You are on page 1of 8

PT.

CITRA KARSA DINAMIKA


DAILY REPORT

No. PO Periode/Date Selasa 17 Pebruari, 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

PASANG BESI RING BALOK COR RING BALOK

BOBOKAN BETON LANTAI AS A-4 PASANG PANEL DAN KONEKSI KABEL SITE PROJECT

GALIAN PILE CAP LEVEL - 2.60 M AS B-5 BONGKAR POS SECURITY


HSSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. PASANG BESI RING BALOK 1. BRIFING PAGI & SAFETY TALK
Week 2. COR RING BALOK 2. BOBOKAN LANTAI UNTUK PONDASI
Cumulative Manhour until This 3. BOBOKAN BETON LANTAI AS A-4 3. PLESTER DINDING BATA
Month 4. PASANG PANEL DAN KONEKSI KABEL DI SITE PROJECT 4. GALIAN PILE CAP
Safety Trainning 5. GALIAN PILE CAP LEVEL -2.60 M AS B-5 5. FABRIKASI BESI
6. BONGKAR POS SECURITY 6.FABRIKASI BEKISTING KOLOM
- Demo body harness
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Dede Rusna.K


PT. CITRA KARSA DINAMIKA
DAILY REPORT

No. PO Periode/Date Rabu 18 Februari, 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

BOBOKAN BETON LANTAI AS B-3 CUTTING LANTAI DI AREA AS A-(8-9)

BOBOKAN BETON DI KORIDOR AHU BOBOKAN BETON LANTAI AS A-4

PEKERJAAN PLESTERAN PARTISI AS 5 BONGKAR POS SECURITY


HSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. BOBOKAN LANTAI AS B-3 1. BRIEFING PAGI & SAFETY TALK
Week 2. CUTTING LANTAI DI AREA AS A-(8-9) 2. BOBOKAN LANTAI UNTUK PONDASI
Cumulative Manhour until This 3. BOBOKAN BETON LANTAI AS A-4 3. PLESTER DINDING BATA
Month 4. BOBOKAN BETON DI KORIDOR AHU 4. GALIAN PILE CAP
Safety Trainning 5. PEKERJAAN PLESTERAN PARTISI AS 5 5. FABRIKASI BESI
6. BONGKAR POS SECURITY 6.FABRIKASI BEKISTING KOLOM
- Demo body harness 6. BONGKAR POS SECURITY
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Toman Edoardo


PT. CITRA KARSA DINAMIKA
DAILY REPORT

No. PO Periode/Date Jumat, 20 Februari, 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

BOBOKAN BETON LANTAI AS B-3 PEMASANGAN PELAT DI RUANG PRODUKSI

PEMASANGAN PELAT DI KORIDOR AHU PENGGALIAN PILE CAP AS A-4

PEKERJAAN PLESTERAN PARTISI AS 5 BONGKAR POS SECURITY


HSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. BOBOKAN LANTAI AS B-3 1. BRIEFING PAGI & SAFETY TALK
Week 2. PEMASANGAN PELAT DI RUANG PRODUKSI 2. BOBOKAN LANTAI UNTUK PONDASI
Cumulative Manhour until This 3.PENGGALIAN PILE CAP AS A-4 3. PLESTER DINDING BATA
Month 4. PEMASANGAN PELAT DI KORIDOR AHU 4. GALIAN PILE CAP
Safety Trainning 5. PEKERJAAN PLESTERAN PARTISI AS 5 5. FABRIKASI BESI
6. BONGKAR POS SECURITY 6.FABRIKASI BEKISTING KOLOM
- Demo body harness 6. BONGKAR POS SECURITY
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Toman Edoardo


PT. CITRA KARSA DINAMIKA
DAILY REPORT

No. PO Periode/Date Senin 23 Februari, 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

BRIFING PAGI ACIAN DINDING BATA

BOBOKAN LANTAI GALIAN PILE CAP

FABRIKASI BESI PILE CAP FINISHING EX. BONGKARAN POS SECURITY


HSSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. BRIFING PAGI 1. BRIFING PAGI & SAFETY TALK
Week 2. ACIAN DINDING BATA 2. BOBOKAN LANTAI UNTUK PONDASI
Cumulative Manhour until This 3. BOBOKAN BETON LANTAI AS 2 3. ACIAN DINDING BATA
Month 4. GALIAN PILE CAP 4. GALIAN PILE CAP
Safety Trainning 5. FABRIKASI BESI PILE CCAP 5. FABRIKASI BESI
6. FINISHING EX. BONGKARAN POS SECURITY 6. CLEANING AREA
- Demo body harness
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Dede Rusna.K


