You are on page 1of 1

M/S.

ANJALI INTERIOR WORKS


Bhamini Sankul 611,Near Nawkar Tower,Naigaon East,Mumbai no-401208,
Email Id:- anjaliv.interior@gmail.com Contact Mr.Sanjay Shivhari Vishwakarma no- 8356046321

Quotation:- Labour Date :- 25-11-2022

To,
Moxy Hotel Guest Room,
Andheri (East),
Mumbai

Sr. No. ITEMS Qty. Unit Rate Amount

1 PEG WALL PANELLING 145.00 SQ.FT 175.00 25,375.00

Laminate ,Plywood ,Aluminium frame ,metal hook


fixing
STUDY TABLE (700 MM WIDE X 500 MM DEEP X
2 1.00 NO 2500.00 2,500.00
250 MM HIGH)
OPEN STYLE WARDROBE (1175 mm WIDE X 550
3 12.00 SFT 550.00 6,600.00
mm DEEP X 2200 MM HIGH)
VANITY COUNTER MIRROR ( 700 MM WIDE X 950
4 7.50 SFT 150.00 1,125.00
MM HIGH X 70 MM DEEP)Mirror ,Plywood and profile

5 FULL LENGTH MIRROR (450 MM WIDE X 1500 MM HIGH)Mirror ,Plywood and profile 7.50 SFT 150.00 1,125.00

SHELF @ PEG WALL (430 MM WIDE X 100 MM


6 1.00 NO 1,500.00 1,500.00
DEEP x 1155 MM HT.) metal frame fixing with shelf making
Only fixing Door and Frame with unloading D1 1000
7 1.00 NO 3,000.00 3,000.00
MM X 2200 MM SINGLE DOOR
SOLID CORE DOORS WITH 200 MM x 50 MM THK ASHWOOD FRAME ON THREE SIDES(
HEIGHT =2200 AS MENTIONED BELOW)

8 WOODEN SKIRTING 55.00 R.FT. 75.00 4,125.00

FALSE CEILING – WOODEN FRAME & MDF


9 18.00 S.FT. 250.00 4,500.00
(VESTIBULE AREA ONLY)
PROVIDING & FIXING SOLID WOOD FRAME
FINISHED IN 12 MM THK. MDF. CEILING
Floor profile fixing SS BEADING FOR CARPET /
10 3.00 R.FT. 75.00 225.00
WOODEN FLOOR

11 PELMET 12" X 6" IN SIZE WITH LUSTURE PAINT FINISH 11.00 RFT 225.00 2,475.00

12 TRAP DOORS - (1500 MM x 1200 MM) 20.00 S.FT. 250.00 5,000.00

13 Paneling Laminate finish Ledge top fixing 4" wide 10.00 RFT 250.00 2,500.00

Total Amount Per Room ₹ 60,050.00


56 Room Amount 56 ₹ 33,62,800.00

Term & Condition:-

1 All material loading & unloading by client.


2 All material required at each floor where work is going on by client
3 Labour toilet provided by client on working floor
4 Drinking,Working water supply by client free of cost.
5 Electricity provide by client free of cost.
6 Any debit charge not accepted.