Professional Documents
Culture Documents
Slump Test
Objective
he Slump Test is one of several method for determining the workability
of fresh concrele.
Main Principles
The
slump test is carried out by filling a
specified mould with freshly
mIxed concrete and
measuring the slump after remnoval of the mould.
The method
applies to cóhesive concrete of medium to
and with maximum high workability,
aggregate size of 40 mn.
References
BS 1881: Part 102: 1983.
Required equipment
f A slump mould of galvanized
form of a iron or steel. The mould shall be in the
çut-off with cone the following internal dimensions:
diameter of base: 200 + 2 mm
diameter of top: : 100 +2 nmm
height: 300 +2 mm
2 Scoop
Sampling tray
Shovel
Tamping rod, made out of
600 mni long. straight steel bar, 16
Rule,
mm
diameter and
graduated from O mm to 300 mm at 5
point being at one end mm
of the rule. intervals, the zero
Sampling
The sample can be
taken
mixing, and determination from
of
a
laboratory mix, maximum 2
slump should commence minutes after
If the
concrete is delivered instantly.
using a sample in a
irom the initial mixing truck, the
discharge. slump may be measured
cation TestProcedure
Step 1: Ensure that the
dry. Place the inner surtace of the
horizontal, firmbottom of the
mould onmould clean andis
Step 2:
an
non-absorbent surfaceclean, smooth, damp or
a
top layer
have been tamped, strike off
E the concrete tamped
Step4 fter the o f the mould
the m with aa s
o u l d wiTUh sawIng
aw motion of the
thhe top of
Notes level witlh
tamping rod.
ld
still held
clean away excessConcrete
down, clean
mould
With the o t the
mould.
Step5
outside
found
the
filling
to
the c o m p l e t e d within 2
e d oum
the start of and
snall be
interruption
without
is removed.,
me.
the m pto
mould
the
Immediately
after the rule to determine fference
Step 7: 5 mm by using the highest point of.
ofa
concrele mix the
nearest mouid and ot the
the hydration oof
the ot
The workability to the heiglit
tirme due n
TesIs hetween
changes with of
moistiire. specimen being tested.
and loss
the
cement
should,
therefore,
alter
De
d i f f e r e n t samples
constant
time interval
lo
at a
are
cammed out
comparable
resuills Expression of results
1his beng a slump in which
ch
if stricty a true slump. sho
mIxing
be obtained. Poct is only
valid ifit yields intact and symnetrical as
substantially
remains
concrete
the
Figure l(a).
or collapses, as shhown n
shown in
Figure 1(b),
as procedure.
shears, the
and irepeat
Ifthe specimen
take
another
sample
Figure 1(c),
nearest 5 mm.
to the
to Record the slump
expectead
concrele may be
Nomal mm.
150
of 80
-
information:
have a slump
Report include the following
shall
The test report * * * * * * * * * * * * *
procedure identification
Reference to this and sample
a
Date, time
and place of san1pling
and test
test in triplicate Time and place of of test
performs the
c o m m e n c e m e n t
of c) to
TMH1
a s the
mean resuilt from sampling
the Slump Time lapse slhear Or collapse
eports whether irue,
hree tests. Form of slump,
e) Measured true Slun1p
****************
19
Laboratory Testing Manual 2000
e *** ***
B. THE COMPACTING FACTOR
TI METHOD
18.4 APPARATUS:
i. The standard compacting factor appara is.
ii. A hand scoop
ii. A standard rod
iv. Two trowels
V. A duster
18.5 PROCEDURE:
. Make sure that the hoppers and the cylnder re clean nd dry, oil them and close both
the trap-doors and the cylinder lid.
2. Using a hand scoop, place concrete loos l in the upper iopper until full.
3. Open the trap-door at the base ofthe top hopper, allowing the concrete to fall into the
second hopper.
4. As soon as the concrete has fallen into the lower hoppertemove the lid and open the
second trap-door, so that the concrete now falls inte the eylinder. (If it sticks in the
hopper, free it by pushing a rod gently into the concrete from above).
5. Remove surplus concrete above the top of the cylinder by holding trowels in each
hand and moving them towards each other,
making a ctean cut level with the top.
6. Wipe the outside of the cylinder and weigh the concrete in it. This is done by
subtracting the weight of the cylinder when clean and empty from the weight of the
cylinder when full of concrete, and gives the ""WEIGHT OF PARTIALLY
COMPACTED CONCRETE".
7. Refill the cylinder from the same batch of concrete, in
layers about 50mm deep, hand-
ramming each layer or using vibration to ohtain full compaction.
