THK R E I N F O R C E M E N T LEFT SUPPORT MIDSPAN RIGHT SUPPORT DIMENSION BAR Ø MIDDLE STIRRUPS
MARK PARALLEL TO SHORT SPAN PARALLEL TO LONG SPAN REMARKS MARK B x D (mm) (mm)
(mm) BAR
TOP BOTTOM TOP BOTTOM TOP BOTTOM
@ SUPPORT @ MIDSPAN @ SUPPORT @ MIDSPAN
ROOF BEAMS
TB 12mmØ @ 200 mm O.C. TB 12mmØ @ 200 mm O.C.
S-1 120 TWO - WAY RB-1 4 2 2 4 4 2 200 x 350 16 mm A
BB 12mmØ @ 400 mm O.C. 12mmØ @ 200 mm O.C. BB 12mmØ @ 400 mm O.C. 12mmØ @ 200 mm O.C.
RB-2 3 2 2 3 3 2 200 x 350 16 mm A
TB 12mmØ @ 200 mm O.C.
S-2 120 ONE - WAY RCB-1 4 2 4 2 200 x 350 16 mm A
BB 12mmØ @ 400 mm O.C. 12mmØ @ 200 mm O.C. BB 10mmØ @ 300 mm O.C. 10mmØ @ 300 mm O.C.
DB-1 5 2 2 5 5 2 200 x 400 16 mm 2-12 mm A
DB-2 4 2 2 4 4 2 200 x 400 16 mm A
SECOND FLOOR BEAMS
B-1 5 2 2 5 5 2 200 x 400 16 mm 2-12 mm A
B-2 4 2 2 4 4 2 200 x 400 16 mm A
CB-1 5 2 5 2 200 x 400 16 mm 2-12 mm A
CB-2 4 2 4 2 200 x 400 16 mm A
GROUND FLOOR BEAMS
FTB-1 2 2 2 2 2 2 200 x 300 16 mm A
STIRRUPS "A" 10mm. Ø 4 @ 50mm., 4 @ 100mm., 2 @ 150mm., REST @ 200mm. O.C.
GRID GRID
L/4 L/4 CANTILEVER BEAM
"B"
TOP BARS TOP BARS
TOP BARS
ADD'L LEFT CONTINUOUS
ADD'L RIGTH
TOP BARS
WEB BARS
"D"
BOT. BARS
BOTTOM BARS BOTTOM BARS
CONTINUOUS ADDITIONAL
50 50 STIRRUPS 50 50
S/2 S/4
TYP. SECTION
L/5 L/5
S (SHORT SPAN )
REPUBLIC ACT NO. 9266 PROJECT TITLE: OWNER: SHEET CONTENTS: CADD BY: SHEET NO:
Drawings and specifications duly signed, stamped or DESIGN BY:
sealed, as instruments of service, are the intellectual
properties and documents of the architect, whether
the object for which they are made is executed or not.
PROPOSED TWO (2) - STOREY SCHEDULE OF SLAB
SCHEDULE OF BEAM
CHECKED BY: S
architectural designs It shall be unlawful for any person, without the consent SINGLE-DETACHED RESIDENTIAL BUILDING APPROVED BY:
of the architect or author of said documents to SCHEDULE OF FOOTING
duplicate or to make copies of said documents for use ANDREW C. ONGTECO GENERAL SPECIFICATIONS
(+63922) 8011682,
52 Marvex Drive, Balintawak, QC.
in the repetition of and for other projects or buildings,
whether executed partly or in whole. LOCATION: TAAL CRYSTAL ESTATE ALFONSO, CAVITE
REVISION:
DATE:
1