You are on page 1of 30

JAAMACADA EELO JAAMACADA EELO

EELO UNIVERSITY EELO UNIVERSITY

TITLE:

CONSTRUCTION OF A CONCRETE ELEVATED WATER TANK IN GOBSHO, MUDUG,


PUNTLAND, SOMALIA

SUBTITLE:

Addressing Water Storage Needs for Sustainable Agriculture and Domestic Usage

Submitted by:
Group 3: ID: NUMBER

BISHAAR IIMAN CUMAR [3736]


ABDIKARIM ABDULLAHI MOALIM [3748]
ASAD MOHAMED HUSSEIN [3585]
YUUSUF ABDULLAHI MOALIM [3747]
SAED ABDULLAHI MOHAMED [3822]

PROJECT: ELEVATED WATER TANK ESTIMATIONS 1


DECLARATION

We hereby declare that this report isour original work and all the writings here in are our personal efforts and in
other person’s material has been dully acknowledged

PROJECT: ELEVATED WATER TANK ESTIMATIONS 2


APPROVAL

This is to certify that this piece of work was done under my supervision and that it is the original work of the
above authors.
Eng. Adifatah Mohamud Obsiiye ……………………

PROJECT: ELEVATED WATER TANK ESTIMATIONS 3


DEDICATION
We dedicate this book to Our dear parents, sisters and brothers.

PROJECT: ELEVATED WATER TANK ESTIMATIONS 4


ACKNOWLEDGEMENT

All praises to Allah the most gracious the most merciful for his showers of blessings throughout our research
successfully.
In this part I would like to thank to Eng. Abdifatah Mohamud Obsiiye who guided us from beginning to the
end. If it was not for his guidance this report wouldn’t have been completed.
Furthermore, we would like to acknowledge with much appreciation the engineers and lecturers who assisted
Us and gave me their opinions about this project.
Last but not least We thankful to Our family who supported us in every way possible.

PROJECT: ELEVATED WATER TANK ESTIMATIONS 5


CONTENTS
DECLARATION................................................................................................................................................. 2
APPROVAL......................................................................................................................................................... 3
DEDICATION..................................................................................................................................................... 4
ACKNOWLEDGEMENT.................................................................................................................................. 5
CHAPTER ONE.................................................................................................................................................. 8
Introduction:...................................................................................................................................................... 8
BACKGROUND & RATIONALE....................................................................................................................9
Introduction:.................................................................................................................................................. 9
Project Rationale:........................................................................................................................................ 9
Conclusion:.................................................................................................................................................... 9
Project Objectives & Scope of Work...............................................................................................................10
Project Objectives:...................................................................................................................................... 10
Scope of Work:............................................................................................................................................ 10
Conclusion:.................................................................................................................................................. 10
Methodology.................................................................................................................................................. 11
Introduction:.............................................................................................................................................. 11
Key Methodological Aspects:....................................................................................................................11
Conclusion:.................................................................................................................................................. 11
Significance of Project & Conclusion............................................................................................................. 12
Significance of Project:............................................................................................................................... 12
Conclusion:.................................................................................................................................................. 12
CHAPTER TWO:................................................................................................................................................13
Water tank Design in Gobsho Region..............................................................................................................13
Designing Process of the tank for AutoCAD 2D with the elevations..............................................................15
Designing Process of the tank for ArchiCAD 3D with the elevations.............................................................16
CHAPTER THREE:......................................................................................................................................... 18
ESTIMATIONS:.............................................................................................................................................. 18
SITE CLEARANCE..................................................................................................................................18
LEAN CONCRETE.................................................................................................................................. 19
R.C.C FOOTING...................................................................................................................................... 20
R.C.C COLUMN....................................................................................................................................... 22
R.C.C BEAM............................................................................................................................................. 24
R.C.C SLAB............................................................................................................................................... 26

PROJECT: ELEVATED WATER TANK ESTIMATIONS 6


PLASTERING........................................................................................................................................... 28
BOQ PREPARATION...................................................................................................................................... 30

CHAPTER ONE:
Introduction:

Water scarcity in Gobsho city is a pressing concern, and addressing this challenge requires innovative solutions.
This proposal outlines a comprehensive project for the construction of a concrete elevated water tank, tailored
for sustainable agricultural practices and domestic water use. Led by Group 3, this group project aims to
implement a robust water storage system, ensuring a consistent and reliable water supply.

