Professional Documents
Culture Documents
DECLARATION
We hereby declare the content of this report is fully and accurately contains all the tasks that
we perform in our project time. We declare that all of the necessary contents and
requirements have been meet. This final report for internship program has been submitted to
department of Hydraulic and Water Resource Engineering.
AUHHC Page i
Design of storage dam for Arjo Dedessa irrigation project
ACKNOWLEDGEMENT
First of all we would like to thanks for God who helped from the beginning of our work up
to the final of our work. Surly, we cannot do anything if God not give the power to reach.
Next to this we would like to express our deepest thank to Ambo University Hachalu
Hundessa Campus department of hydraulics and water resource engineering lectures and
workers. My deepest thanks go to my Advisor Mr. Firaol for his valuable advice and
encouragement.
AUHHC Page ii
Design of storage dam for Arjo Dedessa irrigation project
EXCUTIVE SUMMARY
Designing of a storage dam for Arjo Dedessa irrigation project consists of legitimate work on
the irrigation scheme, to irrigate 80000ha command area, which is used to enhance amount
of sugarcane for Arjo sugar factory at the period of dry season by storing water. The report
consists of background information of the project area, such as soil, climate, crop water
demand assessment, the selection of crops, Hydrologic analysis, storage dam design, and
conclusion.
The 1st section describes that general information on the project area, i.e. statement of the
problems, objective of the project, and description of the project area, scope of the arjo
Dedessa irrigation project and all necessity of the project.
The second section shows overall irrigation water assessment, which is Selection and land
allocation of crops grown has been made by considering different factors like weather
condition how much water is losses through evaporation by crop, infiltration and other
similar causes which limit the crop production using appropriate techniques. Irrigation water
demand assessment for the selected crops has been computed being by the cropwatt8
software package. The software solves how much duty of water is needed during its base
period of crop. Maximum daily water demand in 24hrs watering of the crop is 0.4 l/se/ha,
Therefore to fulfill demand of water to supply 80000ha command area, it needs amount of
discharge 32m3/sec. Next hydrological analysis has been conducted based on 30years
maximum daily stream flow data, after unrecorded data is estimated and filled using linear
regression method to know amount of firm discharge, consistency of flow, probability of flood
occurrence , risk, reliability and other different parameters are solved. The frequency
analysis has been carried out by Log Pearson Type III distribution method due to Skewness
and kurtosis relation based and probability of occurrence in 1000return period peak flood
discharge is 1508m3/sec. From the comparison between demand of irrigation and
availability of firm discharge in the river, the firm flow is much smaller than the demand.
Based on the fact it is necessary to store water by providing Arjo Dedessa storage dam.
Finally, conclusion has been drawn has been made on the design and management system of
the project.
Contents
DECLARATION ................................................................................................................... i
ACKNOWLEDGEMENT ..................................................................................................... ii
ACRONYMS ....................................................................................................................... ix
1 INTRODUCTION ............................................................................................................. 1
AUHHC Page iv
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page v
Design of storage dam for Arjo Dedessa irrigation project
CONCLUSION ................................................................................................................... 31
REFERENCES ................................................................................................................... 32
AUHHC Page vi
Design of storage dam for Arjo Dedessa irrigation project
LIST OF FIGURE
Figure 1Location Map of Dedessa catchment (source from Dedessa hydropower project) ..... 2
LIST OF TABLE
Table 1ETO value at Arjo Dedessa........................................................................................ 7
Table 10Risk and Reliability for different return and design period. .................................... 24
Table 11Upstream and downstream slope based on USBR Design standard ........................ 30
ACRONYMS
AE Application efficiency
CWR crop water requirement
ETC evapotranspiration of crop
ETO evapotranspiration
DA drainage area
FAO food and agriculture organization
GIR gross irrigation requirement
NIR net irrigation requirement
AUHHC Page ix
Design of storage dam for Arjo Dedessa irrigation project
1 INTRODUCTION
1.1 General Background of the Project
Global warming is the main issue of the world specially, in Africa; those are live under sub-
Saharan desert. Ethiopia also faced a lot of drought and problems of food scarcity at different
time in the country, due to which results increase in temperature and decrease in rainfall both
in amount and distribution. This unreliable rainfall and desertification in turn reduce the
production return from the existing limited natural resource. This problem is becoming the
main constraint for development and increasing agricultural production. Ethiopia is “The
water tower of Africa”. This reflects how much Ethiopia is gifted with the natural recourses
specially water, more than any other countries of Africa. Arjo Dedessa dam and irrigation
project located in Oromiya regional state was financed by the Ethiopian they can plant
sugarcane and sale to Arjo Dedessa sugar factory.
