0.19 0.74
1031400 Joint Coating (Heat Shrink Sl ive) PLAN 4.38% 0.00% 0.00% 0.31% 0.31% 0.31% 0.40% 0.40% 0.40% 0.40% 0.31% 0.31% 0.31% 0.31% 0.31% 0.27%
ACT 0.00 0.07 0.08 7.72% 7.72% 7.72% 7.72% 7.72% 7.72% 7.72%
1020000 Trenching (Open Cut) Incl Backfi ll PLAN 10.57% 0.00% 0.45% 0.66% 0.69% 0.90% 0.66% 0.93% 1.21% 1.24% 0.90% 0.66% 0.68% 0.66% 0.90% 0.03%
ACT 0.027 1.07 3.04
1030200 Pipe Lowering In PLAN 6.87% 0.00% 0.00% 0.48% 0.51% 0.48% 0.48% 0.67% 0.64% 0.66% 0.48% 0.48% 0.51% 0.48% 0.50% 0.48%
ACT 0.10 0.06
1030500 Installation Valves PLAN 5.82% 0.00% 0.00% 0.37% 0.60% 0.30% 0.39% 0.58% 0.64% 0.57% 0.55% 0.32% 0.60% 0.28% 0.30% 0.32%
ACT
1020000 CIVIL WORKS & REINSTATEMENT
1020400 Repair Works PLAN 14.32% 0.00% 0.50% 0.76% 0.76% 1.49% 1.01% 1.49% 0.76% 1.26% 1.99% 1.26% 0.76% 0.76% 1.49% 0.07%
ACT
1020500 Si gn Marker Installation PLAN 1.32% 0.00% 0.06% 0.07% 0.12% 0.12% 0.12% 0.12% 0.10% 0.14% 0.10% 0.07% 0.06% 0.07% 0.19%
ACT
1020600 Block Valve Box Installation PLAN 3.16% 0.19% 0.64% 0.19% 0.35% 0.14% 0.50% 0.49% 0.15% 0.49%
ACT
WEEKLY PROGRES 100.00% 0.68% 2.53% 2.68% 5.66% 5.80% 7.33% 8.84% 8.73% 8.66% 8.66% 8.19% 7.58% 7.51% 5.89% 5.32% 5.28% 0.68%
PLAN
PROGRES ACUMMULATIVE 0.68% 3.20% 5.88% 11.54% 17.34% 24.68% 33.52% 42.25% 50.91% 59.56% 67.75% 75.33% 82.84% 88.73% 94.04% 99.32% 100.00%
WEEKLY PROGRES 1.31% 1.34% 3.44% 3.95% 4.70% 6.40%
ACTUAL
PROGRES ACUMMULATIVE 0.00% 0.00% 1.31% 2.65% 6.09% 10.04% 14.75% 21.15%
Approved by ; Prepared by ;
NOTES : Client Company

PIC PIC
0 Issued for approval Date:__________ CONSTRUCTION MANAGER SITE MANAGER
PERIOD PROGRESS WEEK 8th

FROM 22 UP TO 28
CLIENT :_______________________________________________
OWNER :_______________________________________________ WEEKLY PROGRESS
PROJECT :_______________________________________________
:_______________________________________________
LOCATION :______________________________________________
PROJECT NAME : ….................................................................

