SALURAN IRIGASI NGR-PASERON DUSUNDESA - Awal
SALURAN IRIGASI NGR-PASERON DUSUNDESA - Awal
Desa : Sukasetia
Lokasi : Dusun Cinangka
Volume : 133.20 m
Tanggal :
SKETSA VOLUME PEKERJAAN
PERHITUNGAN VOLUME VOLUME
Tembok Penahan Tanah p= 129.00 m
VOLUME PEKERJAAN
Pasangan Batu Mortar P= 133.20 m3
P.0 Kanan Type 1
Volume Kanan P= 30.00 m 44.30 m3
P X ( L1 + L2 X T
30.00 X ( 0.30 + 0.50 ) / 2 X 2.50 30.00 m3
Pondasi
P X L X T
30.00 X 0.5 X 0.5 7.50 m3
P.0 Kiri Volume Kiri P= 30.00 m
P X L X T
30.00 X ( 0.25 + 0.30 ) / 2 X 0.50 4.13 m3
Pondasi
P X L X T
30.00 X 0.3 X 0.3 2.70 m3
P.1 Kanan Type 2
Volume Kanan P= 31.00 m 22.90 m3
P X ( L1 + L2 X T
31.00 X ( 0.30 + 0.40 ) / 2 X 1.00 10.85 m3
Pondasi
P X L X T
31.00 X 0.40 X 0.40 4.96 m3
P.1 Kiri Volume Kiri P= 31.00 m
P X L X T
31.00 X ( 0.25 + 0.30 ) / 2 X 0.50 4.26 m3
Pondasi
P X L X T
31.00 X 0.3 X 0.3 2.79 m3
P.2 Kanan Type 3
Volume Kanan P= 24.00 m 19.80 m3
P X ( L1 + L2 X T
24.00 X ( 0.30 + 0.40 ) / 2 X 1.25 10.50 m3
Pondasi
P X L X T
24.00 X 0.40 X 0.40 3.84 m3
P.2 Kiri Volume Kiri P= 24.00
P X L X T
24.00 X ( 0.25 + 0.30 ) / 2 X 0.50 3.30 m3
Pondasi
P X L X T
24.00 X 0.3 X 0.3 2.16 m3
P.3 Kanan Type 4
Volume Kanan P= 22.00 m 23.10 m3
P X ( L1 + L2 X T
22.00 X ( 0.30 + 0.40 ) / 2 X 2.00 17.60 m3
Pondasi
P X L X T
22.00 X 0.50 X 0.50 5.50 m3
P.4 Kanan Type 5
Volume Kanan P= 22.00 m 23.10 m3
P X ( L1 + L2 X T
22.00 X ( 0.30 + 0.40 ) / 2 X 2.00 17.60 m3
Pondasi
P X L X T
22.00 X 0.50 X 0.50 5.50 m3
P.5 Kanan Type 6
Volume Kanan P= 0.00 m 0.00 m3
P X ( L1 + L2 X T
0.00 X ( 0.3 + 0.4 ) / 2 X 1.00 0.00 m3
Pondasi
P X L X T
0.00 X 0.40 X 0.40 0.00 m3
Tanda Tangan
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Cinangka
Volume : 51.60 m²
Tanggal :
SKETSA VOLUME
PLESTERAN 51.60 m²
P X L
129.00 X 0.40 51.60 m2
GALIAN PONDASI P X L XT
129.00 X 0.47 X 0.475 27.78 m3 27.78 m3
27.30
Tanda Tangan
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Nangerang
133.2 m
Tanggal :
SKETSA VOLUME
P.1 Kanan
50.00 m 8.80 m3
2.81 m3
3.75 m3
2.25 m3
P.1+36 m kiri
14.00 m 2.50 m3
0.79 m3
1.05 m3
0.63 m3
P.2 Kiri
40.00 m 7.10 m3
2.25 m3
3.00 m3
1.80 m3
P.2 Kanan
50.00 m 8.80 m3
2.81 m3
3.75 m3
2.25 m3
Tanda Tangan
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Nangerang
Volume : 133.2 m
Tanggal :
SKETSA VOLUME
P. 3 Kiri
38.00 m 6.70 m3
2.14 m3
2.85 m3
1.71 m3
P. 3 Kanan
50.00 m 8.80 m3
2.81 m3
3.75 m3
2.25 m3
P.4 Kiri
10.00 m 3.20 m3
1.13 m3
1.50 m3
0.60 m3
P.4 Kanan
10.00 m 1.80 m3
0.56 m3
0.75 m3
0.45 m3
Tanda Tangan
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Nangerang
Volume : 133.2 m
Tanggal :
SKETSA VOLUME
P.4 + 11 m Kiri
14.00 m 3.60 m3
1.96 m3
1.68 m3
P.4 + 25 m Kiri
18.00 m 3.20 m3
1.01 m3
1.35 m3
0.81 m3
P.4+25m Kanan
25.00 m 12.80 m3
8.75 m3
4.00 m3
P.4 + 25 m Kanan
25.00 m 4.40 m3
1.41 m3
1.88 m3
1.13 m3
Tanda Tangan
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Nangerang
Volume : 133.2 m
Tanggal :
SKETSA VOLUME
P4 + 43 m Kiri
7.00 m 2.30 m3
0.79 m3
1.05 m3
0.42 m3
P.5 Kiri
4.00 m 1.30 m3
0.45 m3
0.60 m3
0.24 m3
P.5 Kanan
47.00 m 8.30 m3
2.64 m3
3.53 m3
2.12 m3
Tanda Tangan
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Nangerang
Volume : 133.2 m
Tanggal :
SKETSA VOLUME
P.5 + 4 m Kiri
42.00 m 7.40 m3
2.36 m3
3.15 m3
1.89 m3
P.12 Kiri
13.00 m 5.70 m3
3.64 m3
2.08 m3
P.11+2.5m Kanan
1.80 m 1.00 m3
0.63 m3
0.36 m3
P.11 Kanan
2.50 m 1.60 m3
1.05 m3
0.50 m3
18.00 m
5.99 m3
2.88 m3
Tanda Tangan
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Nangerang
Volume : #REF! m²
Tanggal :
SKETSA VOLUME
#REF! m²
#REF! m2
#REF! m2
#REF! m2
#REF! m2
Tanda Tangan
U/ Saluran Drainase, P =
Volume I
483 p x ( l1 + l2) / 2 x t x 2
29 x(0.10+ 0.20)/2 x 0.55x2 =
Volume II
p x l x t
29 x 0.40 x 0.15 =
pxl
1.50 0.90
2.40
-2.40
0.666666666666667
m3
m3
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume : 303.60 m