Though our country has sample sources of water for irrigation besides its good arable lands,
only insignificant amount of it has been utilized, and the country was exposed to a severe
drought and famine for the past few decades. As a matter of fact, a decrease in soil fertility
and the dependency of farmers on rain fed agriculture, which is the production of crop with
erratic rainfall distribution leads to yield decrement.
Therefore, the implementation of Arjo Dedessa Irrigation Project is one of the irrigation
projects essential to overcome the adverse effect of erratic rainfall dependent agricultural
activities in Ethiopia. Irrigation is essential to overcome water deficiencies and ensure stable
agricultural production throughout the year. It is vital in areas where the amount and timing
of rainfall are not adequate to meet the moisture requirement of crops, maximize the value of
the land and farmers and increase their living standards, create job opportunity and generate
additional income for those are live around nearby sugar factory and other.
1.2 Statements of Problems
Arjo Dedessa Dam storage project has been proposed at the Dedessa River due to the cause
of high flood problem happened at the population the lived around the area. Throughout an
Ethiopia country the sugarcane shortage face, therefore due to those causes Arjo Dedessa
irrigation project has one factor. Other problems has the presence of unemployed of young
person around the project area and also the Dedessa rivers has not functional used for the
community even if the river has adverse effect on the population during the rainy season
period. Therefore this project has response for the flooding and sugarcane shortage though
out the country
AUHHC Page 1
Design of storage dam for Arjo Dedessa irrigation project
1.3 Objectives
1.3.1 General Objective
The main objective of the project is to find the firm flow and quantify irrigated land
of 80000ha command area to the proportionality of available water, finally, Design
Safe durable storage dam across the river and store water.
1.3.2 Specific Objectives
To analysis the hydrological data, and evaluate the maximum design flood, firm
discharge, reliability of the project.
To estimate the crop water requirement and select the best crop for Arjo Dedessa
irrigation project.
To estimate crop water requirements and determine total duty at the worst period.
1.4 Description of the project area
1.4.1 Location of River Basin
Dedessa River is a river, located in the eastern Wollega zone, Oromiya region; Ethiopia. It is
tributary of the Abay River. It rises in the mountains of Gomma, flowing in the northwestern
direction to its confluence where the course of the Abay has curved to its southern most point
before turning northwards at about 9.30°N and 36.06°E Coordinates.
Figure 1Location Map of Dedessa catchment (source from Dedessa hydropower project)
AUHHC Page 2
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 3
Design of storage dam for Arjo Dedessa irrigation project
less than 150 centimeters to more than 200 centimeters. The Dedessa catchment, besides
reflecting a marked rainfall increase with higher elevation, also receives heavier annual
quantities than most of the catchments in the Abay Basin. Examination of the rainfall records
from this area shows that this is due to a longer (May through October) rainy season rather
than heavier maximum monthly quantities.
1.5 Socio-Economic Condition
The proposed project location is in East Wollega zone Oromiya Regional state of Ethiopia
between district of Getema and Bedele. Around the dam site there are about twelve villages
from the two districts. Related to environmental factors and lower life standard the residents
of the project area health status are so scary. Diseases like malaria, intestinal parasite,
diarrhea, are the most causes of outpatient visits.
1.6 Scope of the project
The project is proposed to increase yield of sugarcane by irrigating sugarcane farm land, and
to watering 80000ha command area around Arjo Dedessa to increase demand of sugar. To
enhance the amount of irrigation water, we check firm discharge in the river and evaluate the
value of how much water is needed using Cropwatt8.0 software. After all hydrological
analysis is determined; storage dam is applied to reserve water at the excess flow to the worst
time of watering.