Key Components:

PROJECT: ELEVATED WATER TANK ESTIMATIONS 7


Aspect Details
Background & In-depth analysis of water scarcity issues, providing a rationale
Rationale for the project.
Project Clearly defined goals, including sustainable agriculture and
Objectives domestic water use.
Scope of Work Overview of the tasks and responsibilities within the project
scope.
Methodology Proposed methods for project execution, ensuring efficiency and
quality.
Significance of Discussion on the potential impact and benefits of the proposed
Project water tank.

Conclusion:
This executive summary provides a glimpse into the multifaceted aspects of the proposed project. The
subsequent sections will delve into each component, offering a thorough understanding of the project's depth
and significance.

PROJECT: ELEVATED WATER TANK ESTIMATIONS 8


BACKGROUND & RATIONALE

Introduction:

Water scarcity is a global challenge with direct implications for agriculture and daily life. We recognize the
need for a sustainable solution to address water storage deficits. The proposed concrete elevated water tank
project aims to serve as a pivotal step toward mitigating the impacts of water scarcity on agricultural activities
and domestic water needs.

Project Rationale:

The need for a concrete elevated water tank stems from the limitations of conventional water storage methods.
Concrete offers durability, stability, and longevity, ensuring the water tank's ability to withstand varying
environmental conditions. Additionally, the project aligns with broader sustainability goals by promoting
efficient water use and conservation.

Tables:
Water Scarcity Statistics Details
Global Water Scarcity Status [Statistics and trends related to global water scarcity.]
Regional Water Challenges [Specific challenges faced in the project region regarding
water scarcity.]

Conclusion:
Understanding the background and rationale behind the project sets the stage for a purposeful and impactful
initiative. The ensuing sections will delve into the practical aspects of the proposed concrete elevated water
tank.

PROJECT: ELEVATED WATER TANK ESTIMATIONS 9


Project Objectives & Scope of Work

Project Objectives:

The primary objectives of the concrete elevated water tank project are as follows:

1. Sustainable Agriculture: Enhance water availability for agricultural activities, promoting sustainable
farming practices.
2. Domestic Water Supply: Provide a reliable and continuous water supply for domestic usage.
3. Environmental Responsibility: Integrate eco-friendly features, such as rainwater harvesting, to align with
sustainability goals.

Scope of Work:

The scope of this project encompasses the following key tasks:

Task Responsibility
Site Assessment and Selection Project site assessment team
Design and Engineering Consultation Engineering design team
Regulatory Approvals Project regulatory compliance team
Excavation and Site Preparation Site preparation crew
Concrete WaterTankConstruction Construction team
Sealing and Interior Finishing Finishing team
Integration with Water Supply System Irrigation team

Conclusion:
Clearly defining the project objectives and the scope of work ensures a focused and systematic approach to
achieving the desired outcomes. The subsequent sections will delve into the methodology and the significance
of the proposed concrete elevated water tank.

PROJECT: ELEVATED WATER TANK ESTIMATIONS 10


Methodology

Introduction:

The methodology for the concrete elevated water tank in Gobsho project is rooted in a systematic and
collaborative approach. Leveraging the expertise of each team member, Group 3 aims to achieve the project
objectives with efficiency and precision.

Key Methodological Aspects:

1. Design Process: Collaborative efforts in designing a customized water

tank that meets the specific needs of sustainable agriculture and domestic water usage.

2. Engineering Excellence: Engaging in consultations with experts to ensure that the construction adheres to
the highest engineering standards, ensuring durability and stability.

3. Regulatory Compliance: Rigorous adherence to local regulations and obtaining necessary approvals for
seamless project execution.

4. Efficient Construction Practices: Utilizing modern construction techniques for excavation, concrete tank
construction, and finishing to ensure both speed and quality.

5. System Integration: Implementing cutting-edge technology for the seamless integration of the water tank
with the existing water supply system.

Conclusion:
A well-defined methodology is pivotal for the successful execution of the proposed concrete elevated water tank
project. The subsequent section will underscore the significance of the project, outlining the potential impact on
both the local community and the environment.