PEKERJAAN : Tembok Penahan Tanah (TPT) Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Tembok Penahan Tanah p= 303.60 m
VOLUME PEKERJAAN
Pasangan Batu Mortar P= 220.30 m3
P.0 Kanan Type 1
Volume Kanan P= 30.00 m 9.90 m3
p x ( l1 + l2) / 2 x t
30 x (0.3+0.4)/ 2 x 0.6 = 6.30 m3
Pondasi
p xlx t
30 x 0.4 x 0.3 = 3.60 m3
P.0 + 30 Kanan Type 2
Volume Kanan P= 22.00 m 9.20 m3
p x ( l1 + l2) / 2 x t
22 x (0.3+0.4)/ 2 x (1.3+0.4)/2 = 6.55 m3
Pondasi
p xlx t
22 x 0.4 x 0.3 = 2.64 m3
P.1 Kanan Type 3
Volume Kanan P= 12.00 m 3.50 m3
p x ( l1 + l2) / 2 x t
12 x (0.3+0.4)/ 2 x 0.5 = 2.10 m3
Pondasi
p xlx t
12 x 0.4 x 0.3 = 1.44 m3
P.1 + 12 Kanan Type 4
Volume Kanan P= 38.00 m 8.60 m3
p x ( l1 + l2) / 2 x t
38 x (0.3+0.4)/ 2 x 0.3 = 3.99 m3
Pondasi
p xlx t
38 x 0.4 x 0.3 = 4.56 m3
P.2 Kanan Type 5
Volume Kanan P= 50.00 m 11.30 m3
p x ( l1 + l2) / 2 x t
50 x (0.3+0.4)/ 2 x 0.3 = 5.25 m3
Pondasi
p xlx t
50 x 0.4 x 0.3 = 6.00 m3
P.3 Kanan Type 6
Volume Kanan P= 8.00 m 1.80 m3
p x ( l1 + l2) / 2 x t
8 x (0.3+0.4)/ 2 x 0.3 = 0.84 m3
Pondasi
p xlx t
8 x 0.4 x 0.3 = 0.96 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume : 303.60 m
PEKERJAAN : Tembok Penahan Tanah (TPT) Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
P.3 + 8 m Kanan Type 7
Volume Kanan P= 13.00 m 2.90 m3
p x ( l1 + l2) / 2 x t
18 x (0.3+0.4)/ 2 x 0.3 = 1.37 m3
Pondasi
p xlx t
18 x 0.4 x 0.3 = 1.56 m3
P4 Kanan Pasangan Batu Mortar P=
Type 8
Volume Kanan P= 17.00 m 5.00 m3
p x ( l1 + l2) / 2 x t
17 x (0.3+0.4)/ 2 x 0.5 = 2.98 m3
Pondasi
p xlx t
17 x 0.4 x 0.3 = 2.04 m3
P. 17 + 29.70 m Kiri Pasangan Batu Mortar P =
Type 11
Volume Kanan P= 20.30 m 68.10 m3
p x ( l1 + l2) / 2 x t
20.30 x (0.4+1.0)/ 2 x 3..0 = 42.63 m3
Pondasi
p xlx t
20.30x 1.0 x 1.20 = 24.36 m3
Loneng 11.00 buah
(Jmlh x p x l x t)-(1/2 x a x t)
(11x0.50x0.40x0.50)-(1/2x0.10x0.15x0.4) 1.07 m3
P. 17 + 21 m Kanan Pasangan Batu Mortar P=
Type 11
Volume Kanan P= 29.00 m 63.20 m3
p x ( l1 + l2) / 2 x t
29 x (0.3+0.8)/ 2 x 2.8 = 44.66 m3
Pondasi
p xlx t
29 x 0.8 x 0.8 = 18.56 m3
Loneng 15.00 buah 1.10 m3
(Jmlh x p x l x t)-(1/2 x a x t)
(15x0.50x0.30x0.50)-(1/2x0.10x0.15x0.3) 1.09 m3
P. 18 Kiri Pasangan Batu Mortar P =
Type 12
Volume Kanan P= 4.50 m 5.10 m3
p x ( l1 + l2) / 2 x t
7.60 x (0.4+0.8)/ 2 x (2.0+0.8)/2 = 2.25 m3
Pondasi
p xlx t
7.60 x 0.8 x 0.8 = 2.88 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume : 303.60 m3
PEKERJAAN : Tembok Penahan Tanah (TPT) Tanggal :
P. 19 Kanan Pasangan Batu Mortar P =
Type 13
Volume Kanan P= 19.00 m 5.30 m3
p x ( l1 + l2) / 2 x t
19.00 x (0.3+0.4)/ 2 x0.45 = 2.99 m3
Pondasi
p xlx t
19.00 x 0.4 x 0.3 = 2.28 m3
P. 19 + 48.30 m Kanan Pasangan Batu Mortar P =
Type 14
Volume Kanan P= 8.60 m 4.10 m3
p x ( l1 + l2) / 2 x t
8.60x (0.3+0.4)/ 2 x 0.9 = 2.71 m3
Pondasi
p xlx t
8.60 x 0.4 x 0.4 = 1.38 m3
P. 20 Kanan Pasangan Batu Mortar P =
Type 15
Volume Kanan P= 8.20 m 5.00 m3
p x ( l1 + l2) / 2 x t
8.70 x (0.3+0.4)/ 2 x 1.4 = 4.02 m3
Pondasi
p xlx t
8.70 x 0.4 x 0.3 = 0.98 m3
P. 20 Kiri Pasangan Batu Mortar P =
Type 16
Volume Kanan P= 6.00 m 3.20 m3
p x ( l1 + l2) / 2 x t
6.00 x (0.3+0.4)/ 2 x 1.05 = 2.21 m3
Pondasi
p xlx t
6.00 x 0.4 x 0.4 = 0.96 m3
P. 21 Kanan Pasangan Batu Mortar P =
Type 17
Volume Kanan P= 18.00 m 13.00 m3
p x ( l1 + l2) / 2 x t
8.70 x (0.3+0.4)/ 2 x 1.6 = 10.08 m3
Pondasi
p xlx t
8.70 x 0.4 x 0.4 = 2.88 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume : 148.10 m²
PEKERJAAN : Tembok Penahan Tanah (TPT) Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Plester 1 : 5 148.10 m²
TPT
pxl
303.60 x 0,4 121.44 m2
0.95 x 15 14.25 m2
1.13 x 11 12.38 m2
87.10 39,282,100
20.3
12.65
14.5
64.30
0.075
0.0023
0.0728
1.09125 325
0.95
ANALISA UPAH DAN BAHAN
DESA : Sukasetia
JENIS PEKERJAAN : Tembok Penahan Tanah Jalan
LOKASI : Dusun Cinangka
UKURAN :P= 129.00 m
Jumlah Jumlah
No Jenis Pekerjaan Satuan Koef Vol Pek. Hrg Sat.
