STRUCTURE PROGRAMME MONTH OF AUGUST-20 (BGAKHPL)

S.No. NAME OF STRUCTURE LOCATION SIDE FOUNDATION SUB-STRUCTURE SUPER STRUCTURE REMARK
161+586
MAJOR BRIDGE
1
A1 SR LHS
A1 MCW LHS
A1 MCW RHS
A1 SR RHS
P1 SR LHS
P1 MCW LHS
P1 MCW RHS
P2 SR RHS
P2 SR LHS
P2 MCW LHS
P2 MCW RHS
P2 SR RHS
A2 SR LHS 1
A2 MCW LHS 1
A2 MCW RHS 1
A2 SR RHS 1
4 0 0
1 PLYOVER 165+400
A1 LHS 1
P1 LHS 1
P2 LHS 1
A2 LHS Compelete
A1 RHS Compelete
P1 RHS
P2 RHS Diversion Required
A2 RHS
2 PLYOVER 172+960
A1 LHS Compelete 1
P1 LHS Compelete Compelete
P2 LHS Compelete 1
A2 LHS Compelete
A1 RHS
P1 RHS Compelete 1
P2 RHS Compelete
A2 RHS Compelete
3 3 0
1 MNB 153+052
A1-A2 SR LHS
A1-A2 MCW LHS Diversion Required
A1-A2 MCW RHS
A1-A2 SR RHS Compelete Compelete Compelete
2 MNB 155+391
A1-A2 SR LHS
A1-A2 MCW LHS
Errg. Canal
A1-A2 MCW RHS
A1-A2 SR RHS
3 MNB 161+510
A1-A2 SR LHS 1
A1-A2 MCW LHS 1
Subject Soil Filling
A1-A2 MCW RHS 1
A1-A2 SR RHS 1
4 MNB 163+889
A1-A2 LHS Diversion Required
A1-A2 RHS Compelete Compelete Compelete
5 MNB 177+549
A1-A2 SR LHS
A1-A2 MCW LHS
Drawing not final
A1-A2 MCW RHS
A1-A2 SR RHS
6 MNB 177+673
A1-A2 SR LHS
A1-A2 MCW LHS
Drawing not final
A1-A2 MCW RHS
A1-A2 SR RHS
7 MNB 184+987
A1-A2 LHS
Location not final
A1-A2 RHS
8 MNB 185+190
A1-A2 LHS 1 1
A1-A2 RHS
9 MNB 186+897
A1-A2 LHS
Errg. Canal
A1-A2 RHS
10 MNB 190+173
A1-A2 LHS Compelete Compelete 1
A1-A2 RHS
5 1 1
1 VUP-I 153+350
A1 LHS Compelete 1
A2 LHS Compelete 1 Contractor manpower
A1 RHS Compelete issue
A2 RHS Compelete
2 VUP-II 155+865
A1 -A2 LHS Compelete 1
A1-A2 RHS 1
3 VUP-II 159+209
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS Diversion Required
4 VUP-I 162+280
A1 LHS Compelete
A2 LHS Compelete 1
A1 RHS Compelete
A2 RHS Compelete 1
5 VUP-II 169+934
A1 -A2 LHS
A1-A2 RHS Compelete Compelete Compelete
6 VUP-I 179+153
A1 LHS Compelete 1
A2 LHS Compelete
A1 RHS Compelete 1
A2 RHS Compelete
7 VUP-II 180+252
A1 -A2 LHS Compelete
Villager Dispute
A1-A2 RHS Compelete
8 VUP-I 181+798
A1 LHS Compelete 1
A2 LHS Compelete
A1 RHS Compelete 1
A2 RHS Compelete
9 VUP-II 182+799
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS Compelete Compelete Compelete
10 VUP-I 184+200
A1 LHS Compelete 1
A2 LHS Compelete Compelete
A1 RHS Compelete Compelete
A2 RHS Compelete Compelete
11 VUP-I 189+096
A1 LHS Compelete Compelete
A2 LHS Compelete Compelete
A1 RHS Compelete Compelete
A2 RHS Compelete Compelete
1 10 0
1 BOX CULVERT 151+294
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
2 BOX CULVERT 156+360
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
3 BOX CULVERT 156+731
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
4 BOX CULVERT 159+431
