Structure Program to be achieved by end of October -2022

Foundation (Raft) in Numbers Foundation (Pile) in Numbers


LHS RHS Total Raft Complete Str LHS RHS Total Piles Sets
MJB
BC 8 8 16 8 32 32 64 16
277+542
SVUP 3 3 6 3
LVUP 6 6 12 6 Foundation (Pile Cap) in Numbers
VUP 1 1 2 1 LHS RHS Total Cap
MJB 6 Nos.
3 3
277+542 (Complete Caps)

Sub-Structure (Walls) in Numbers Sub- Structure (Pier) in Numbers


LHS RHS Total complete Walls Complete Str Pier Shafts Pier Locations
MJB 4 Nos.
BC 26 26 52 26 8
277+542 (2x4 complete)
SVUP 4 4 8 4
LVUP 4 4 8 4 Super- Structure (Girders) in Numbers
VUP 1 1 2 1 Casting of Girder
MJB
6 Nos. complete
277+542

Super Structure (Slab) in Numbers Miscellenious


LHS RHS Total Slabs Complete Str Panel (Nos) 2300

BC 22 22 44 22 Column (nos.) 767

SVUP 7 7 14 7 RE Block (nos) 80000

LVUP 4 4 8 4
VUP 1 1 2 1 Pipe Culverts in Numbers
LHS RHS Total Complete Str
Hume PC 10 10 20 10