bahan/upah Total
91.00
231.00
375
#REF! #REF!
#REF!
#REF!
#REF!
2.93
0.633987500000 50,719.00
8,190,000.00 1.01
101,438
0.001 0.010
0.060
0.8
16,638,600
76,320,400
16,638,600 81,925,700
18,010,534
- 99,936,234
15,303,500 124,878,400
1.000 0.00 - 35,000 -
176,000,000
76,063,766
ANALISA UPAH DAN BAHAN
DESA : Sukasetia
JENIS PEKERJAAN : Tembok Penahan Tanah Jalan
LOKASI : Dusun Desa
UKURAN :P= 303.60 m
Jumlah Jumlah
No Jenis Pekerjaan Satuan Koef Vol Pek. Hrg Sat.
bahan/upah Total
Harga Jumlah
Uraian Volume Satuan Satuan Swadaya
(Rp) (Rp)
Bahan
1. Batu Belah 160.00 - 160.00 m3 190,000 -
2. Semen 376.00 3.00 373.00 zak 64,000 192,000
3. Pasir pasang 73.80 0.79 73.01 m3 135,000 106,500
Sub Total 298,500
Alat
Ember 26 3 23.00 buah 12,000 36,000
Benang 5 3 2.00 buah 3,000 9,000
Palu 5 2 1 1.00 buah 150,000 150,000
Skop 2 2 - buah 65,000 130,000
Garfu 2 2 - buah 75,000 150,000
Papan Nama Proyek 1.00 - 1.00 buah 150,000
Prasasti 1.00 - 1.00 buah 350,000
Sub Total
Upah
1. Tukang 91.00 50.00 41.00 hok 90,000 4,500,000
2. Pekerja 231.00 128.00 103.00 hok 80,000 10,240,000
3. Kepala Tukang 10.00 3.00 7.00 hok 95,000
Sub Total 14,740,000
Total 15,513,500
Tono Kartono
:
: APBD PROV TA 2021
DUUSUN DESA
RT 001 0.01066666666667
: P = 85,00 m 13
22040000
Jumlah 344.3750 75815700
APBD PROV 7224978
(Rp)
9694 3,600,000
(6.11)
30,400,000 #REF! 0.0005263157895 52.5
23,872,000 #REF! 20,888,000.00
9,856,500 #REF! 1.660740741
64,128,500 75.200 29,104,500
14.800
276,000 1.54184210526 ###
6,000 7.66667 -
150,000 932,000
-
-
150,000
350,000
932,000
0.00001117
3,690,000 45 2
8,240,000 40000 2.8888888889
665,000
12,595,000 0.09904761904762 69,638,000
77,655,500 83.78% (8,017,500)
9150
ober 2020
h:
giatan
ISNA
eh :
sa
no
7,500,000.00
83.33
0.0930175438596491
76,063,766 (6,425,766)
1 (112.73273403508800)
RENCANA ANGGARAN BIAYA PRASARANA
Propinsi : Jawa Barat No. RAB : 01
Kabupaten : Ciamis Program : PNPM-MPd
Kecamatan : Cihaurbeuti Jenis Kegiatan : TPT Jalan
Desa : Sukasetia Ukuran/Dimensi : P = 348,50 m
Bahan
1. Batu Belah 264.00 104.00 160.00 m3 I.a 100,000 10,400,000 16,000,000 26,400,000
2. Semen 630.00 257.00 373.00 zak I.a 58,500 15,034,500 21,820,500 36,855,000
3. Pasir pasang 123.90 50.89 73.01 m3 I.a 100,000 5,088,889 7,301,111 12,390,000
Sub Total 30,523,389 45,121,611 75,645,000
Alat
Ember 26 15 11.00 buah II.a 5,000 75,000 55,000 130,000
Benang 13 8 5.00 buah II.a 4,250 34,000 21,250 55,250
Drum Air 2 2 - buah II.a 100,000 200,000 - 200,000
Meteran 3 3 - buah II.a 15,000 45,000 - 45,000
Slang Air 28 28 - m II.a 6,000 168,000 - 168,000
Linggis 7 7 - buah II.a 30,000 210,000 - 210,000
Cangkul - - - buah II.a 40,000 - - -
Palu 1/2 5 5 - buah II.a 35,000 175,000 - 175,000
Palu 5 4 4 - buah II.a 135,800 543,200 - 543,200
Skop 1 1 - buah II.a 82,950 82,950 - 82,950
Garfu 1 - 1.00 buah II.a 72,400 - 72,400 72,400
Papan Proyek 1 - 1 buah I.a 100,000 - 100,000 100,000
Prasasti 1 - 1 buah I.a 350,000 - 350,000 350,000
Sub Total 1,533,150 598,650 2,131,800
Upah
1. Tukang 217.00 176.00 41.00 hok III.a/Iva 37,500 6,600,000 1,537,500 8,137,500
2. Pekerja 505.00 79.67 425.33 hok III.a/Iva 26,250 2,091,250 11,165,000 13,256,250
Sub Total 8,691,250 12,702,500 21,393,750
Total 40,747,789 58,422,761 99,170,550
Total Biaya (PNPM MP+Swadaya) 99,170,550
Total Biaya PNPM MP 58,422,761
Sumber Dana
Total Biaya Swadaya 40,747,789
Catatan :
1. Sumbangan dalam bentuk bahan, upah, dan alat ditulis dalam kolom volume dari swadaya
2. Nilai RAB didapat dari kolom Volume Dari Dana dikalikan dengan kolom harga satuan yang kemudian ditotalkan
3. Sumbangan dalam bentuk uang dimasukan pada baris terbawah(sumber dana dari swadaya)
4. Swadaya dalam bentuk lahan ditulis dalam format lain
9694 3,600,000
43.99
#REF! 2000000 52.5 7,500,000.00
#REF! 20,888,000.00 83.33
#REF!
