Draw neatly
a)
Learning Phase Steady State Phase
Productivity
Time
Productivity
Estimate
- Quantity of Work
Initial Duration
- Weather
Estimation
- Number of Crews
Overall Adjustment
(e.g. Learning)
Activity Duration
Estimate