AUHHC Page 4
Design of storage dam for Arjo Dedessa irrigation project
2.1 General
Every crop requires a certain quantity of water after a certain fixed interval, throughout its
period of growth. If the natural rain is sufficient and timely. So as to satisfy both these
requirements, no irrigation water is required for raising that the crop. The natural rain is
falling regularly throughout the years, satisfies both these requirements for practically all the
crops, and therefore, irrigation is not significantly needed.
Water requirement of the crop is the total quantity of water required by the crop from the
time it is grown to the time it is harvested. Different crops required different quantity of
water. Since the growing crops use water continuously, it is essential to maintain the quantity
of readily available mixture in the soil by irrigation. As such the total quantity of water
required by a crop is so distributed that a plant of it is applied at each time at a more or less
fixed interval trough out the period of growth.
The quantity of water applied on each irrigation intervals should be in such a way that water
sufficient to meet needs of the crop is stored in the soil. Therefore, in addition to the total
quantity of water required by a crop, it is also essential to determine the frequency of
irrigation as well as the quantity of water required to be applied during each applications.
Every crop requires a certain quantity of water after a certain field interval throughout its
growth period. If the natural rain is sufficient and timely sows satisfy both those requirement,
no irrigation water is required for raising that the crop. But countries like Ethiopia the natural
rainfall is erratic if it does so meeting the timely requirement is a must. Crop water
requirement is defined as the total amount of water required at fixed head to mature a crop,
of course, it is includes the amount required to meet loss though evaporation losses through
transpiration, plant metabolism needs application and quantity of water required for
operational land preparation, leaching etc.
2.2 application of CROPWAT
The main purpose of CROPWAT is to calculate crop water requirements and irrigation
schedules based on data provided by the user. These data can be directly entered into
CROPWAT or imported from other applications. For the calculation of crop water
requirements (CWR), CROPWAT needs data on evapotranspiration (ETo). CROPWAT
allows the user to either enter measured ETo values, or to input data on temperature,
humidity, wind speed and sunshine, which allows CROPWAT to calculate ETo using the
Penman-Monteith formulae. CROPWAT fully supports the .PEN and .CLI files from the
AUHHC Page 5
Design of storage dam for Arjo Dedessa irrigation project
CLIMWAT database. Rainfall data are also needed, and are used by CROPWAT to compute
effective rainfall data as input for the CWR and scheduling calculations. Finally, crop data
(dry crop or rice) are needed for the CWR calculations and soil data if the user also wants to
calculate irrigation schedules (dry crop or rice). Whereas CROPWAT normally calculates
CWR and schedules for 1 crop, it can also calculate a scheme supply, which is basically the
combined crop water requirements of multiple crops, each with its individual planting date (a
so-called cropping pattern).
The data input modules of CROPWAT are:
1. Climate/ETo: for the input of measured ETO data or of climatic data that allow.
Calculation of ETO Penman-Monteith.
2. Rain: for the input of rainfall data and calculation of effective rainfall.
3. Crop (dry crop or rice): for the input of crop data and planting date.
4. Soil: for the input of soil data for (only needed for irrigation scheduling).
5. Crop pattern: for the input of a cropping pattern for scheme supply calculations
6. CWR - for calculation of Crop Water Requirements
7. Schedules (dry crop or rice) - for the calculation of irrigation schedules
8. Scheme - for the calculation of scheme supply based on a specific cropping pattern
2.3 determination of crop water requirement
Water is the critical input for obtaining maximum production of a particular crop which has
its own tolerance limits of soil moisture variation that do not affect its yield. The moisture
availability in the root zone of the crop could be maintained within the crop tolerance limits
by adopting water management practice.
2.4 Climate /ETO
Potential crop of evapotranspiration is the depth of water needed to meet the water growth
loss through evapotranspiration of a diseases free crop growing fields under a none-restriction
soil Condition including soil water and fertility to achieving full production potential under
the given grown environment (FAO 24, 1983).