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
5 BOX CULVERT 166+940
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
6 BOX CULVERT 167+780
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
7 BOX CULVERT 175+718
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
8 BOX CULVERT 176+798
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
9 BOX CULVERT 176+498
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
10 BOX CULVERT 176+898
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
11 BOX CULVERT 178+170
A1 -A2 LHS 1 1 1
A1-A2 RHS 1 1 1
12 BOX CULVERT 180+931
A1 -A2 LHS 1 1 1
A1-A2 RHS 1 1 1
13 BOX CULVERT 185+500
A1 -A2 LHS 1 1 1
A1-A2 RHS Compelete Compelete Compelete COMPLETE
14 BOX CULVERT 185+702
A1 -A2 LHS 1 1 1
A1-A2 RHS Compelete Compelete Compelete COMPLETE
15 BOX CULVERT 185+905
A1 -A2 LHS 1 1 1
A1-A2 RHS Compelete Compelete Compelete
16 BOX CULVERT 186+732
A1 -A2 LHS 1 1 1
A1-A2 RHS Compelete Compelete Compelete COMPLETE
17 BOX CULVERT 190+500
A1 -A2 LHS 1 1 1
A1-A2 RHS Compelete Compelete Compelete COMPLETE
18 BOX CULVERT 188+088
A1 -A2 LHS 1 1 1
A1-A2 RHS Compelete Compelete Compelete COMPLETE
19 BOX CULVERT 189+675
A1 -A2 LHS Compelete Compelete Compelete
A1-A2 RHS 1 1 1
21 21 21
SUMMARY FOUNDATION SUB-STRUCTURE SUPER STRUCTURE
1 MJB Nos 4 0 0
2 FLYOVER Nos 3 3 0
3 MNB Nos 5 1 1
4 VUP Nos 1 10 0
5 BOX CULVERT Nos 21 21 21 CS=8 Nos &PC=13 Nos
6 PSC GIRDER Nos 5
STRUCTURE STATUS WITH MANPOWER
SCOPE OF WORK
MANPOWER MANPOWER REMARK
S.No. NAME OF STRUCTURE LOCATION FOUNDATION PIER CAP/SLAB CONTRACTOR AVAILABLE REQUIRED
MAJOR BRIDGE
1 161+586 1 4 AK GROUP 20
2 PLYOVER 172+960 0 4 2 NOS REQD. 0 30
3 MNB 153+052 1 2 ISHIKA 15 0
IT CAN BE START ABOUT 30
MNB 155+391 2 2 2 NOS REQD. 30 MARCH-21, DURING WATER
4 CLOSING
4 MNB 163+889 1 OCC 9
5 MNB 177+549 2 2 AK GROUP 7
IT CAN BE START ABOUT 30
MNB 177+673 2 2 2 NOS REQD. 30 MARCH-21, DURING WATER
6 CLOSING
ENGEGED FOR CRESH BARRIER
MNB 186+897 AK GROUP 7
6 WORK
7 SVUP-II 179+672 1 2 AK GROUP 8
8 VUP-II 180+252 2 2 AK GROUP 6
9 BOX CULVERT 158+635 0 0 AS CONSTRUCTION 5 ENGEGED FOR R/WALL
10 BOX CULVERT 165+420 1 1 CASTA INFRA 7 8
161+510 &
MNB+ BOX CULVERT 0 1 SR CONSTRUCTION 5 5
11 172+788
179+153
BOX CULVERT 2 2 AVON CONSTRUCTIO 3 10
12 &181+520
13 BOX CULVERT 189+360 2 2 AK GROUP 8
STATUS OF STRUCTURE
SCOPE OF WORK
S.No. NAME OF STRUCTURE TOTAL SCOPE COMPLETE WORK IN PROGRESS REMARK
MAJOR BRIDGE
1 1 60 % Work Complete
1
About 70% work done of Flyover 172 and Flyover 164
PLYOVER 2 1 LHS work done up to Pier cap but RHS stoped due to
2 land issues.

MNB 9 7 2
3
VUP-II 6 2 2 Gider Launching WIP
4
VUP-II 6 5 2
4
ROB 1 GAD not approve yet
5
BOX CULVERT 103 190 13
6