PROJECT: ELEVATED WATER TANK ESTIMATIONS 11


Significance of Project & Conclusion

Significance of Project:

The concrete water tank project holds substantial significance for various stakeholders, including the local
community, the environment, and future generations.

1. Community Impact: Reliable water supply for agriculture and domestic use improves living conditions and
enhances community resilience.

2. Environmental Contribution: Incorporating eco-friendly features, such as rainwater harvesting, reduces


reliance on external water sources, contributing to environmental sustainability.

3. Economic Boost: Increased agricultural productivity can positively impact the local economy, fostering
growth and development.

Conclusion:
In conclusion, the proposed concrete elevated water tank project is not merely a construction endeavor but a
concerted effort by Group 3 to address pressing issues related to water scarcity. We look forward to the approval
and support for this project, confident in its potential to be a beacon of sustainable water management practices.

PROJECT: ELEVATED WATER TANK ESTIMATIONS 12


CHAPTER TWO:

Water tank Design in Gobsho Region

Gobsho is small town located in Somalia, Mudug region Gobsho is 20 km away from east Galkayo
This small town consists of 150 houses and each house it’s a family of 7 member (5 children and 2 parents) and
the population will be

P = 150 x 7 = 1050 people


We plan this project for the 20 coming years. The population of the next 20 years, 2043 will be.
P2043 = Pe x (1 + IG¿n
Note the growth of Somalian is 3% per year.
P2043 = 1050 x (1 + 0.03¿20 = 1897
The population of the village will become 1897 people.
Now we find the Domestic water they use or need per day.
Domestic water L/ D / P
Dinking 4L
Cooking 10L
Pathing/clothing 15 L
School 30 L
Praying 5L
MCH 20 L
Total 84L/D/P + accessory
Total = 84 L/D/P
The charge is equal to population times percent.
Q = population x per capital
Q = 1897 x 84 = 159348 L/D
The people of this village are shepherd.
The average number of animals each family has 50 goats and the design in our tank to give a water 200 goats
per day and we know the average water needed in one goat per day is 5L.
5 x 200 = 10,000 L
The water will be.
159348 + 10000 = 169348 L/D

PROJECT: ELEVATED WATER TANK ESTIMATIONS 13


And we change this L/D into L/S
169348
=¿ 1.96 L/s
24 x 60 x 60
The charge maximum will be Q max = Q x daily max = 1.8 x 1.96 = 3.53 L/s
The next step is to find the storage and we will only store 30% of the total water
Storage = 20% x 169348 x 1.8 = 61 m3
And our tank will be rectangular.
V=Axh
And we assume the height of our tank is 2.5 m
61 m3 = A x 2.5 m
3
61 m
A= = 24.4 m2
2.5 m
A=LxW
2
24.4 m = 6.1 m and the length and width is 4 m
The pressure of the water will be
P = 61 x 9.81 = 598.4 KN

Designing Process of the tank for AutoCAD 2D with the elevations

PROJECT: ELEVATED WATER TANK ESTIMATIONS 14


PROJECT: ELEVATED WATER TANK ESTIMATIONS 15
Designing Process of the tank for ArchiCAD 3D with the elevations

PROJECT: ELEVATED WATER TANK ESTIMATIONS 16


PROJECT: ELEVATED WATER TANK ESTIMATIONS 17
CHAPTER THREE:

ESTIMATIONS:

SITE CLEARANCE EXCAVATION OF FOOTING


Area of clearance: 6.1 x 4 = 24.4m2 Area of Excavation footing: 1.5 x 1.5 =2.25m2
1 unskilled labour = 20 m2 Volume of Excavation footing: 2.25 x 1 =
24.4 2.25m3
= 1.22 = 2 unskilled labour
20
Number of excavations: 6 x 2.25m3 = 13.5m3
2 x $8 = $16
1 unskilled can excavate = 0.5 m3 – 1.5 m3
1
One Forman = so we take one Forman So, we take 1.5 m3.
20
13.5
One Forman =$25 Number of unskilled = = 9 unskilled
1.5
Total cost of site clearance
labors
$16 + $25 = $41
Cost of labor = 9 x $8 = $72
Rate of site clearance
One Forman = $25
41
= $1.7 m2. Total cost of Excavation footing
24.4
$72 + $25 = $97
Rate of excavation footing
97
= $7.2 m3
13.5