2.5 Methods to determine evapotranspiration (ETO)
The FAO groups of scientists have screened 31empirical formula for predicting the ETO and
recommend four of them under different climatic conditions.
FAO Blaney-criddle method
FAO Radiation method
FAO Pan evaporation method
AUHHC Page 6
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 7
Design of storage dam for Arjo Dedessa irrigation project
observation. Rainfall is highly effective when little or no runoff takes place. Small rainfall
amounts are not very effective as these small quantities of water are quickly lost to
evaporation. As input of monthly rainfall, the average, dependable or actual rain-fall data can
be given. Care should be taken in select-ing ap-propria-te val-ues for the dependable rainfall,
based on separately carried out statistical analyses of long-term rainfall records.
Table 2Effective rainfall result
Month Rain Eff rain
mm Mm
January 15.3 14.9
February 18.4 17.9
March 15.6 15.2
April 69.5 61.8
May 181 128.6
June 243 148.5
July 246 149.2
August 238 147.4
September 228.6 145
October 115.5 94.2
November 31.4 29.8
December 12.7 12.4
SUM 1415 964.9
2.5.3 Coefficient Crop (Kc) at different stages
The crop coefficient is used to relate the potential evapotranspiration (ETO) to the
evapotranspiration of crop (ETc).
𝑬𝑻𝒄
𝑲𝒄 =
𝑬𝑻𝒐
The crop coefficient varies according to crop characteristics, due to planting date, stage of
growth and other climatic condition. There are four growth period of crop
Initial stage: early growth and germination when the soil surface is not covered by crop
(ground cover is less than 10%)
Development stage: from end of initial stage to attainment of effective full ground cover
(ground covers approximately 70 to 80%).
Mid –stage: from attainment of effective full ground cover to start of maturity.
Late stage: from end of mid –stage until maturity of harvest.
AUHHC Page 8
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 9
Design of storage dam for Arjo Dedessa irrigation project
Irrigation requirement of crop; it is defined as the part of water requirement of crops that
should be fulfilled by irrigation.
CWR = 425.5mm + 964.6mm + 1215mm + 290mm = 2895.1mm
Table 4Crop scheduling at different stage of sugarcane
Month Decade Stage Kc ETc ETc Eff rain Irr. Req.
coeff mm/dec mm/dec mm/dec mm/dec
Dec 2 Init 0.59 1.93 3.9 0.6 12.2
Dec 3 Init 0.4 1.34 14.7 3.8 10.9
Jan 1 Init 0.4 1.37 13.7 4.7 9
Jan 2 Devt 0.41 1.42 14.2 5 9.2
Jan 3 Devt 0.5 1.85 20.3 5.3 15
Feb 1 Devt 0.62 2.4 24 5.8 18.2
Feb 2 Devt 0.74 2.97 29.7 6.2 23.5
Feb 3 Devt 0.84 3.54 28.3 5.8 22.5
Mar 1 Devt 0.94 4.15 41.5 3.8 37.7
Mar 2 Mid 1.05 4.83 48.3 2.8 45.5
Mar 3 Mid 1.09 4.85 53.4 8.7 44.7
Apr 1 Mid 1.09 4.73 47.3 14.8 32.5
Apr 2 Mid 1.09 4.6 46 19.7 26.3
Apr 3 Mid 1.09 4.5 45 27.4 17.6
May 1 Mid 1.09 4.39 43.9 36.9 7
May 2 Mid 1.09 4.29 42.9 45.1 0
May 3 Mid 1.09 4.11 45.2 46.5 0
Jun 1 Mid 1.09 3.94 39.4 47.9 0
Jun 2 Mid 1.09 3.76 37.6 50.4 0
Jun 3 Mid 1.09 3.56 35.6 50.2 0
Jul 1 Mid 1.09 3.35 33.5 49.7 0
Jul 2 Mid 1.09 3.15 31.5 49.8 0
Jul 3 Mid 1.09 3.19 35.1 49.6 0
Aug 1 Mid 1.09 3.22 32.2 49.3 0
Aug 2 Mid 1.09 3.26 32.6 49.1 0
Aug 3 Mid 1.09 3.46 38.1 48.9 0
Sep 1 Mid 1.09 3.66 36.6 50.1 0
