Professional Documents
Culture Documents
The Kanchpur, Meghna and Gumti 2nd Bridges Construction and Existing Bridges
Rehabilitation Project
Scope of Work
1. Kanchpur 21
2. Meghna 32
3. Gumti 102
Total 155
2
Work Procedure
3
Work Procedure
4
Survey Work
• Survey the center point of CIP Piles
5
Setting Power Jack
6
Installation of Temporary Casing and Excavation by
Hammer Grab
7
Setting Rotary Table, Tricon Bit etc.
8
Filling Stabilization Liquid (Bentonite)
9
Drilling
10
Reverse Circulation Drilling Mechanism
11
Set of Equipment
12
Cleaning Bottom of Hole (1st Cleaning)
13
KODEN Test
• Measure condition, verticality and diameter of bore
hole using ultra sonic test.
14
Installation of Rebar Cage
15
Splicing of Main Bars by U-Bolt
16
Setting Tremie Pipe and Re-cleaning of Bore Hole
• Bottom of the Tremie Pipe (dia 250mm) shall be at least 250mm to
300mm from the bottom of bore hole
17
Concrete Mix proportion for CIP (kg/m3)
30 18 ± 2.5
Class Y MPa cm 193 429 636 161 685 293 3.65
18
Casting of Concrete
19
On shore Casting
20
Off Shore Casting
21
Sonic Logging Test
To check the homogeneity and integrity of concrete - sonic logging test after 1 week.
Sonic tubes:60.5mm,
114.3mm dia.
22
Sonic Logging Test Report
23
Finally - Grouting of Sonic Tube
Sika Intraplast Z
Grout Proportion
24
Thank You
25