PROJECT: ELEVATED WATER TANK ESTIMATIONS 18


LEAN CONCRETE
2
Area = 1.5mX 1.5m = 2.25m 2. Cost of labours
Volume of the lean concrete 2.25m2 x 0.2m = 3. Meson
3
0.45m3 2.7 m
1 = 5m3 , 3
=0.54=1meson
0.45 M3 X 6 = 2.7 m3 5m

Ratio of concrete we take m20, 1:1.5:3 = 5.5 Cost of meson: 1 x $16 = $16

1. Cost of materials 4. Mixers

1. Cement 1 = 3m3=¿ 2.7m3 /¿3m3= 0.9 mixers

1 0.49 Cost of mixers: 1 x $10 = $10


x 2.7=0.49= = 14.03= 14 bags
5.5 0.035 5. Unskilled
Cost of cement: 14 x $ 9 = $126 1= 0.9m3 = 2.7m3 /0.9 m3 = 3
2. Sand Cost of unskilled: 3 x $8 = $24
1, 5 0.74 Total cost of labors
x 2.7 = 0.74= =0.368=1 loads
5.5 2
• Meson = $16
Cost of sand: 1 x $25 = $25
• Mixers = $10
3. Gravel
• Unskilled = $24
3 1.47
x 2.7 = 1.47 =0.74=1 loads Total cost of labor = $50
5.5 2
Cost of gravel: 1 x $45 = $45
4. Water Total cost of a slab

14 x 100 • Total cost of material =$206.5


= 7 barriers
200 • Total cost of labor = $50
Cost of water: 7 x $1.5 = $10.5 Total cost of the lean concrete = $206.5 +
Total cost of materials $50 = $256.5
• Cement = $126
• Sand = $25 contingency 5% = $12.825+ $256.5 =
• Gravel = $45 $269.325
• Water = $10.5 269.4
= 99.75 = $100/m3
Total cost of materials =206.5 2.7
Rate of Column = $100m3

PROJECT: ELEVATED WATER TANK ESTIMATIONS 19


R.C.C FOOTING
2
Area (1.5 x 1.5) = 2.25m Vertical length of bars: 9 + 9 + 9 + 9 = 36 x 0.5
Volume of the Footing 2.25m2 x 0.5m = 1.125m3 = 18 m
1.125 M3 X 6 = 6.75 m3 Total length of bars:
Ratio of concrete we take m20, 1:1.5:3 = 5.5 488 m + 18 =506m
1. Cost of materials 506m/ 12 m = 42.16 = 43 main bars
2 2
1. Cement d 12
x L=¿ x 12=10.66 x 43 = 428.41 kg
1 1.23 162 162
x 6.75=1.23= = 35.06= 35 bags
5.5 0.035 Cost of bars: 43 x $14 = $602
Cost of cement: 35 x $ 9 = $315
2. Sand Total cost of materials
1, 5 1.84 • Cement = $315
x 6.75 = 1.84 = =0.92=1loads
5.5 2 • Sand = $25
Cost of sand: 1 x $25 = $25 • Gravel = $90
3. Gravel • Water = $27
3 3.68
x 6.75 = 3.68 =1.84=2loads • Steel bars = $602
5.5 2
Total cost of material = $1059
Cost of gravel: 2 x $45 = $90
4. Water
35 x 100
= 17.5 = 18 barrier
200
Cost of water: 18 x $1.5 = $27
5. Main bars
Distance b/w bars = 20 cm
∅ main= 12 mm, L =12m
1.5
=9 x 1.5m = 11.25m of bars
0.2
1.5
= 9 x 1.5m = 11.25m of bars
0.2
Horizontal length of bars: 122 + 122 = 244 m x2 =
488m