8. Smooth the top of the concrete with a trowel to make sure the
cylinder is completely
full, but not over full.
9. Wipe the outside of the cylinder and COnerete in it, in the same manner as
before, to give, "WEIGHT OF FULLY
AGIED CONCRETE
18.6 CALCULATIONS
The compacting factor is found by dividing the partially compacted weight by the full
weight, thus: compactec
to
1 OBJECTIVES: measure of the resistance of an aggregate
value gives a relative
The aggregate crushing compressive load.
under a gradually
applied
crushing
base plate.
APPARATUS: with plunger and
.2 ended steel cylinder
diameter open 150mm -600mm long.
i. A 150mm rod, 16mm dia and
standard metal
tamping
ii. A
A 3 k g baland. 9.52mm and 2.40mm (No.7).
(in.), (3/8in),
ii. sieve of
sizes
12.70mm
BS test machine.
iv. testing 180mm deep.
115mm diameter and
compression
V.
A
measure,
standard the
A and is retained on
vi. which passes
the 12.70mm sieve
4 . 3 P R O C E D U R E :
aggregate
of the
a sample
Prepare that it is in a clean surface-dry
i. 9.52mm sieve. t w o tests
and ensure
er
for
25 strokes of the metal tan
qual layers giving
aggregate
sufficient
Prepare m e a s u r e
in three with the tamping rod.
ii. Fill the aggregate
ndition.
Level
f the
offf top ofthe and use the same weight of
nearest gram
each layer. ate to the
rod t o
the weight ofaggregate
Determine
in three equal layers givingg
iii. base
nd fill in the aggregate
plate
material1 the with tamping rod and insert the
the top of aggregate
on
L e v e l off
cylinder
the
Place
each
layer.
on the surface of the aggregate.
iv. to horizon zontally
25
blows
it
rests
machine ling at
loading at a uniform rate as possible so that the
that
so
he total load is 400 KN.
compression
plunger the
in ten
minutes.
sample
ed in fro the cylinder without further breaking of
Test the material
r e a c h e d
load
is v
remo vee
and minute.
passes
of
a m o u n t
the
weight
a g g r e g a t e
used. Thi
used. This is the Aggregate Crushing Value.
Determine
ot
weight
total
vii.
o f the
Carry out two tests.
14.4 CALCULATIONS:
Aggregate Crushing Value
= BA x 100%
sample used.
Where A= Weight in grams of surface-dry sieve.
B=Weight in grams of the
iractions
passing 2.40mm
17.1 OB.JECTIVES
beams using three different concrete mixes.
To cast concrete cubes, cylinders and
17.2 APPARATUS:
1. Nine standard cube moulds.
moulds.
ii. Three standard cylinder
moulds.
iii. Three standard beam
balance.
iv. A 50kg platform
A vibrating table.
V.
Plasterer's trowels.
VI.
A concrete mixer.
vii.
Kango vibrator.
vii.
17.3 P R O C E D U R E
cylinder and one standard beam for each of the three following concrete
one
Cast three cubes,
table and the cylinder and beams by means of Kanoo
cubes On a vibrating
mives, compacting the ango
the compacung lactor, slump and VB values for each mix.
Vibrator. Measure
M I X NO.1:
Water: Cement ratio by weight 0.5
Aggregate: Cementratio by weight= 4.0
17.4 RESULTS:
of materials used.
Comment on the workability of each mix.Report ihe weights
pteria
CML
Central Materials Laboratory
Aggregates.and Concrete
Notes **s"
i****err** ****
Objective
s*
This method describes the making of concrete test cubes for testing for
compressive strength.
Main Principles
The test cubes shall have nominal sizes of 100 mm or 150 mm. The
maximum size of aggregate is 20 mm for 100 mm cubes and 40 mm for
150 mn cubes.
References
BS 1881: Part 108: 1983. * * * * * * * * * * * * * * ****
Required equipment
Mould of cast iron or steel, witlh removable base plate.
For further details of tolerances, ref. BS The depth of the mould and the distance between the two pairs of
1881:Part 108.
opposite internal side faces, shall be the nominal size of 100 +
0.15 mm or 150 E 0.15 mm
Scoop
Vibrating table or steel compacting bar weighing I.8 kg, 380 mm
long and having a ramming face 25 mm square.
Plasterer's steel float
Sampling tray
Shovel
Mixing
The actual ambient temperature will Step 1: Air-dry the aggregate to be used and bring it to temperature
determine the mixing and Cung preferably about 25 °C. Mix the cement thoroughly and bring it
Conditions. However, exposure to direct to a temperature preferably about 25 °C. Portion the material by
Sunlight must be avoided.
nmass to the nearest 0.5 %.