CONTRACT APPROVED PROGRESS


NO DESCRIPTION UNIT WEIGHT PREVIOUS THIS PERIODE TO DATE NOTES
QTY FACTOR WEIGHT PROG. WEIGHT PROG. WEIGHT PROG.
QTY QTY QTY
% % % % % % %
MATERIAL TRANSPORTATION
1010500 Material Transportation ls 1 4.08 0.40 1.65 40.38% 0.11 0.44 10.69% 0.51 2.08 51.07%
CONSTRUCTION
1010000 PREPARATION & CLEANING WORK
1010100 Direction Kit ls 1 0.37 0.75 0.28 75.00% 0.75 0.28 75.00%
1010200 Area Prep. Incl. Survey & Line Marker ls 1 0.58 0.29 0.17 28.64% 0.29 0.17 28.64%
1010300 Mobilization dan Demobilization ls 1 1.84 0.45 0.83 45.00% 0.45 0.83 45.00%
1010400 Stockyard ls 1 0.40 0.70 0.28 70.00% 0.70 0.28 70.00%
1010411 Dia 24"
1010600 Safety Equipment on Site ls 1 0.75 0.25 0.19 25.00% 0.25 0.19 25.00%
PIPELINE INSTALLATION
1030000 PIPING WORKS
1030100 Pipe Stringing
Dia 24" M 34,250 5.92 11,328 1.96 33.07% 2,095 0.36 6.12% 13,423 2.32 39.19%
Dia 16" M 550 0.07
Dia 12" M 200 0.02
Dia 8" M 12 0.00
1030300 Welding (Cuting, Bevel & Fiting )
Dia 24" M 34,392 31.84 8,280 7.67 24.08% 1,824 1.69 5.30% 10,104 9.35 29.38%
Dia 16" M 550 0.30
Dia 12" M 200 0.08
1040100 NDE Test
Non Destructive Test (100%) Ls 1 7.31 0.06 0.45 6.22% 0.10 0.74 10.07% 0.16 1.19 16.30%
1031400 Joint Coating (Heat Shrink Slive)
Dia 24" Joint 2,809 1.40 157 0.078 5.59% 155.00 0.08 5.52% 312 0.155 11.11%
Dia 16" Joint 46 0.01
Dia 12" Joint 17 0.00
Joint Coating (3 Layer)
Elbow Dia 24" Ea 130 0.11
Elbow Dia 16" Ea 11 0.01
Elbow Dia 6" Ea 11 0.00
Equal Tee Dia 24" Ea 2 0.00
Equal Tee Dia 16" Ea 2 0.00
Equal Tee Dia 12" Ea 3 0.00
1031500 Repair Coating Dia 24" (3 Layer) M 3,425 1.45
1031600 Repair Coating Dia 16" (3 Layer) M 55 0.02
1031700 Painting Pipa Dia. 24" Kg 1,000 0.85
1031800 Pipe Support Kg 1,000 0.20
1031900 Neopreme Sheet Gasket M2 30 0.31
Trenching (Open Cut) Incl Backfilling
1020100 Trenching of Concrete M 2,288 1.23
1020200 Trenching of Hotmix M 1,970 1.17
1020300 Normal Trenching
Dia 24" M 30,256 8.02 518.00 1.10 13.73% 1,429.00 3.04 37.88% 1947.00 4.139 51.61%
Dia 16" M 550 0.13
Dia 12" M 200 0.02
1030200 Pipe Lowering In
Dia 24" M 34,250 6.75 518 0.10 1.51% 314.00 0.06 0.92% 832.00 0.164 2.43%
Dia 16" M 550 0.09
Dia 12" M 200 0.03
1030500 Installation Valves
1030400 Weldolet
Dia 24" x 2" Ea 14 0.11
Dia 16" x 4" Ea 5 0.05
Dia 16" x 2" Ea 7 0.05
Dia 12" x 2" Ea 3 0.02
Dia 8" x 2" Ea 3 0.02
1030500 Pemasangan Valve
Dia 24" Ea 7 0.08
Dia 16" Ea 5 0.05
Dia 12" Ea 3 0.02
Dia 8" Ea 4 0.02
Dia 6" Ea 9 0.03
Dia 4" Ea 5 0.01
Dia 2" Ea 29 0.02
1030600 Insulation Joint
Dia 24" Ea 1 0.01
Dia 16" Ea 1 0.01
Dia 12" Ea 2 0.01
1030700 Gasket
Dia 24" Ea 4 0.00
Dia 16" Ea 28 0.00
Dia 10" Ea 2 0.00
Dia 8" Ea 4 0.00
Dia 6" Ea 18 0.00
Dia 2" Ea 86 0.00
1030800 Flange
WN Dia 24" Ea 2 0.02
WN Dia 16" Ea 42 0.35
WN Dia 12" Ea 4 0.03
WN Dia 8" Ea 10 0.06
WN Dia 6" Ea 6 0.03
WN Dia 4" Ea 15 0.04
WN Dia 2" Ea 29 0.04
Blind Dia 2" Ea 29 0.01
1030900 End Cap
Dia 16" Ea 3 0.06
Dia 10" Ea 1 0.00
Dia 8" Ea 4 0.01
1031000 Elbow
Dia 24" Ea 130 3.59
Dia 16" Ea 10 0.18
1031100 Tee
Red Dia 24" x 16" Ea 2 0.04
Red Dia 16" x 10" Ea 1 0.02
Red Dia 16" x 8" Ea 2 0.03
Equal Dia 16" Ea 2 0.04
1031200 Reducer Conc. Dia. 16" x 12" 0.02
Conc Dia 16"x12" Ea 1
1031300 Stud Bolt & Nut
Dia 24" Ea 336 0.44
Dia 16" Ea 200 0.23
Dia 12" Ea 64 0.02
Dia 8" Ea 96 0.02
Dia 2" Ea 464 0.02
103 CIVIL WORKS & REINSTATEMENT
1020400 Repair Works
Asphalt / Hotmix Road Repair M2 3,432 7.57
Concrete Road Repair M3 650.10 3.68
Grass Planting M2 36,990 2.04
Asphalt /Concrete Cleaning M 822 0.05
Site Cleaning 0 1 0.98
1020500 Sign Marker Installation
Marks every 100 m Bh 276 0.33
Marks every 500 m Bh 60 0.09
Sign Marker for Bridge Bh 12 0.27
Project Signboard Bh 7 0.19
Marker Tape M 34,942 0.44
1020600 Block Valve Box Installation
Dia 24" Ea 7 1.34
Dia 16" Ea 5 0.80
Dia 12" Ea 3 0.46
Dia 8" Ea 4 0.56

