You are on page 1of 5

Republic of the Philippines

Department of Education
Region II – Cagayan Valley
Schools Division of Nueva Vizcaya

Title of the Project: Project ROOF (Reaching Out the Optimistic Future of Our School
Learners)

Sponsoring Agency/Company: K-G2 Parents, Donations and other Stakeholders


Source of Fund: Donations
Amount of Project: 34,438.00

I. Rationale

To protect the health and safety of teachers and students. the school must provide a learning-

friendly environment in the classroom so that students' academic performance is not adversely

affected.

A roof is the uppermost part of a building that serves as a structural covering to protect it from

elements such as rain, sun, and wind. Because the condition of the school has a direct impact on

the performance of the students, a roof extension is necessary to provide protection from the

elements for the teachers, students, and parents. The main goal of the projects is to build a new

roof over an existing concrete classroom from Kinder to Grade 2. It is true that having a well-

maintained classroom is critical for students to achieve the expected academic results.

With this issue, Inaban Elementary School, particularly in the Kinder to Grade 2 classrooms,

proposed a separate roof extension in order to protect the classrooms from rain, sun, and wind and

provide a good place for instruction from Kinder to Grade 2 classrooms in preparation for the New

Normal Education for SY 2022-2023.

School: Inaban Elementary School


Address: Inaban, Dupax del Norte, Nueva Vizcaya
Email Address: 104044@deped.gov.ph
II.Objectives of the Project
a. General

Provide build a new roof over an existing concrete classroom from Kinder to Grade 2
that can be used by the pupils outside their classroom.

b. Specific

The author of this planning process is required to launch a development project to


achieve the following goals:
1. to create better and more comfortable educational facilities, including classrooms with
roof extensions from Kindergarten to Grade 2
2. to enhance the quality of education and
3.to increase achievement level of the learners from Kinder to Grade 2

III. Plan of Action

ACTIVITIES TIME FRAME


June July Aug Sep Oct Nov Dec Jan Feb Mar

Conduct dialogue and


presented the proposed /
project to General PTA
Secured permit from the
Division Office for its /
approval and implementation
Designed the
ATEP and make lay- out of /
the project
List of parents from Kinder
/
to Grade 2
Prepare the Program of
/
Works
Follow –up payment /
Purchase of Materials needed /
Prepare a schedule for the
/
construction of the project
Construction of the
/
LINONG
Painting the Roof of the
/
LINONG
Document and submit the
/
results to the Division Office

School: Inaban Elementary School


Address: Inaban, Dupax del Norte, Nueva Vizcaya
Email Address: 104044@deped.gov.ph
IV. Project Committee

The project greatly benefits the learners, parents, teachers, visitors and
stakeholders.

Working Committees

Committee In-Charge Position Role/s


Checking and Quality Quality Assurance District Level, Checked and
Assurance of proposal Team Quality quality assurance
and reports Assurance Team of proposal
Team of and reports
proposal and
reports

Solicitation/ MINETTE E. Proponent S 1. Scouted donors


Partnership/ PONTALBA or and prepared and
Mobilization for forward
SHARLY N. communicate
PASCUA terms and
conditions

2. Receive the
donation

3.Prepared photo
document activities

Purchase Materials K-G2 Parents, Officers Tod To purchase needed


Officers Ma materials

Implementation Laborer Laborer To


carry out the
project
Monitoring Supervision CAMILO T. School Head To monitor supervise
and Evaluation SARANDI JR. and evaluate the
finished product
ALFREDO V. Master
ORDINARIO JR Teacher I

V. Budgetary Requirements

School: Inaban Elementary School


Address: Inaban, Dupax del Norte, Nueva Vizcaya
Email Address: 104044@deped.gov.ph
Item Source of
Activities Unit Unit Cost Total Cost fund
Quantity

Description

Construction Cement 10 bags 250.00 2500.00 Donation


of kiosk tie wire 1 kg 75.00 75.00 Donation

RSB 8 2 mm 100.00 100.00 Donation

GI Sheet 8’ 6 pieces 150.00 900.00 Donation

CWN 3” 3 kg 65.00 195.00 Donation

CWN 4” 3 kg 64.00 192.00 Donation

Umbrella 3 kg 68.00 204.00 Donation


nail

Wooden post 4 pieces 300.00 1200.00 Donation


8x8x8

Lumber 10 Pieces 150.00 1500.00 Donation


2’x6’x10’

Ridge roll 4 pieces 100.00 400.00 Donation

Skilled 1 Pakyawan 10,000.00 Donation


Labor carpenter

Helper 1 Pakwayan 8000.00 Donation

24,866.00
Total Estimated

Mural of wall Skilled 1 6 spans 1000.00 6000.00 Donation


and fence Painter per span
(Pakyawan)

Total Estimated 6000.00 Donation

School: Inaban Elementary School


Address: Inaban, Dupax del Norte, Nueva Vizcaya
Email Address: 104044@deped.gov.ph
Total Estimated Amount 34,348.00

VI. Project Outputs

This project definitely expects outcomes such as the following, to wit:

1. to create better and more comfortable educational facilities, including classrooms


with roof extensions from Kindergarten to Grade 2
2. to enhance the quality of education and
3.to increase achievement level of the learners from Kinder to Grade 2

Prepared by:

MINETTE E. PONTALBA SHARLY N. PASCUA


Proponent/ T-III Proponent/ T-III

Recommending Approval:

CAMILO T. SARANDI JR.


Head Teacher III

JOSIE L. CONDE EdD.


Public Schools District Supervisor

APPROVED:

RACHEL R. LLANA, PhD. CESO V


Schools Division Superintendent

Date: December 01, 2022

School: Inaban Elementary School


Address: Inaban, Dupax del Norte, Nueva Vizcaya
Email Address: 104044@deped.gov.ph