Sep 2 Late 1.08 3.82 38.2 50.6 0
Sep 3 Late 1.02 3.73 37.3 44.2 0
Oct 1 Late 0.97 3.61 36.1 37.4 0
Oct 2 Late 0.91 3.49 34.9 32 2.9
Oct 3 Late 0.86 3.23 35.5 24.6 10.9
Nov 1 Late 0.8 2.97 29.7 15.6 14.1
Nov 2 Late 0.75 2.73 27.3 7.7 19.5
Nov 3 Late 0.69 2.44 24.4 6.5 17.9
Dec 1 Late 0.64 2.17 21.7 5.5 16.2
Dec 2 Late 0.59 1.93 15.4 2.6 12.2
Sum 1215 964.6 425.5
AUHHC Page 10
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 11
Design of storage dam for Arjo Dedessa irrigation project
Date Day Stage Depl% Net Irr( mm) Gr. Irr (mm) Flow(l/s/ha)
AUHHC Page 12
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 13
Design of storage dam for Arjo Dedessa irrigation project
Normal ratio method, and other used based on their characters. Among those types of
method linear regression is used for Dedessa River near Arjo to fill the missing data.
3.3 Data Consistency checking
Flow record maybe Inconsistent for the following reasons:-
The records for different gauging stations cover different periods of time.
The location of stations has changed.
The observation procedure has changed.
The instrument exposure has changed.
These inconsistence record data must be adjusted before use. Therefore it is essential to
detected using
L Moment methods or techniques.
Double Mass curve
3.4 Data Outlier Test
Water resources council recommended that adjustment be made for outliers. Outliers are data
point that departs significantly from the remaining data. There are three cases to check the
outliers according to the water resource council of the (1981). These are:-
Case1 If skewness (Cs) < -0.4 check for lower outlier.
Case2 If skewness (Cs) > +0.4 check for higher outlier.
Case3 If skewness (Cs) -0.4<Cs<+0.4 check for both outlier.
From these cases, Coefficient of skewness (Cs) is 0.4415. So the station skew greater than
+0.4, it is essential to test only higher outlier and considered. The following frequency
equation can be used to detect high outliers:
3.4.1 Higher Outlier Test
The following frequency equation can be used to detect higher outliers
YH=Ym+Kn*Sy, where,
YH is the high outlier threshold in log units
Kn is constant value for sample size n which is 2.563(source from US water Resource council
1981) used in one sided test that detect outliers at the 10% level of normally distribution data.
Peak flood considered at the high outliers should be compared to historic flood is necessary
and have flood information nearby site.
YH=2.741184706+2.563* 0.1647426=3.163419975
AUHHC Page 14
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 15
Design of storage dam for Arjo Dedessa irrigation project
If the drainage area (DA) of the site is within 20% of the drainage area of the gauge (0.8 ≤
𝐷𝐴𝑠𝑖𝑡𝑒 𝐷𝐴𝑔𝑎𝑢𝑔𝑒 ≤ 1.2), use C=1. The estimated discharge at the site will probably be
within 10% of the actual discharge, which is normally sufficient.
If the DA site is within 50% of the DA gauge, consider whether the data of the two gauges
(upstream and downstream gauges, if any) can be combined. In addition, when a weighted
average between upstream and downstream gauges is possible, the following linear
interpolation equation may be applied for a site lying between upstream & downstream
gauging station.