PROGRESS CUMMULATIVE 100.00 14.75 14.75% 21.15 21.15%

PROJECT CONTROL

PIC
COMPANY NAME_____________

SITE MANAGER

PIC

PROJECT CONTROL

PIC
CLIENT NAME________________

SITE MANAGER

PIC
50 DAYS CALENDAR RE-SCHEDULE (RECOVERY SCHEDULE)

CLIENT :_______________________________________________
OWNER :_______________________________________________ WORK PROGRESS & " S " C U R V E
PROJECT :_______________________________________________
:_______________________________________________
THE PROJECT NAME : ….................................................................... Rev. 01.
LOCATION :______________________________________________

PROGRESS PERIOD FROM______________UP TO____________________ Scale


NO DESCRIPTION Plan/ MONTH-YEAR MONTH-YEAR MONTH-YEAR MONTH-YEAR Progress
WEIGHT %
Act. 27 - 04 5 - 09 10 - 16 17 - 23 24 - 30 01 - 07 08 - 14 15 - 21 22 - 28 29 - 04 05 - 11 12 - 18 19 - 25 26 - 01 02 - 08 09 - 15 16 - 22 23 - 29 (%)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

MATERIAL TRANSPORTATION
100%
1010500 Material Transportation Plan 4.08% 0.82% 0.82% 0.82% 0.82% 0.82% 1.04% 1.04% 0.52%
Act. 0.17 0.30 0.29 0.29 0.44 0.36 0.75 0.61
CONSTRUCTION
1010000 PREPARATION & CLEANING WORK 90%
1010100 Direction Kit Plan 0.37% 0.19% 0.19% 0.05% 0.05%
Act. 0.28 0.05 0.05 0.003
1010200 Area Prep. Survey & Line M Plan 0.58% 0.29% 0.29% 0.21% 0.21%
Act. 0.17 0.21 0.21 0.004
80%
1010300 Mobilization and Demobilization Plan 1.84% 0.00% 0.61% 0.61% 0.34% 0.34% 0.34%
Act. 0.83 0.34 0.63
1010400 Stockyard Plan 0.40% 0.20% 0.20% 0.12% 0.12% 70%
Act. 0.28 0.12 0.02 0.06
1010600 Safety Equipment on Site Plan 0.75% 0.00% 0.38% 0.38% 0.19% 0.38%
Act. 0.19 0.19 0.38 0.04
PIPELINE INSTALLATION 60%
1030000 PIPING WORKS
1030100 Pipe Stringing Plan 6.01% 0.42% 0.42% 0.44% 0.42% 0.42% 0.44% 0.42% 0.75% 0.76% 0.76% 0.75%
Act. 0.20 0.78 0.60 0.37 0.36 0.44 0.41 0.22
50%
1030300 Welding (Cuting, Bevel & Fiting ) Plan 32.22% 0.00% 0.00% 1.17% 1.14% 2.73% 3.94% 3.22% 2.60% 5.63% 5.59% 3.81% 2.38%
Act. 2.21 2.85 2.60 1.69 1.34 3.17 0.98