126.000 10,097,611
24.800
18.40000
194.40000 0.230039789473801
50.88888889
3,790,700
TPT SKST 75,815,700.00 1,516,300.00
op 5% 3,790,700.00 2,274,400.00
-
#REF! #REF!
-
137 2
40000
0.09904761904762 69,638,000 76,063,766
11,215,239
112.152389
#REF! 41.09% 191.7135
#REF! 0.697464277858981
50
0 0
69.75% #REF!
(40,747,789)
(18,478,889)
]
83800
3.19238095238095
3.19047619
9150
0.122
3,345,400
127.4438095238
5250
0.2
1644000
63
0.0930175438596491
(6,425,766)
(112.73273403508800)
REKAPITULASI ANGGARAN BIAYA PRASARANA
Jenis Prasarana : Tembik Penahan Tanah Jalan
Dra. Rina Takarina, Msi Johan Wahyudi, ST / Andi Yogaswara, SP Toni Hidayat
NIP. 19651201.199303.2.006
Jumlah Total Bobot %
PNPM Swadaya
83,897,000 298,500 349.66%
15,070,000
#REF! 14,740,000
#REF! 62.81% 85.00% 85,380,000
3,172,100
105,736,800 15,513,500 440.68%
2,475,000 14,740,000
144.00 -
DAFTAR HARGA BAHAN & UPAH
URAIAN HARGA
Bahan
1. Batu Belah 80,000
2. Semen 58,500
3. Pasir pasang 75,000
4. Papan Proyek 100,000
5. Prasasti 750,000
Alat
Ember 5,000
Benang 1,500
Drum Air 50,000
Meteran 15,000
Slang Air 1,000
Linggis 30,000
Cangkul 40,000
Palu 1/2 35,000
Palu 5 135,000
Upah
1. Tukang 45,000 60,000
2. Pekerja 37,500 50,000
3. Mandor 37,500 50,000
RENCANA KERJA
TEMBOK PENAHAN TANAH
DESA CIOMAS KEC. PANJALU
TAHUN 2003
MINGGU KE
No URAIAN PEKERJAAN 1 2 3 4 5 6 7 8 9 10 11 12
1 JALAN TELPORD
PERSIAPAN
PEMBENTUKAN BADAN JALAN
PENIMBUNAN + TURAP
PENGADAAN BAHAN
PEMASANGAN BATU
PENGHAMPARAN SIRTU
PEMADATAN DENGAN MESIN GILAS
26 Kode Peke : 03.2.5
1 m3 Pasangan Pondasi Batu Kali 1 PC :5 Pasir
Keuntungan 10 %
Jumlah Semua
- 92,125.00
- 2,937.60 0.0544 54000000
- 45,560.00
45,000.00 -
24,000.00 -
2,550.00 -
3,187.50 -
74,737.50 140,622.60 215,360.10
21,536.01
236,896.11
REKAPITULASI ANGGARAN BIAYA PRASARANA
Jenis Prasarana : 1. Tembok Penahan Tanah Jalan
2. SPP
PNPM#REF! Swadaya
#REF! #REF! PNPM Swadaya 0.00% PNPM#REF! Swadaya
#REF!
75,223,200.00
100.00% 37,152,100
Swadaya 31%
ber 2009
53.21%
1.48%
40.31%
01+045PNPM-Mandiri Perdesaan Integrasi
Form - 36
Mengetahui,
FT / FK PJOK
3.05
3.06204 3.06
244000
244963.2 244800
58.80%
LAPORAN PENGGUNAAN DANA TAHAP I
Komulatif Laporan Lalu Realisasi Laporan Ini Komulatif s/d Laporan Ini
No Uraian Sat Harga Sat
Vol Jmlh Biaya Vol Jmlh Biaya Vol Jmlh Biaya
PNPM-
PNPM-MPd PNPM-MPd PNPM-MPd PNPM-MPd
MPd PNPM-MPd
1. Tembok Penahan Tanah
1.1. Batu Belah m3 190,000 - - 71.00 13,490,000 71.00 13,490,000
1.2. Semen zak 64,000 - - 150.00 9,600,000 150.00 9,600,000
1.3. Pasir Pasang m3 135,000 - - 20.20 2,727,000 20.20 2,727,000
Sub Total - 25,817,000 25,817,000
2 Alat
Ember Bh 12,000 - - 6.00 72,000 6.00 72,000
Benang Bh 3,000 - - 2.00 6,000 2.00 6,000
Garfu Bh 75,000 - - - - - -
Papan Proyek Bh - - - 1.00 - 1.00 -
Prasasti m - - - - - - -
Sub Total - 78,000 78,000
3 Upah
4.1. TPT
4.1.1. Tukang HOK 90,000 - - 73.33 6,600,000 73.33 6,600,000
4.1.2. Pekerja HOK 80,000 - - 144.00 11,520,000 144.00 11,520,000
Sub Total - 18,120,000 18,120,000
Total I 44,015,000 44,015,000
4 Operasional UPK 2% 1,698,800 - 650,000 650,000
Operasional TPK 3% 2,548,200 - 1,000,000 1,000,000
Sub Total - 1,650,000 1,650,000
Total - 45,665,000 45,665,000
Saldo - -
Jumlah Total 45,665,000
Mengetahui :
FK /FT PJOK
Mengetahui,
FT / FK PJOK
Volume
Pengajuan Unit / Harga Satuan
Uraian Real. s/d. tahap Jumlah Jumlah (Rp.)