Table 6Transposed inflow data to dam site
Year Average Max Min
1979 55.373 203.934 2.622
1980 101.063 318.474 2.464
1981 11.907 42.223 0.452
1982 79.313 234.136 4.928
1983 99.505 304.274 5.963
1984 50.782 173.744 2.421
1985 59.572 229.151 0.640
1986 45.521 186.922 2.604
1987 47.471 171.798 1.625
1988 79.158 288.947 1.962
1989 54.606 277.706 3.547
1990 68.725 301.616 8.220
1991 68.756 282.464 1.922
1992 64.521 203.787 3.399
1993 74.753 286.403 6.030
1994 67.664 301.790 3.828
1995 35.894 140.625 3.350
1996 70.804 211.192 2.871
1997 87.275 211.005 3.712
1998 100.836 293.320 16.118
1999 72.755 252.171 0.105
2000 68.082 169.961 5.909
2001 52.906 147.542 11.431
2002 52.906 147.542 11.431
2003 52.906 147.542 11.431
2004 62.445 164.104 7.323
2005 71.475 253.529 9.119
2006 93.344 358.072 10.220
2007 86.424 244.398 12.664
2008 71.203 203.077 7.008
AUHHC Page 16
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 17
Design of storage dam for Arjo Dedessa irrigation project
(n − r)(n − r − 1) ∗ Qr
b2 = = 𝟐𝟒𝟑. 𝟏𝟕𝟒
n ∗ (n − 1)(n − 2)
(n − r)(n − r − 1)(n − r − 2) ∗ Qr
b3 = = 𝟏𝟗𝟎. 𝟒𝟕𝟎
n ∗ (n − 1)(n − 2)(n − 3)
AUHHC Page 18
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 19
Design of storage dam for Arjo Dedessa irrigation project
100 0.160
95 4.302
50 37.00
30 127.0
Therefore, from the above computation the average yearly flow for a period of the 30yrs
AUHHC Page 20
Design of storage dam for Arjo Dedessa irrigation project
500
400
Discharge m^3/s
300
200 FDC
100
0
0.000 50.000 100.000 150.000
%Exedence
AUHHC Page 21
Design of storage dam for Arjo Dedessa irrigation project
Selecting the higher return period means the corresponding flood magnitudes is also very
high such a very high flood may never occur during the life time of the structures on the other
hand, if the low discharge corresponding to lower return period is chosen for the design and
exceeded it will result in the failure of the structure causing more damage than would have
been caused in the absence of the structure.
Table 9General Guidelines to select return period
Types of structure Return period
Spillways for project with storage more than 1000
60Mm3
Barrage and minor dams with storage less than 100
60Mm3
Spillway for small reservoir dam 10-20
Diversion weir 50-100
Source: Subramanian (1989) and Nevec (1972)
In our case we expect the total storage greater than 60M m3, therefore we have taken the
return period as 1000yrs.
3.10.1 Plotting Position
Probability analysis seeks to define the flood flows with a probability P of being equaled or
exceed in any years. The return period T is often used in views of probability to describe
design flood. Return period is reciprocal of probability i.e. P = 1/T. The data are arranged in
decreasing order of magnitude and the probability P of the each event being equaled or
exceeded is calculated by using a plotting position formula
Probability (P) of each event being equal or exceeded at a plotting position formula.
AUHHC Page 22
Design of storage dam for Arjo Dedessa irrigation project
1200.000
1000.000
Discharge in cms(y)
800.000
200.000
0.000
0.000 5.000 10.000 15.000 20.000 25.000 30.000 35.000
Value of (P & T)
AUHHC Page 23
Design of storage dam for Arjo Dedessa irrigation project
Table 10Risk and Reliability for different return and design period.
N/T 25 50 100 1000
100 0.22 0.39 0.63 1.00
200 0.12 0.22 0.39 0.99
300 0.08 0.15 0.28 0.96
400 0.06 0.12 0.22 0.92
500 0.05 0.10 0.18 0.86
600 0.04 0.08 0.15 0.81
800 0.03 0.06 0.12 0.71
900 0.03 0.05 0.11 0.67
1000 0.02 0.05 0.10 0.63
1000 0.98 0.95 0.90 0.37
900 0.97 0.95 0.89 0.33
800 0.97 0.94 0.88 0.29
600 0.96 0.92 0.85 0.19
500 0.95 0.90 0.82 0.14
400 0.94 0.88 0.78 0.08
300 0.92 0.85 0.72 0.04
200 0.88 0.78 0.61 0.01
100 0.78 0.61 0.37 0.00
Risk 10%
Reliability 90%
From the table above there is high probability of flood risk if design period is lowered and
return period is high. Therefore it is essential to provide necessary design period of the
project. Based on our reliability and risk analysis, we provide less risk probability of flood
and higher reliability based on the function of the dam service and overcome the flood risk
when it happened.