If hand mixing: mix the dry cement and Step 2: Mix the concrete in a mixing machine. Load the mixing drum
fine aggregate before adding the coarse with coarse aggregate, fine aggregate, cement and add water
aggregate and finally the water in slowly. Continue mixing until the concrete is uniform in
increments.
apearance, but not for less than 2 minutes after alH material is in
the drum.
Samplingg
Obtain a sample of fresh concrete either from the laboratory nmade batch
or from a mix at a building site. The
sample shall be thoroughly mixed just
before it is moulded.
From each sample of fresh eonerete there shall be made 2 test cubes
specimens.
Moulding ******************
TESTNO, 2.12
WorAs
Making Test Cubes from Fresh Concrete
h
is then
When using a
vibrating
taOle
Vibraling
Curing
Onpaction
Step I:
Cover the test cubes (in the moulds) with an impervious sheet
and store them in a place free from vibrations.
The roorn shall
have a relative hunidity
preferably of min. 90 % and a Lenpe-
on Sle, a t
the Speci
rature preferably about 25 °C.
e s are made aSle
as
28 days.
Step 3: Submerge the cubes immediately in water at a
temperature
is
omal cuning penod preferably of about 25 °C
Report
The test report shall include the following infarmation:
atch
just
ating
ep
TESTNO 2.13
whtls Laboratory
Main Principles
cured and stored in
Test specimens shall be concrete cubes made,
accordance with BS 1881. Do not test cubes whiclh have been made in
the reasons
badly assembled mou lds or which are clearly nmisshapen. State
in the test report. Remove any projecting fins.
References
BS 1881 : Part 116.: 1983.
Required equipment
Compression Testing Machine.
Auxiliary platens. When'auxiliary platens are used, the top auxiliary
platen shall rest on and be aligned with the cube.
A balance witih min. 10 kg
capacity, readable and accurate to I g.
Test Procedure
mple shall consist of two Step I: Weigh each specimen, as-received or saturated.
of the same form and
made of one sample of fresh Step 2: Check tlhe nominal dimensions and take measured dimensions of
each specimen.
Step 5: Carefully centre the cube on the lower platen and ensure that
the load will be applied to two opposite cast faces of
the eube.
205
2000
Laboratory Testing Manual
CML
Central Materials Laboratory
Aggrogates and Concrete
Ministry of Warks
TEST NO. 2.6
Aggregate Grushing en
ötes
Value- ACV Minis
Objective
Aggregates used in road
crushing under construction
integrity of tlhe tralfic wheel loads. should be
ls. If the
strength of coarsepavement structure strong en1O
test aggregates may belikelyaggregales
to be are weak,k, theo resist lotes
The asured byadversel
measured the y affected.
Aggregate
resistance of an Cruslhing Value
Aporer e The
Aggregat
Main Principles aggregate to (ACV)
The
V) gives Crushi
Aggregate Cruslhing Value crushing under relative a
e
ot
standard size fraction material passing specitied (ACV) is graduallymeasure
a
of the
available, tests 14 10 mm a
applied load
load.
er
size
mm, ref.fractions
may be
perfomed
BS 812, between 2.36
and table
on
mm and
The test
sieve and
is
applicable
Sieve
to
alter determined by meaeauin.
crushing
below: retained on a
standard fraclion under load ring the
a
Fraction Separating sieve a 10 mm of 400 kN
28 20 mm The sieve.
20-14 nmm 5.0 mm than method
30. ln
is not
suitable
aggregates passing a14
4-10 mm
0-6.3 mm
3.35 mm
2.36 mmn applicable, such cases the for testing soft
ref. CML Test metliod for Ten aggregates
mm
3-5.0 mm 1.70 mm
References
no. 2.7. Percent Fineswitll an ACV
0-3.35 mm 1.18 mm BS 812: Value (TFV)liigh:he ap
850 um Part is
35-2.36mm oi2pprnldroounglxlic-ageesure qeu
110 : 1990
600 im
he sizes RequiredSteelequipment ayer 25 equa
ratus maysmaller than 10mm a A nm abo tro
be
eter 75 mm, used, i.e. cylindersmaller with Cylinder, open
Plunger ended of
*nessnee Evel
evel Olta
olee sute
tamping rod mould size 57 Test sieves and
lied force 100 diameter 8 mim,mm x 90 ref. nominal 150 mm internal
Baseplate,
square-hole
-
10
kN. and mm, and a figure 1. diamet
Tamping woven wire
rod, steel bar 2.36 mm
ends hemispherical 16 sieve.
type perforated-plate
of sizes 14
mm and
mm
Compression diameter and 600
Cylindrical Testing Machine,
Metal S00 kN
mn:
long with bet
internal
A depth Measure,
of 180 with internalcapacity
sample mm diameter of II5 mm ake can
Drying ovendivider,withe.g. a riffle box ani jam a
ensure
-
C r i a l ' s L a b o r a t o r y
TEST NO. 2,6
size 45
All-in aggregate 20 max.