Kebutuhan sekarang Satuan (Rp.)
lalu Swadaya Kumulatif
1. Bahan. TPT
1.1. Batu Belah 0.00 - 3.00 #REF! m3 190,000 #REF!
1.2. Semen 3.00 - 12.80 #REF! zak 64,000 #REF!
1.3. Pasir Pasang 0.79 - 21.20 #REF! m3 135,000 #REF!
1.4. Papan Nama Proyek #REF! - - #REF! #REF! #REF! #REF!
1.5. Prasasti #REF! - - #REF! #REF! #REF! #REF!
Sub Total #REF!
2. Bahan Gorong-gorong
2.1 Batu Belah 3.70 - - - #REF! 190,000 -
2.2 Semen 4.00 - - - #REF! 64,000 -
2.3 Pasir Pasang 1.70 - - - #REF! 135,000 -
2.4 Buis Beton dia 0,4 P=5 7.00 - - - #REF! #REF! #REF!
Sub Total #REF!
3. Alat
Ember 3.00 - 12.00 12.00 buah 12,000 144,000
Benang 3.00 - 7.00 7.00 buah 3,000 21,000
Garfu 0.00 - 1.00 1.00 buah 75,000 75,000
Papan Proyek 0.00 - 2.00 2.00 buah - -
Prasasti 0.00 - 27.00 27.00 m - -
#REF! 0.00 - 5.00 5.00 #REF! #REF! #REF!
#REF! 0.00 - 10.00 10.00 #REF! #REF! #REF!
#REF! 0.00 - 5.00 5.00 #REF! #REF! #REF!
#REF! 1.00 - 2.00 2.00 #REF! #REF! #REF!
Sub Total #REF!
4. Upah
4.1 TPT
4.1.1. Tukang - - 8.00 #REF! HOK 90,000 720,000
4.2.2. Pekerja - - 76.00 #REF! HOK 80,000 6,080,000
Sub Total 6,800,000
4.2 Gorong-gorong
4.2.1. Tukang 9.33 - - - 0 90,000 -
4.2.2. Pekerja 28.00 - - - 0 80,000 -
Sub Total -
Total I #REF!
Operasional UPK 2% - - - 0 -
Operasional TPK 3% - - - 0 -
Sub total -
Total Pengajuan #REF!
9,000
-
#REF!
#REF!
(107.83)
-263% (211.00)
305% -205%
(40,676,500) 292,500.00 0.25
#REF! 31888000
1516000
30372000
20000 14500
0.266666666666667 0.193333333333333
LAPORAN PENGGUNAAN DANA TAHAP II
KEGIATAN TEMBOK PENAHAN TANAH JALAN ( TPT )
Komulatif Laporan Lalu Realisasi Laporan Ini Komulatif s/d Laporan Ini
No Uraian Sat Harga Sat
Vol Jmlh Biaya Vol Jmlh Biaya Vol Jmlh Biaya
PNPM- PNPM- PNPM-
PNPM-MPd PNPM-MPd PNPM-MPd
MPd MPd MPd
1. Tembok Penahan Tanah
1.1. Batu Belah m3 190,000 71.00 13,490,000 82.00 15,580,000 153.00 29,070,000
1.2. Semen zak 64,000 150.00 9,600,000 206.00 13,184,000 356.00 22,784,000
1.3. Pasir Pasang m3 135,000 20.20 2,727,000 39.90 5,386,500 60.10 8,113,500
Sub Total 25,817,000 34,150,500 59,967,500
2 Alat
Ember Bh 12,000 6.00 72,000 17.00 204,000 23.00 276,000
Benang Bh 3,000 2.00 6,000 - - 2.00 6,000
Garfu Bh 75,000 - - - - - -
Papan Proyek Bh - 1.00 - (1.00) - - -
Prasasti m - - - - - - -
Sub Total 78,000 204,000 282,000
3 Upah
4.1. TPT
4.1.1. Tukang HOK 90,000 73.33 6,600,000 75.50 6,795,000 148.83 13,395,000
4.1.2. Pekerja HOK 80,000 144.00 11,520,000 170.00 13,600,000 314.00 25,120,000
Sub Total 18,120,000 20,395,000 38,515,000
Total I 44,015,000 54,749,500 98,764,500
4 Operasional UPK 2% 1,698,800 650,000 650,000 1,300,000
Operasional TPK 3% 2,548,200 1,000,000 900,000 1,900,000
Sub Total 4,247,000 1,650,000 1,550,000 3,200,000
Total 45,665,000 56,299,500 101,964,500
Saldo - - -
Jumlah Total 45,665,000 56,299,500 101,964,500
Mengetahui :
FK /FT PJOK
### #REF!
#REF!
### #REF!
#REF!
PROGRAM NASIONAL PEMBERDAYAAN MASYARAKAT MANDIRI PERDESAAN INTEGRASI
( PNPM-MPd INTEGRASI )
RENCANA PENGGUNAAN DANA TAHAP KE III
KEGIATAN TPT JALAN
Desa Sukasetia Kecamatan Cihaurbeuti Kabupaten Ciamis Jumlah
Volume Harga
Unit /
Uraian Real. s/d. tahap lalu Pengajuan sekarang Jumlah Satuan
Kebutuhan Satuan
PNPM-MPd PNPM-MPd Kumulatif (Rp.)
PNPM-
1. Bahan. TPT MPd (Rp.)
1.1. Batu Belah 160.00 153.00 7.00 160.00 m3 190,000 1,330,000
1.2. Semen 373.00 356.00 17.00 373.00 zak 64,000 1,088,000
1.3. Pasir Pasang 73.01 60.10 12.91 73.01 m3 135,000 1,743,000
Sub Total 4,161,000
2. Alat
Ember 23.00 23.00 - 23.00 buah 12,000 -
Benang 2.00 2.00 - 2.00 buah 3,000 -
Garfu - - - - buah 75,000 -
Papan Proyek - - - - buah - -
Prasasti - - - - m - -
Sub Total -
3. Upah
4.1 TPT
4.1.1. Tukang 41 149 (107.83) 41 HOK 90,000 (9,705,000)
4.2.2. Pekerja 103 314 (211.00) 103 HOK 80,000 (16,880,000)
Sub Total (26,585,000)
4. OP
Operasional UPK 2% 479,900 1,300,000 (820,100) 479,900 (820,100)
Operasional TPK 3% 719,800 1,900,000 (1,180,200) 719,800 (1,180,200)
Sub total 1,199,700 3,200,000 (2,000,300) 1,199,700 (2,000,300)
Total Pengajuan (24,424,300)
( Sembilan Belas Juta Empat Ratus Tiga Puluh Sembilan Ribu Tujuh Ratus Lima Puluh Rupiah )
Mengetahui,
FK / FT PJOK
#REF!