PROJECT: ELEVATED WATER TANK ESTIMATIONS 20


2. Cost of labours Total cost of labours
1. Steel fixers • Steel fixers = $100
1 = 100kg, 428.41 kg/100 kg = 4.28 = 5 steel fixers • Meson = $32
Cost of steel fixers: 5 x $16 = $80 • Mixers = $20
Steel fixer helper = 2 x $10 = $20. T = $100 • Unskilled = $64
2. Meson Total cost of labour = $158
3
6.75 m
1 = 5m3 , 3
=1.35=2 meson
5m Total cost of footing
Cost of meson: 2 x $16 = $32 • Total cost of material =$1059
3. Mixers • Total cost of labour = $158
3 3 3
1 = 3m =¿ 6.75m /¿3m = 2 .25 mixers Total cost of the footing = $158 + $1059 =
Cost of mixers: 2 x $10 = $20 $1218
5. Unskilled
1= 0.9m3 =6.75m3 /0.9 m3 = 7.5 contingency 10% = $121.8 + $1218 = $1339.8
Cost of unskilled: 8 x $8 = $64 1339.8 .
= 198.5 = $200/m3
6.75

Rate of Footing = $200m3

PROJECT: ELEVATED WATER TANK ESTIMATIONS 21


R.C.C COLUMN
2
Area = 0.4mX 0.4m = 0.16m 9. Main bars
Volume of the Column 0.16m2 x 6.5m = 1.04m3 ∅ main= 12 mm, L =12m
1.04 M3 X 6 = 6.24 m3 Total length of bars: 10 x 6.5m = 65m of steel
Ratio of concrete we take m20, 1:1.5:3 = 5.5 65
= = 5.42 = 6 x 6 column = 36 main bars
12
1. Cost of materials
2 2
2. Cement d 12
x L=¿ x 12=10.66 x 36 = 383.76 kg
162 162
1 1.135
x 6.24=1.135= = 32.4= 33 bags Cost of bars: 36 x $14 = $504
5.5 0.035
Cost of cement: 33 x $ 9 = $297 10. Strippers

3. Sand ∅ main= 6 mm, L =12m


1, 5 1.7018 6.5
x 6.24 = 1.7018= =0.85=1 loads = 22 x 6 =132 of steel bar = 132 x 1.6m =
5.5 2 0.3
Cost of sand: 1 x $25 = $25 211.2 m
2 2
4. Gravel d 6
x L=¿ x 12=2.66 x 17 = 45.33 kg
162 162
3 3.403
x 6.24 = 3.403 =1.7018=2 loads
5.5 2 211.2 m of strippers. 211.2/ 12 = 17 stripper
Cost of gravel: 2 x $45 = $90 17 x $9 = $158.4
5. Water
33 x 100 Total cost of materials
= 16.5 = 17 barrier
200 • Cement = $297
Cost of water: 17 x $1.5 = $25.5 • Sand = $25
6. Frame wood • Gravel = $90
2
Area = (0.4m + 0.4m) x2 = 1.6m x 6.5 =10.4 m • Water = $25.5
2
Area of flat wood (comesato) 1.5x2 = 3m = $22 • Nails = $20
2 2
Cost of frame wood: 10.4m /3m = 3.466 = 4 x • Steel Main bars = $504
$22 = $88 • Stripper bars =$158.4
7. Supporting wood of the column(isteli) • Frame Wood = $88
48pics /16 = 3 x $20 = $60 • Support steel for slab = $60
8. Nail & wires Total cost of material = $1267.9
20kg x $1 = $20

PROJECT: ELEVATED WATER TANK ESTIMATIONS 22


2. Cost of labours Total cost of labours
1. Steel fixers • Steel fixers = $90
1 = 100kg, 429.04 kg/100 kg = 4.3 = 5 steel • Carpenters = $42
fixers • Meson = $32
Cost of steel fixers: 5 x $16 = $80 • Mixers = $20
Steel fixer helper =2 x $10 = $20. T = $90 • Unskilled = $56
2. Carpenters Total cost of labor = $240
1 = 10m2, 10.4m2/ 10m2 =1.04 = 2 carpenter
Cost of carpenters: 2 x $ 16 = $32 Total cost of a slab
Carpenter’s helper = 1 x $10 = $10. T = $42 • Total cost of material =$1267.9
4. Meson • Total cost of labour = $240
6.24 m
3
• Total cost of the slab = $1267.9 + $240 =
1 = 5m , 3
3
=1.248=2 meson
5m $1507.9
Cost of meson: 2 x $16 = $32
5. Mixers contingency 10% = $150.7 + $1507.9 = $1658.6
3 3 3
1 = 3m =¿ 6.24m /¿3m = 2.08 mixers 1658.6
= 265.8 = $266/m3
Cost of mixers: 2 x $10 = $20 6.24