PT. CITRA KARSA DINAMIKA
DAILY REPORT

No. PO 4070006000 Periode/Date Selasa 24 Februari, 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

BRIFING PAGI GALIAN PILE CAP

ACIAN DINDING BATA BOBOK BETON LANTAI AS A-02

GROUTING LANTAI AREA PRODUKSI REPAIR JALAN EX BONGKARAN


HSSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. BRIFING PAGI 1. BRIFING PAGI & SAFETY TALK
Week 2. GALIAN PILE CAP 2. BOBOKAN LANTAI UNTUK PONDASI
Cumulative Manhour until This 3. ACIAN DINDING BATA 3. ACIAN DINDING BATA
Month 4. BOBOKAN BETON LANTAI 4. GALIAN PILE CAP
Safety Trainning 5. GROUTING LANTAI AREA PRODUKSI ( SI ) 5. FABRIKASI BESI
6. REPAIR JALAN EX BONGKARAN ( SI ) 6. CLEANING AREA
- Demo body harness
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Dede Rusna.K


PT. CITRA KARSA DINAMIKA
DAILY REPORT

No. PO 4070006000 Periode/Date Rabu 25, Pebruari 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

BRIFING PAGI GALIAN PILE CAP

BOBOKAN BETON LANTAI ACIAN DINDING BATA

FABRIKASI BESI SHUT DOWN INSTALLASI EXISTING


HSSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. BRIFING PAGI 1. BRIFING PAGI & SAFETY TALK
Week 2. GALIAN PILE CAP 2. BOBOKAN LANTAI UNTUK PONDASI
Cumulative Manhour until This 3. BOBOKAN BETON LANTAI 3. ACIAN DINDING BATA
Month 4. ACIAN DINDING BATA 4. GALIAN PILE CAP
Safety Trainning 5. FABRIKASI BESI 5. FABRIKASI BESI
6. SHUT DOWN INSTALLASI EXISTING 6. CLEANING AREA
- Demo body harness
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Dede Rusna.K


PT. CITRA KARSA DINAMIKA
DAILY REPORT

No. PO 4070006000 Periode/Date Kamis 26, Pebruari 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

BRIFING PAGI BOBOKAN BATU KALI AS A-02

CHECKING DINDING PARTISI BY QC PENGUKURAN DIMENSI MATA BOR STRAUS

PENGEBORAN STRAUS PILE PENYEDOTAN AIR SAAT STRAUS


HSSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. BRIFING PAGI 1. BRIFING PAGI & SAFETY TALK
Week 2. BOBOKAN BATU KALI AS A-02 2. BOBOKAN LANTAI UNTUK PONDASI
Cumulative Manhour until This 3. CHECKING DINDING PARTISI BY QC 3. ACIAN DINDING BATA
Month 4. PENGUKURAN DIMENSI MATA BOR STRAUS 4. GALIAN PILE CAP
Safety Trainning 5. PENGEBORAN STRAUS PILE 5. FABRIKASI BESI
6. PENYEDOTAN AIR SAAT STRAUS 6. STRAUS PILE
- Demo body harness
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Dede Rusna.K


PT. CITRA KARSA DINAMIKA
DAILY REPORT

No. PO 4070006000 Periode/Date Jum'at 27 Pebruari 2015

Project Name RENOVASI GEDUNG 72 B Contractor PT. CITRA KARSA DINAMIKA

Client PT. BENTOEL PRIMA PM/SM VIKTOR RENDRA/DEDE RUSNA

BRIFING PAGI STRAUS PILE

GALIAN PILE CAP FABRIKASI BEKISTING KOLOM

FABRIKASI BESI ACIAN DINDING BATA PARTISI


HSSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. BRIFING PAGI 1. BRIFING PAGI & SAFETY TALK
Week 2. STRAUS PILE 2. STRAUS PILE
Cumulative Manhour until This 3. GALIAN PILE CAP 3. ACIAN DINDING BATA
Month 4. FABRIKASI BEKISTING KOLOM 4. GALIAN PILE CAP
Safety Trainning 5. FABRIKASI BESI 5. FABRIKASI BESI
6. ACIAN DINDING BATA PARTISI 6. PERAPIHAN DINDING
- Demo body harness
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues

- Near Miss
Material Approval

Prepared by, Dede Rusna.K