#REF!
PROGRAM NASIONAL PEMBERDAYAAN MASYARAKAT MANDIRI PERDESAAN INTEGRASI
( PNPM-MPd INTEGRASI )
LAPORAN PENGGUNAAN DANA TAHAP III
Desa Sukasetia Kecamatan Cihaurbeuti Kabupaten Ciamis
Komulatif Laporan Lalu Realisasi Laporan Ini Komulatif s/d Laporan Ini
Vol Jmlh Biaya Vol Jmlh Biaya Vol Jmlh Biaya Vol Jmlh Biaya Vol Jmlh Biaya
No Uraian Sat Harga Sat
PNPM-
PNPM-MPd
PNPM-MPd DDUB DDUB MPd
PNPM-MPd DDUB DDUB PNPM-MPd DDUB PNPM-MPd DDUB
1. Tembok Penahan Tanah
1.1. Batu Belah m3 190,000 153.00 ### #REF! #REF! 7.00 1,330,000 #REF! #REF! 160.00 #REF! 30,400,000 #REF!
1.2. Semen zak 64,000 356.00 22,784,000 #REF! #REF! 17.00 1,088,000 #REF! #REF! 373.00 #REF! 23,872,000 #REF!
1.3. Pasir Pasang m3 135,000 60.10 8,113,500 #REF! #REF! 12.91 1,743,000 #REF! #REF! 73.01 #REF! 9,856,500 #REF!
1.4. Papan Nama Proyek ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
1.5. Prasasti ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub Total #REF! #REF! #REF! #REF! #REF! #REF!
2 Bahan Gorong-gorong
2.1 Batu Belah m3 190,000 - - - - 23.00 4,370,000 #REF! #REF! 23.00 #REF! #REF! #REF!
2.2 Semen Zak 64,000 - - - - - - #REF! #REF! - #REF! #REF! #REF!
2.3 Pasir Pasang m3 135,000 - - - - - - #REF! #REF! - #REF! #REF! #REF!
2.4 Buis Beton dia 0,4 P=7 Bh 65,000 - - - - - - #REF! #REF! - #REF! #REF! #REF!
Sub Total - - 4,370,000 #REF! #REF! #REF!
3 Alat
3.1. Ember Bh 12,000 23.00 276,000 #REF! #REF! 4.00 48,000 #REF! #REF! 27.00 #REF! 324,000 #REF!
3.2. Benang Bh 3,000 2.00 6,000 #REF! #REF! - - #REF! #REF! 2.00 #REF! 6,000 #REF!
3.3. Drum Air Bh 75,000 - - #REF! #REF! ### (8,087,500) #REF! #REF! (107.83) #REF! (8,087,500) #REF!
3.4. Meteran Bh - - - #REF! #REF! ### - #REF! #REF! (211.00) #REF! - #REF!
3.5. Salang Air 1/2" m - - - #REF! #REF! - - - - - #REF! - #REF!
3.6. Linggis Bh #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.7. Cangkul Bh #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.8. Palu 1/2 Bh #REF! #REF! #REF! #REF! #REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.9. Palu 5 Bh #REF! #REF! #REF! #REF! #REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub Total #REF! #REF! #REF! #REF! #REF! #REF!
4 Upah
4.1. TPT
4.1.1. Tukang HOK 90,000 148.83 13,395,000 #REF! #REF! #REF! #REF! - - #REF! #REF! #REF! #REF!
4.1.2. Pekerja HOK 80,000 314.00 25,120,000 #REF! #REF! #REF! #REF! - - #REF! #REF! #REF! #REF!
Sub Total 38,515,000 #REF! #REF! - #REF! #REF!
4.2. Gorong - gorong
4.2.1. Tukang HOK 90,000 - - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.2.2. Pekerja HOK 80,000 - - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub Total - - #REF! #REF! #REF! #REF!
Total I #REF! #REF! #REF! #REF! #REF! #REF!
5 Operasional UPK 2% #REF! 1,300,000 #REF! #REF!
Operasional TPK 3% #REF! 1,900,000 #REF! #REF!
Sub Total 3,200,000 #REF! #REF!
Total #REF! #REF! #REF! #REF! #REF! #REF!
Saldo - - - - #REF! -
Jumlah Total #REF! #REF! #REF! #REF! #REF! #REF!
Jumlah Total PNPM-MPd + DDUB #REF! #REF! #REF!
Mengetahui :
FK /FT PJOK
3.06204
244963.2
#REF!
#REF!
#REF!
#REF!