1040100 NDE Test Plan 7.31% 0.00% 0.00% 0.49% 0.49% 0.49% 0.73% 0.73% 1.20% 1.20% 0.80% 0.70% 0.48%
Act. 0.15 0.26 0.19 0.74 0.72 0.48 0.42 40%
1031400 Joint Coating (Heat Shrink Slive) Plan 4.38% 0.00% 0.00% 0.31% 0.31% 0.31% 0.40% 0.40% 0.66% 1.08% 1.10% 0.51% 0.51% 0.51%
Act. 0.00 0.07 0.08 0.11 0.04 0.06
1020000 Trenching (Open Cut) Incl Backfill Plan 10.57% 0.00% 0.45% 0.66% 0.69% 0.90% 0.66% 0.93% 1.99% 3.11% 2.64% 1.34% 1.37% 0.12%
Act. 0.03 1.07 3.04 0.16 0.00 0.09
30%
1030200 Pipe Lowering In Plan 6.87% 0.00% 0.00% 0.48% 0.51% 0.48% 0.48% 0.67% 1.06% 1.09% 0.79% 0.79% 0.84% 1.77% 0.53%
Act. 0.10 0.06 0.18 0.04 0.09
1030500 Valves Installation Plan 5.82% 0.00% 0.00% 0.37% 0.60% 0.30% 0.39% 0.58% 1.05% 1.11% 0.99% 0.93% 0.91% 0.52% 0.31% 20%
Act.
1020000 CIVIL WORKS & REINSTATEMENT
1020400 Repair Works Plan 14.32% 0.00% 0.50% 0.76% 0.76% 1.49% 1.01% 2.45% 1.24% 2.06% 3.28% 2.06% 1.98% 1.24%
Act. 10%
1020500 Sign Marker Installation Plan 1.32% 0.00% 0.06% 0.07% 0.12% 0.12% 0.12% 0.19% 0.21% 0.31% 0.25% 0.19% 0.16%
Act.
1020600 Block Valve Box Installation Plan 3.16% 0.00% 0.19% 0.64% 0.00% 0.19% 0.35% 0.23% 0.83% 1.38% 0.40% 0.20% 0.20%
0%
Act.

WEEKLY CUMMULATIVE ORIGINAL PLAN PROGRESS WEEK LY CUMMULATIVE RE COVERY PLAN PROGRES S
WEEKLY CUMMULATIVE ACTUAL PROGRESS
TOTAL 100.00%
WEEKLY ORIGINAL PLAN PROGRESS 0.00% 0.68% 2.53% 2.68% 5.85% 6.44% 7.33% 8.84% 8.44% 8.61% 8.81% 8.05% 7.08% 7.51% 5.89% 5.32% 5.28% 0.68%
WEEKLY RECOVERY PLAN PROGRESS 0.00% 0.68% 2.53% 2.68% 5.85% 6.44% 7.33% 8.84% 8.44% 13.58% 18.20% 17.67% 12.76% 8.95% 5.27% 2.09% 0.34%
PLAN
WEEKLY CUMMULATIVE ORIGINAL PLAN PROGRESS 0.00% 0.68% 3.20% 5.88% 11.73% 18.18% 25.51% 34.36% 42.79% 51.40% 60.21% 68.26% 75.33% 82.84% 88.73% 94.04% 99.32% 100.00%
WEEKLY CUMMULATIVE RECOVERY PLAN PROGRESS 0.00% 0.00% 0.00% 1.31% 2.65% 6.09% 10.04% 14.75% 21.15% 34.73% 52.93% 70.59% 83.36% 92.31% 97.58% 99.66% 100.00%
WEEKLY ACTUAL PROGRESS 0.00% 0.00% 0.00% 1.31% 1.34% 3.44% 3.95% 4.70% 6.40%
ACTUAL
WEEKLY CUMMULATIVE ACTUAL PROGRESS 0.00% 0.00% 0.00% 1.31% 2.65% 6.09% 10.04% 14.75% 21.15%