Graded aggregate 40 to 5
40
Graded aggregate 20 to 5 25
Graded aggregate l4 to S 15
the 14 mm and 10 mm
Sieve the entire surface dry test portion on
Step 2: undersize fractions.
sieves to remove the oversize and
compact d by 25 stroke_
rod shall be dropped
over the surface of the layer. The tamping of the aggregate.
above the surface
from a height of about 50 m m
and insert the plunger
care the surface of the aggregate
2: Carefully level surface.
Step on this
jam aeloensure that the plunger does so that it rests horizontally
and plunger in position,
an the cylinder. the specimen
ing the
Step 3: Place the apparatus with testing machine. Apply
is platens of the compression is
gnilica
ossibleany stages
of the test, there between the force of 400 kN
u n i f o r m rate so
that the required
cant deformation, and it may not force at a
ng aran e fo maintain the required reached in 10 min
+ 30 s:
the aggregate
the tray and
Weigh to the nearestIg.
Step used (M) sieve
until
aggregate
the tray on the 2.36 m m
whole specimen in record
the
2000
Manual
Testing
Laboratory
Aggregates,and Concrote
CML
Central Materials Laboratory
TEST NO, 2.6
same mass as
the first specimen
the
Calculations
1) Calculate the Aggregate Crushing Value (ACV) expressed ae.
percentage to the first decimal place
tor cach test
specimen fro
following cquation:
ACV=Mx 100
where
is the mass of the test specimen (in g)
is the mass of the material passing the 2.36 mm sieve (in a
Calculate the mean of the two results to the nearest whole numbe
2)
If the individual results differ by more than 7 % of the mean value, the e
The median of 4 results is calculated by
the highest and lowest result
shall be repeated for two further specimens. The median value shall be
disregarding
and averaging the two middle results. reported as the ACV.
Report
The test report shall include the following:
Practical Considerations
Knock on the cylinder with a rubber mallet to remove the materal.
knock on the material itself.
Maintenance med on
Calibration of the compression testing machine should be pet
a year.
Figure 4 Outline form of cylinder and plunger apparatus jor the aggregate crushing value
14.2 APPARATUS:
i. A 150mm diameter open ended sieel cylinder with plunger and base plate.
ii. A standard metal tamping rod: 1omm dia and 150mm-600mm long.
iii. A 3kg baland.
IV. BS test sieve of sizes 12.70mmn). (3/8in), 9.52mm and 2.40mm (No.7).
V. A compression testing machine.
vi. A standard measure, 115mm diameter ant i deep.
14.3 PROCEDURE
i. Prepare a sample of the aggregate which passes the 12.70mm sieve and is retained on the
9.52mm sieve.
ii. Prepare sufficient aggregate for two tests and ensure that it is in a clean surface-dry
condition. Fill the measure in three equal layers giving 25 strokes of the metal tamping
rod to each layer. Level off the top of the aggregate with the tamping rod.
iii. Determine the weight of aggregate to the nearest gram and use the same weight of
material
iv. Place the cylinder on the base plate and fill in the aggregate in three equal layers giving
25 blows to each layer. Level off the top of aggregate with tamping rod and insert the
plunger so that it rests horizontally on the surface of the aggregate
V. Test sample in the compression machine loading at a uniform rate as possible so that the
total load is reached in ten minutes. The total load is 400 KN.
vi. Release the load, and remove the material from the cylinder without further breaking of
the sample and sieve on the 2.4mm (No.7) B.S. test sieve until no further significant
amount passes in one minute.
vii. Determine the weight of the fines passing 2.40mm sieve and express this as a percentage
of the total weight of aggregate used. This is the Aggregate Crushing Value.
Carry out two tests.
14.4 CALCULATIONS:
Aggregate Crushing Value =B/Ax 100%
used.
Where A =
grams of surface-dry sample
Weight in
sieve.
the fractions passing 2.40mm
B=weght in grams of