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 100.70 m
PEKERJAAN : Tembok Penahan TTanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Tembok Penahan T 100.70 m
VOLUME PEKERJAAN
Pasangan Batu Mortar P = 59.00 m3
P.0 Kanan Type 1
Volume Kanan 6.00 m 14.70 m3
p x ( l1 + l2) / 2 x t
30 x (0.3+0.4)/ 2 x 0.6 11.70 m3
Pondasi
p xlx t
30 x 0.4 x 0.3 3.00 m3
Pondasi
p xlx t
22 x 0.4 x 0.3 6.00 m3
Pondasi
p xlx t
12 x 0.4 x 0.3 2.25 m3
Pondasi
p xlx t
38 x 0.4 x 0.3 3.60 m3
Pondasi
p xlx t
50 x 0.4 x 0.3 3.20 m3
Pondasi
p xlx t
8 x 0.4 x 0.3 0.34 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 100.70 m
PEKERJAAN : Tembok Penahan TTanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
P.3 + 8 m Kanan Type 7
Volume Kanan 0.00 m 0.00 m3
p x ( l1 + l2) / 2 x t
18 x (0.3+0.4)/ 2 x 0.3 0.00 m3
Pondasi
p xlx t
18 x 0.4 x 0.3 0.00 m3
Pondasi
p xlx t
15 x 0.4 x 0.3 0.00 m3
Pondasi
p xlx t
50 x 0.4 x 0.4 0.00 m3
Pondasi
p xlx t
11 x 0.4 x 0.3 0.00 m3
Pondasi
p xlx t
20.30x 0.8 x 0.8 0.00 m3
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 100.70 m3
PEKERJAAN : Tembok Penahan TTanggal :
P. 17 + 21 m Kanan Pasangan Batu Mortar P =
Type 11
Volume Kanan 0.00 m 0.00 m3
p x ( l1 + l2) / 2 x t
29 x (0.3+0.8)/ 2 x 2.8 0.00 m3
Pondasi
p xlx t
29 x 0.8 x 0.8 0.00 m3
Pondasi
p xlx t
7.60 x 0.6 x 0.6 0.00 m3
Pondasi
p xlx t
32.20 x 0.4 x 0.3 0.00 m3
Pondasi
p xlx t
1.70 x 0.4 x 0.3 0.00 m3
Pondasi
p xlx t
8.70 x 0.4 x 0.4 0.00 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 40.30 m²
PEKERJAAN : Tembok Penahan TTanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Plester 1 : 5 40.30 m²
TPT
pxl
100.70 x 0,4 40.28 m2
49.49%
RENCANA ANGGARAN BIAYA PRASARANA
Propinsi : Jawa Barat No. RAB : 01
Kabupaten : Ciamis Program : PNPM-MPd Integrasi
Kecamatan : Cihaurbeuti Jenis Kegiatan : TPT Jalan
Desa : Sukasetia Ukuran/Dimensi : P = 218,00 m
Bahan
1. Batu Belah 71.00 - 71.00 m3 I.a 190,000 - 13,490,000 13,490,000
2. Semen 168.00 18.00 150.00 zak I.a 64,000 1,152,000 9,600,000 10,752,000
3. Pasir pasang 33.20 13.00 20.20 m3 I.a 135,000 1,755,000 2,727,000 4,482,000
Sub Total 2,907,000 25,817,000 28,724,000
Alat
Ember 11 5 6.00 buah II.a 12,000 60,000 72,000 132,000
Benang 6 4 2.00 buah II.a 3,000 12,000 6,000 18,000
Drum Air - - - buah II.a 100,000 - - -
Meteran - - - buah II.a 15,000 - - -
Slang Air - - - m II.a 25,000 - - -
Linggis - - - buah II.a 30,000 - - -
Cangkul - - - buah II.a 75,000 - - -
Palu 1/2 - - - buah II.a 35,000 - - -
Palu 5 2 1 1 buah II.a 150,000 150,000 150,000 300,000
Skop 2 2 - buah II.a 65,000 130,000 - 130,000
Garfu 2 2 - buah II.a 75,000 150,000 - 150,000
Papan Proyek 1 - 1 buah I.a 150,000 - 150,000 150,000
Prasasti - - - buah I.a 350,000 - - -
Sub Total 502,000 378,000 880,000
Upah
1. Tukang 58.40 (14.93) 73.33 hok III.a/Iva 45,000 (672,000) 3,300,000 2,628,000
2. Pekerja 135.88 (8.12) 144.00 hok III.a/Iva 37,500 (304,557) 5,400,000 5,095,443
Sub Total (976,557) 8,700,000 7,723,443
Total 2,432,443 34,895,000 37,327,443
Total Biaya (PNPM MP+Swadaya) 37,327,443
Total Biaya PNPM MP 34,895,000
Sumber Dana
Total Biaya Swadaya 2,432,443
Catatan :
1. Sumbangan dalam bentuk bahan, upah, dan alat ditulis dalam kolom volume dari swadaya
2. Nilai RAB didapat dari kolom Volume Dari Dana dikalikan dengan kolom harga satuan yang kemudian ditotalkan
3. Sumbangan dalam bentuk uang dimasukan pada baris terbawah(sumber dana dari swadaya)
4. Swadaya dalam bentuk lahan ditulis dalam format lain
Diperiksa :
FT Kec Ketua TPK
44.94%
15.68%
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 55.00 m
PEKERJAAN : Tembok Penahan Tanah ( Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Tembok Penahan Tanah p 55.00 m
VOLUME PEKERJAAN
Pasangan Batu Mortar P = 85.10 m3
P. 11 Kiri Pasangan Batu Mortar P =
Type 9
Volume Kanan 20.00 m 8.80 m3
p x ( l1 + l2) / 2 x t
50 x (0.3+0.4)/ 2 x 0.8 5.60 m3
Pondasi
p xlx t
50 x 0.4 x 0.4 = 3.20 m3
P. 16 Kiri Pasangan Batu Mortar P=
Type 10
Volume Kanan 0.00 m 0.00 m3
p x ( l1 + l2) / 2 x t
11 x (0.3+0.4)/ 2 x 0.6 0.00 m3
Pondasi
p xlx t
11 x 0.4 x 0.3 = 0.00 m3
Pondasi
p xlx t
20.30x 0.8 x 0.8 = 3.84 m3
P. 17 + 21 m Kanan Pasangan Batu Mortar P=
Type 11
Volume Kanan 29.00 m 63.20 m3
p x ( l1 + l2) / 2 x t
29 x (0.3+0.8)/ 2 x 2.8 44.66 m3
Pondasi
p xlx t
29 x 0.8 x 0.8 = 18.56 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi #REF!
Volume #REF! m3
#REF! Tanggal :
P. 18 Kiri Pasangan Batu Mortar P =
Type 12
Volume Kanan 0.00 m 0.00 m3
p x ( l1 + l2) / 2 x t
7.60 x (0.3+0.6)/ 2 x (2.0+0.8 0.00 m3
Pondasi
p xlx t
7.60 x 0.6 x 0.6 = 0.00 m3
Pondasi
p xlx t
32.20 x 0.4 x 0.3 = 0.00 m3
Pondasi
p xlx t
1.70 x 0.4 x 0.3 = 0.00 m3
Pondasi
p xlx t
8.70 x 0.4 x 0.4 = 0.00 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi #REF!