Approved by ; Prepared by ;
NOTES : The Client The Company

PIC PIC
Issued for approval Date____________ CONSTRUCTION MANAGER SITE MANAGER
50 DAYS CALENDAR RE-SCHEDULE (RECOVERY SCHEDULE)

CLIENT :_______________________________________________
OWNER :_______________________________________________ TABLE OF TARGET PROGRESS
PROJECT :_______________________________________________
:_______________________________________________
LOCATION :______________________________________________
THE PROJECT NAME : …...........................................................................

STATUS REMAINING SCH.


NO DESCRIPTION UNIT QTY PROGRESS REMAINING WEIGHT % CUMM. MONTH-YEAR MONTH-YEAR REMARKS
Week-9 Week-10 Week-11 Week-12 Week-13 Week-14 Week-15 Week-16
ACHIEVED 22-28 (%) Unit UNIT 29 - 04 Target 05 - 11 Target 12 - 18 Target 19 - 25 Target 26 - 01 Target 02 - 08 Target 09 - 15 Target 16 - 22 Target
8 9 Perday 10 Perday 11 Perday 12 Perday 13 Perday 14 Perday 15 Perday 16 Perday
A. MATERIAL TRANSPORTATION
1010500 Material Transportation M' 35,012 22,225 12,787 4.08% 2.59% Perweek 1.04% 0.15% 1.04% 0.15% 0.52% 0.07%
M' 5,115 5,115 2,557
1.49% Cumm 2.53% 3.56% 4.08%
M' Unit 8,890 1,270 8,890 1,270 4,445 635
B. CONSTRUCTION
1010000 PREPARATION & CLEANING WORK
1010100 Direction Kit LS 1 24% 76% 0.37% 0.09% Perweek 0.05% 0.01% 0.05% 0.01%
0.28% Cumm 0.33% 0.37%
% % 12.16% 1.74% 12.16% 1.74%
1010200 Area Prep. Survey & Line M LS 1 71% 29% 0.58% 0.41% Perweek 0.21% 0.03% 0.21% 0.03%
0.17% Cumm 0.38% 0.58%
% % 35.34% 5.05% 35.34% 5.05%
1010300 Mobilization and Demobilization LS 1 55% 45% 1.84% 0.67% Perweek 0.34% 0.05% 0.34% 0.05% 0.34% 0.05%
1.17% Cumm 1.50% 1.84% 2.18%
% % 18.30% 2.61% 18.30% 2.61% 18.30% 2.61%
1010400 Stockyard LS 35,012 21,007 14,005 0.40% 0.24% Perweek 0.12% 0.02% 0.12% 0.02%
M' 7,002 7,002
0.16% Cumm 0.28% 0.40%
m' L-m' 10,504 1,501 10,504 1,501
1010600 Safety Equipment on Site LS 1 76% 24% 0.75% 0.57% Perweek 0.19% 0.03% 0.38% 0.05%
0.18% Cumm 0.37% 0.75%
% % 25.33% 3.62% 50.67% 7.24%
C. PIPELINE INSTALLATION
1030000 PIPING WORKS
1030100 Pipe Stringing M' 35,012 17,546 17,466 6.01% 3.01% Perweek 0.75% 0.11% 0.76% 0.11% 0.76% 0.11% 0.75% 0.11%
M' 4,346 4,381 4,398 4,340
3.00% Cumm 3.76% 4.52% 5.28% 6.02%
m' L-m' 4,366 624 4,401 629 4,419 631 4,360 623
1030300 Welding (Cuting, Bevel & Fiting ) JOINT 2,928 1,818 1,110 32.22% 20.01% Perweek 2.60% 0.37% 5.63% 0.80% 5.59% 0.80% 3.81% 0.54% 2.38% 0.34%
