CAST-IN-PLACE

CONCRETE PILING WORK

The Kanchpur, Meghna and Gumti 2nd Bridges Construction and Existing Bridges
Rehabilitation Project
Scope of Work

Bridge Name Number of CIP Piles

1. Kanchpur 21

2. Meghna 32

3. Gumti 102

Total 155

Pile Diameter: 1500 mm Pile length: 32.10 – 75.00 m

2
Work Procedure

3
Work Procedure

4
Survey Work
• Survey the center point of CIP Piles

5
Setting Power Jack

6
Installation of Temporary Casing and Excavation by
Hammer Grab

On shore Off Shore

7
Setting Rotary Table, Tricon Bit etc.

8
Filling Stabilization Liquid (Bentonite)

9
Drilling

10
Reverse Circulation Drilling Mechanism

11
Set of Equipment

12
Cleaning Bottom of Hole (1st Cleaning)

• Circulation of slurry for 5 to 10 minutes to remove


excavated soil and slime
• Remove Rotary Table, Tricon Bit etc.

13
KODEN Test
• Measure condition, verticality and diameter of bore
hole using ultra sonic test.

14
Installation of Rebar Cage

15
Splicing of Main Bars by U-Bolt

16
Setting Tremie Pipe and Re-cleaning of Bore Hole
• Bottom of the Tremie Pipe (dia 250mm) shall be at least 250mm to
300mm from the bottom of bore hole

• Check the depth again

• Replace the old Bentonite liquid by fresh liquid

• Check the sand contents (<3%)

17
Concrete Mix proportion for CIP (kg/m3)

Type of Design Fine Fine Agg. Coarse Coarse Admixture


Strength Slump Water Cement Agg. Agg. Agg. Superplastic
Concrete S2
fc' S1 G1 G2 izer

30 18 ± 2.5
Class Y MPa cm 193 429 636 161 685 293 3.65

18
Casting of Concrete

19
On shore Casting

20
Off Shore Casting

1. Bottom of Tremie Pipe to be kept into concrete 2m or more


2. Remove Temporary Casing and backfill the borehole after 0.5-1hr

21
Sonic Logging Test
To check the homogeneity and integrity of concrete - sonic logging test after 1 week.

Sonic tubes:60.5mm,

114.3mm dia.

22
Sonic Logging Test Report

If the velocity >3600m/sec then the concrete is ok

23
Finally - Grouting of Sonic Tube
Sika Intraplast Z
Grout Proportion

24
Thank You