AUHHC Page 24
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 25
Design of storage dam for Arjo Dedessa irrigation project
Foundation of the catchments area: The foundation rock of the dam should be a sound
water tight rock and percolation below the dam should be minimum.
Geology of the reservoir basin: It should also be reasonably water tight so that the stored
water is not able to escape under the surrounding hills through cavernous rock.
4.2.1.2 Topographic Factor:
The river valley at the site should be narrow so that the length of the dam to be constructed is
less, but it should open out on the upstream side to provide a large basin for the reservoir.
4.2.1.3 Other factors:
Includes the reservoir basin should submerge minimum land and property.
Not have excessive costs associated to works such as roads, housing colonies for
workers and staffs etc.
Not be in cultural archeological mining etc. areas.
Be formed so that evaporation loss is minimum.
4.2.1.4 Physical characteristics of reservoir
The primary function of reservoirs is to provide storage; their most important physical
characteristics are storage capacity. The capacity of reservoir of a regular shape can be
compared with the formulas for the volumes of solids, but the capacity of reservoirs on
natural sites must usually be determined from topographic surveys.
The sediment data is obviously required to plan the size of the storages, for apportioning the
active and inactive storage spaces and for determining the revised geometry of the storage
after certain design life.
The quantity of sediment delivered to a reservoir depends on the rate of gross or absolute
erosion in the watershed and the ability of the stream system to transport eroded material to
the reservoir. Different approach could be used to estimate sediment rate at the projects sites.
However for this study the estimation of sediment rate at the project sites have been
calculated by employing rating curve of the sediment sample data of the stations as described
below:
As the silt originates from the water shed, the characteristics of the catchment such its areal
extent, soil types, land slopes, vegetal cover and climatic conditions like temperature, nature
and intensity of rainfall, have a great significance in the sediment production in the form of
sheet erosion, gully erosion and stream, channel erosion. In regions of moderate rainfall,
sheet erosion is the dominant source of total sediment load while in arid and semi-arid
regions, gullying and stream-channel erosion furnish the greater part of the load.
AUHHC Page 26
Design of storage dam for Arjo Dedessa irrigation project
The suspended sediment load of streams is measured by sampling the water, filtering to
remove the sediment, drying and weighing the filtered material.
V= (A1+A2), Where,
AUHHC Page 27
Design of storage dam for Arjo Dedessa irrigation project
Com Area(m^2)
0.00 500.00 1000.00 1500.00 2000.00 2500.00 3000.00 3500.00
1370
1360
1350
Elevation(m)
1340
1330
Cum Volume-Elevation
1320
Cum Area-Elevation
1310
1300
3500.00 3000.00 2500.00 2000.00 1500.00 1000.00 500.00 0.00
Com Vol(Mm^3)
Figure 6Area Elevation Curve
4.2.3 Sediment load and demand level elevation
From the figure (8) sediment rating curve sediment load is computed by using annual inflow
to Arjo Didessa from table (7) is 66.932𝑚 /𝑠 by interpolation to determine sediment level
on its service life of 100years is 34.7845Mm3 this is used to fix installation level of intake to
prevent clogging by debris or sediment.
40m /s = 100ton/day
66.932(inflow) = x
100m /s = 2000ton/day
𝑥(sediment load = 953ton/day, and kilogram volume relation sediment load in 100yaers of
life it reach elevation 1318.7m. Considering intake position to install recommended at
1920m. And also determine the level of demand levels as sediment computed based on duty,
4.2.4 Reservoir Sedimentation Control
Sediment deposition in reservoirs cannot be actually prevented but it can be retarded by
adopting some of the following measures:
Reservoir sites, which are prolific sources of sediment, should be avoided.