12.21% Cumm 14.81% 20.44% 26.03% 29.84% 32.22%
Joints Jonts 236 34 512 73 508 73 346 49 217 31
1040100 NDE Test LS 1.0 60% 40% 7.31% 4.39% Perweek 1.20% 0.17% 1.20% 0.17% 0.80% 0.11% 0.70% 0.10% 0.48% 0.07%
2.92% Cumm 4.12% 5.33% 6.13% 6.83% 7.31%
% % 16.45% 2.35% 16.45% 2.35% 10.97% 1.57% 9.60% 1.37% 6.59% 0.94%
1031400 Joint Coating (Heat Shrink Slive) JOINT 3,317 3,317 - 4.38% 4.38% Perweek 0.66% 0.09% 1.08% 0.15% 1.10% 0.16% 0.51% 0.07% 0.51% 0.07% 0.51% 0.07%
0.00% Cumm 0.66% 1.73% 2.83% 3.35% 3.86% 4.38%
Joints Joint 498 71 815 116 834 119 390 56 390 56 390 56
1020000 Trenching (Open Cut) Incl Backfill M' 39,522 39,522 10.57% 10.57% Perweek 1.99% 0.28% 3.11% 0.44% 2.64% 0.38% 1.34% 0.19% 1.37% 0.20% 0.12% 0.02%
0.00% Cumm 1.99% 5.11% 7.75% 9.08% 10.45% 10.57%
m' L-m' 7443 1,063 11645 1664 9867 1410 4994 713 5105 729 458 65
1030200 Pipe Lowering In M' 35,000 35,017 (17) 6.87% 6.87% Perweek 1.06% 0.15% 1.09% 0.16% 0.79% 0.11% 0.79% 0.11% 0.84% 0.12% 1.77% 0.25% 0.53% 0.08%
0.00% Cumm 1.06% 2.14% 2.94% 3.73% 4.57% 6.34% 6.87%
m' L-m' 5,387 770 5,538 791 4,040 577 4,040 577 4,275 611 9,022 1,289 2,713 388
1030500 Valves Installation EA 291 291 - 5.82% 5.82% Perweek 1.05% 0.15% 1.11% 0.16% 0.99% 0.14% 0.93% 0.13% 0.91% 0.13% 0.52% 0.07% 0.31% 0.04%
0.00% Cumm 1.05% 2.16% 3.15% 4.08% 4.99% 5.51% 5.82%
Ea Ea 52 7 56 8 50 7 47 7 45 6 26 4 16 2
1020000 CIVIL WORKS & REINSTATEMENT
1020400 Repair Works M' 2,926 2,926 - 14.32% 14.32% Perweek 2.45% 0.35% 1.24% 0.18% 2.06% 0.29% 3.28% 0.47% 2.06% 0.29% 1.98% 0.28% 1.24% 0.18%
0.00% Cumm 2.45% 3.70% 5.76% 9.04% 11.10% 13.08% 14.32%
m' L-m' 501 72 254 36 422 60 669 96 422 60 404 58 254 36
1020500 Sign Marker Installation EA 533 533 - 1.32% 1.32% Perweek 0.19% 0.03% 0.21% 0.03% 0.31% 0.04% 0.25% 0.04% 0.19% 0.03% 0.16% 0.02%
0.00% Cumm 0.19% 0.41% 0.72% 0.97% 1.16% 1.32%
Ea Ea 78 11 86 12 125 18 102 15 78 11 65 9
1020600 Block Valve Box Installation EA 19 19 - 3.16% 3.16% Perweek 0.23% 0.03% 0.83% 0.12% 1.38% 0.20% 0.40% 0.06% 0.20% 0.03% 0.12% 0.02%
0.00% Cumm 0.23% 1.06% 2.44% 2.84% 3.05% 3.16%
Ea Ea 1 0 5 1 8 1 2 0 1 0 1 0
TOTAL WEIGHT ( % ) 100.00%
TOTAL PROGRESS PERWEEK 13.58% 18.20% 17.67% 12.76% 8.95% 5.27% 2.09% 0.34%
1.94% 2.60% 2.52% 1.82% 1.28% 0.75% 0.30% 0.05%
TOTAL CUMMULATIVE PROGRESS PERWEEK 34.73% 52.93% 70.59% 83.36% 92.31% 97.58% 99.66% 100.00%
TOTAL CUMMULATIVE ORIGINAL PROGRESS PERWEEK 50.91% 59.56% 67.75% 75.33% 82.84% 88.73% 94.04% 99.32% 100.00%