6. Unskilled Rate of Column = $266m3

1= 0.9m3 =6.24m3 /0.9 m3 = 7


Cost of unskilled: 7 x $8 = $56

PROJECT: ELEVATED WATER TANK ESTIMATIONS 23


R.C.C BEAM
2
Area = 19.6mX 0.4m = 7.84m 8. Main bars
Volume of the Beam 7.84m2 x 0.3m = 2.352m3 ∅ main= 12 mm, L =12m
Ratio of concrete we take m20, 1:1.5:3 = 5.5 Total length of bars: 6 x 19.6m = 117.6m of steel
1. Cost of materials 117.6
= = 9.8 = 10 main bars
12
1. Cement
2 2
1 0.43 d 12
x 2.352=0.43= = 12.2 = 13 bags x L=¿ x 12=10.66 x 10 = 106.6 kg
5.5 0.035 162 162

Cost of cement: 13 x $ 9 = $11 Cost of bars: 10 x $14 = $140

2. Sand 9. Strippers

1, 5 0.64 ∅ main= 6 mm, L =12m


x 2.352 = 0.64 = =0.32=1loads
5.5 2 19..6
= 65.3 steel bar = 65 x 1.5m = 97.5 m
Cost of sand: 1 x $25 = $25 0.3
3. Gravel 98 m of strippers. 98/ 12 = 8 stripper
3 1.3 8 x $9 = $72
x 2.352 = 1.3 =0.64=1loads
5.5 2 d
2
6
2
x L=¿ x 12=2.66 x 8 = 21.28 kg
Cost of gravel: 1 x $45 = $45 162 162
4. Water
13 x 100 Total cost of materials
= 6.5 = 7 barrier
200 • Cement = $117
Cost of water: 7 x $1.5 = $10.5 • Sand = $25
5. Frame wood • Gravel = $45
Area = 19.6 x (0.4) base fr +( 0.3 + 0.3) x19.6 • Water = $10.5
2
both side fr = 19.6 m of flat wood • Nails = $20
2
Area of flat wood (comesato) 1.5x2 = 3m = $22 • Steel Main bars = $140
Cost of frame wood: 19.6m2/3m2 = 6.53 = 7 x • Stripper bars =$72
$22 = $154 • Frame Wood = $154
6. Supporting steels of the slab • Support steel for slab (rent) = $39
39 pics x $1 = $39 Total cost of material = $623
7. Nail & wires
20kg x $1 = $20

PROJECT: ELEVATED WATER TANK ESTIMATIONS 24


2. Cost of labours Total cost of labours
1. Steel fixers • Steel fixers = $42
1 = 100kg, 127.28 kg/100 kg =1.27 = 2 steel • Carpenters = $42
fixers • Meson = $16
Cost of steel fixers: 2 x $16 = $32 • Mixers = $10
Steel fixer helper = 1 x $10 = $10. T = $42 • Unskilled = $24
2. Carpenters Total cost of labour = $134
1 = 10m2, 19.6m2/ 10m2 =1.96 = 2 carpenter
Cost of carpenters: 2 x $ 16 = $32 Total cost of a slab
Carpenter’s helper = 1 x $10 = $10. T = $42 • Total cost of material =$623
3. Meson • Total cost of labour = $134
2.352m
3
• Total cost of the slab = $623 + $134 =
1 = 5m , 3
3
=0.47=1 meson
5m $757
Cost of meson: 1 x $16 = $16
4. Mixers contingency 10% = $75.7 + $757 = $832.7
3 3 3
1 = 3m =¿ 2.352m /¿3m = 0.78 mixers 832.7
= 354 = $354/m3
Cost of mixers: 1 x $10 = $10 2.352