Volume 22.00 m²
#REF! Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Plester 1 : 5 22.00 m²
TPT
pxl
55.00 x 0,4 22 m2
9,597,680
36,801,600
RENCANA ANGGARAN BIAYA PRASARANA
Propinsi : Jawa Barat No. RAB : 01
Kabupaten : Ciamis Program : PNPM-MPd Integrasi
Kecamatan : Cihaurbeuti Jenis Kegiatan : TPT Jalan
Desa : Sukasetia Ukuran/Dimensi : 55.00
Bahan
1. Batu Belah 102.00 20.00 82.00 m3 I.a 190,000 3,800,000 15,580,000
2. Semen 239.00 33.00 206.00 zak I.a 64,000 2,112,000 13,184,000
3. Pasir pasang 47.40 7.50 39.90 m3 I.a 135,000 1,012,500 5,386,500
Sub Total 6,924,500 34,150,500
Alat
Ember 11 6 5.00 buah II.a 12,000 72,000 60,000
Benang 7 4 3.00 buah II.a 3,000 12,000 9,000
Drum Air - - buah II.a 100,000 - -
Meteran - - buah II.a 15,000 - -
Slang Air - - m II.a 25,000 - -
Linggis - - buah II.a 30,000 - -
Cangkul - - buah II.a 75,000 - -
Palu 1/2 - - buah II.a 35,000 - -
Palu 5 2 - buah II.a 150,000 - -
Skop 2 - buah II.a 65,000 - -
Garfu 2 - buah II.a 75,000 - -
Papan Proyek 1 - buah I.a 150,000 - -
Prasasti - - buah I.a 350,000 - -
Sub Total 84,000 69,000
Upah
1. Tukang 79.40 3.90 75.50 hok III.a/Iva 45,000 175,500 3,397,500
2. Pekerja 189.00 19.00 170.00 hok III.a/Iva 37,500 712,500 6,375,000
Sub Total 888,000 9,772,500
Total 7,896,500 43,992,000
Total Biaya (PNPM MP+Swadaya) 51,888,500
Total Biaya PNPM MP 43,992,000
Sumber Dana
Total Biaya Swadaya 7,896,500
Catatan :
1. Sumbangan dalam bentuk bahan, upah, dan alat ditulis dalam kolom volume dari swadaya
2. Nilai RAB didapat dari kolom Volume Dari Dana dikalikan dengan kolom harga satuan yang kemudian ditotalkan
3. Sumbangan dalam bentuk uang dimasukan pada baris terbawah(sumber dana dari swadaya)
4. Swadaya dalam bentuk lahan ditulis dalam format lain
Diperiksa :
FT Kec Ketua TPK
Johan Wahyudi, ST Toni Hidayat
MPd Integrasi
Jumlah
Total
(Rp)
19,380,000
15,296,000
6,399,000
41,075,000
132,000 -
21,000 -
- -
- -
- -
- - 114.00
- - 19
- -
- -
- -
- -
- 1
- 1
153,000
3,573,000
7,087,500
10,660,500
51,888,500
183.34%
Ketua TPK
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 249.00 m
PEKERJAAN : Tembok Penahan Tanah ( Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Tembok Penahan Tanah p 249.00 m
VOLUME PEKERJAAN
Pasangan Batu Mortar P = 77.20 m3
P.0 Kanan Type 1
Volume Kanan 30.00 m 9.90 m3
p x ( l1 + l2) / 2 x t
30 x (0.3+0.4)/ 2 x 0.6 6.30 m3
Pondasi
p xlx t
30 x 0.4 x 0.3 = 3.60 m3
Pondasi
p xlx t
22 x 0.4 x 0.3 = 2.64 m3
Pondasi
p xlx t
12 x 0.4 x 0.3 = 1.44 m3
Pondasi
p xlx t
38 x 0.4 x 0.3 = 4.56 m3
Pondasi
p xlx t
50 x 0.4 x 0.3 = 6.00 m3
Pondasi
p xlx t
8 x 0.4 x 0.3 = 0.96 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 249.00 m
PEKERJAAN : Tembok Penahan Tanah ( Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
P.3 + 8 m Kanan Type 7
Volume Kanan 13.00 m 2.90 m3
p x ( l1 + l2) / 2 x t
18 x (0.3+0.4)/ 2 x 0.3 1.37 m3
Pondasi
p xlx t
18 x 0.4 x 0.3 = 1.56 m3
Pondasi
p xlx t
15 x 0.4 x 0.3 = 1.80 m3
Pondasi
p xlx t
50 x 0.4 x 0.4 = 8.00 m3
Pondasi
p xlx t
11 x 0.4 x 0.3 = 1.32 m3
Pondasi
p xlx t
20.30x 0.8 x 0.8 = 0.00 m3
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 249.00 m3
PEKERJAAN : Tembok Penahan Tanah ( Tanggal :
P. 17 + 21 m Kanan Pasangan Batu Mortar P =
Type 11
Volume Kanan 0.00 m 0.00 m3
p x ( l1 + l2) / 2 x t
29 x (0.3+0.8)/ 2 x 2.8 0.00 m3
Pondasi
p xlx t
29 x 0.8 x 0.8 = 0.00 m3
Pondasi
p xlx t
7.60 x 0.6 x 0.6 = 0.00 m3
Pondasi
p xlx t
32.20 x 0.4 x 0.3 = 0.00 m3
Pondasi
p xlx t
1.70 x 0.4 x 0.3 = 0.00 m3
Pondasi
p xlx t
8.70 x 0.4 x 0.4 = 0.00 m3
Dibuat Oleh Tanda Tangan
Toni Hidayat
Kecamatan : Cihaurbeuti
Desa : Sukasetia
Lokasi : Dusun Tanjung Asih
Volume 99.60 m²
PEKERJAAN : Tembok Penahan Tanah ( Tanggal :
VOLUME PEKERJAAN
SKETSA PERHITUNGAN VOLUME VOLUME
Plester 1 : 5 99.60 m²
TPT
pxl
249.00 x 0,4 99.6 m2