By adopting soil-conservation measures in the catchment area, as the silt originates in
the watershed.
AUHHC Page 28
Design of storage dam for Arjo Dedessa irrigation project
Agronomic soil conservation practices like cover cropping, strip cropping, contour
farming, suitable crop rotations, application of green manure (mulching),
Proper control over graze lands, terracing and benching on steep hill slopes.
Retard overland flow, increase infiltration and reduce erosion.
Contour trenching and afforestation on hill slopes,
Vegetal cover on the land reduces the impact force of rain drops and minimizes
erosion.
Sluice gates provided in the dam at various levels and reservoir operation, permit the
discharge of fine sediments without giving them time to settle to the bottom.
Sediment deposits in tanks and small reservoirs may be removed by excavation,
dredging, draining and flushing either by mechanical or hydraulic methods and
sometimes may have some sales value.
4.3 Arjo Dam Layout
Maximum demand of water at the time of excess flow is reserved by proper provision of dam
height and all protection work to prevent seepage loss, overtopping and other. Therefore
height is determined based on table shown above and capacity-Area-elevation curve.
H = (Demand level − river bed level) + freeboard
Where demand level is 1331.5mams, river bed level is 1312mams and sediment load level is
1320mams and normal freeboard is 1.5m
𝐻 = (1331.5m − 1312m) + 1.5m = 21m
4.3.1 Top width of the Dam
After determining and fix the dam height based on annual demand and capacity curve
respectively. Top width is determined based on dam height. If the dam height is between 10
and 30m top width is determine as below. (According to USBR Design of Small Dams
standard (1997))
10m < H < 30m
/
Top width of the dam isB = 0.55H + 0.2H , therefore
AUHHC Page 29
Design of storage dam for Arjo Dedessa irrigation project
AUHHC Page 30
Design of storage dam for Arjo Dedessa irrigation project
CONCLUSION
Global warming is the main issue of the world specially, in Africa. This problem is becoming
the main constraint for development and increasing agricultural production. Therefore, the
implementation of Arjo Dedessa Irrigation Project is one of the irrigation projects essential to
overcome the adverse effect of erratic rainfall dependent agricultural activities in Ethiopia.
Irrigation is essential to overcome water deficiencies and ensure stable agricultural
production throughout the year. Arjo Dedessa dam and irrigation project located in Oromiya
regional state was financed by the Ethiopian they can plant sugarcane and sale to Arjo
Dedessa sugar factory. Arjo Didessa dam is embankment storage dam. It store water during
period of surplus water supply, especially rainy season in summer. To use at the deficient
time to give sufficient water demand at the command area. It is vital in areas where the
amount and timing of rainfall are not adequate to meet the moisture requirement of crops,
maximize the value of the land and farmers and increase their living standards, create job
opportunity and generate additional income for those are live around nearby sugar factory
and other.
AUHHC Page 31
Design of storage dam for Arjo Dedessa irrigation project
REFERENCES
1. Allen, R. G., Walter, I. A., Elliot, R. L., Howell, T.A., Itenfisu,D., Jensen, M. E. and
Snyder, R. 2005. The ASCE standardized reference evapotranspiration equation.
ASCE and American Society of Civil Engineers.
2. Allen, R.G., L.S.Pereira, D. Raes, and M. Smith. 1998. Crop evapotranspiration:
guidelines for computing crop water requirements Food and Agriculture
Organization of the United Nations, Rome.
3. ASCE-EWRI (2005) The ASCE standardized reference evapotranspiration equation.
In: Allen RG, Walter IA, Elliott RL, Howell TA, Itenfisu D, Jensen ME, Snyder RL
(eds) American Society of Civil Engineers, 69 p.
4. Blaney, H. F. and Criddle, W. D. 1950. Determining water requirements in irrigated
areas from climatological and irrigation data. United States Department of
Agriculture,Soil Conservation Service
5. Garg, S.K (2003), Irrigation Engineering and Hydraulic Structures, Khanan
publishers, New Delhi.
AUHHC Page 32