5. Unskilled
Rate of Beam = $354m3
1= 0.9m3 =2.352m3 /0.9 m3 = 2.61
Cost of unskilled: 3 x $8 = $24

PROJECT: ELEVATED WATER TANK ESTIMATIONS 25


R.C.C SLAB
2
Area (6.1 x 4) = 24.4m 8. Nail & wires
Ly 6.1 20 kg x $1 = $20
= = 1.5 < 2 there is two-way slab
Lx 4 9. Main bars
L 610 cm Distance b/w bars = 20 cm
Thickness of the slab = = 25 cm
24 24
∅ main= 12 mm, L =12m
Volume of the slab 24.4m2 x 0.25m = 6.1m3
4
Ratio of concrete we take m20, 1:1.5:3 = 5.5 =21 x 6.1m = 128.1m of bars
0.2
1. Cost of materials 6.1
= 31.5 x 4m = 126m of bars
6. Cement 0.2
1 1.1 Total length of bars: 128 + 126 = 254m / 12 m =
x 6.1=1.1= = 31.7 = 32 bags
5.5 0.035 21 = 21 main bars
Cost of cement: 32 x $ 9 = $288 2 2
d 12
x L=¿ x 12=10.66 x 21 = 223.86 kg
7. Sand 162 162
1, 5 1.66 Cost of bars: 21 x $14 = $294
x 6.1 = 1.66 = =0.83=1loads
5.5 2
Total cost of materials
Cost of sand: 1 x $25 = $25
• Cement = $288
8. Gravel
• Sand = $25
3 3.3
x 6.1 = 3.3 =1.16=2loads • Gravel = $90
5.5 2
• Water = $24
Cost of gravel: 2 x $45 = $90
• Nails = $20
9. Water
• Steel bars = $294
32 x 100
= 16 = 16 barrier • Frame Wood = $220
200
Cost of water: 16 x $1.5 = $24 • Support steel for slab (rent) = $36
6. Frame wood Total cost of material = $997
Area = 24.4m2 + (0.25 x 4) x2 +( 0.25 x 6.1) x2 =
29.45 m2 of flat wood
Area of flat wood (comesato) 1.5x2 = 3m2 = $22
Cost of frame wood: 30m2/3m2 = 10 = 10 x $22 =
$220
7. Supporting steels of the slab
36 pics x $1 = $36

PROJECT: ELEVATED WATER TANK ESTIMATIONS 26


2. Cost of labours Total cost of labours
4. Steel fixers • Steel fixers = $58
1 = 100kg, 223.86 kg/100 kg =2.238 = 3 steel fixers • Carpenters = $58
Cost of steel fixers: 3 x $16 = $48 • Meson = $32
Steel fixer helper = 1 x $10 = $10. T = $58 • Mixers = $20
5. Carpenters • Unskilled = $56
1 = 10m2, 27m2/ 10m2 =2.7 = 3 carpenter Total cost of labour = $224
Cost of carpenters: 3 x $ 16 = $48
Carpenter’s helper = 1 x $10 = $10. T = $58 Total cost of a slab
6. Meson • Total cost of material =$975
3
6.1 m • Total cost of labour = $224
1 = 5m3 , 3
=1.22=2 meson
5m • Total cost of the slab = $997 + $224 =
Cost of meson: 2 x $16 = $32 $1221
7. Mixers
1 = 3m3=¿ 6.1m3 /¿3m3= 2 mixers contingency 10% = $122.1 + $1221 = $1343.1
Cost of mixers: 2 x $10 = $20 1343.1.
= 220.18 = $221/m3
10. Unskilled 6.1

1= 0.9m3 =6.1m3 /0.9 m3 = 6.8


Rate of Slab = $221m3
Cost of unskilled: 7 x $8 = $56

PROJECT: ELEVATED WATER TANK ESTIMATIONS 27


PLASTERING PAINTING
Area = 30.5+20+48.8 = 99.3m Area of the elevated tank is
1.6 x 6 = 57.6m = (2.5 x 4)x2 + (6.1 x 2.5)x2
17.08+16.8 = 33.88m 20m2 + 30.5 + (6.1 x 4 )x2
Total Area:190.75m2 20m2 +30.5 + 48.8 = 99.3m2
125 This area is the area of only tank and know we
190.75m2 x = 23.8m3
1000
find the area of beams and columns
Ratio we take: 1:6
The area o columns
1. Cost of materials
(0.4 x 6)
1. Cement
(2.4m2) x sides of the column =2.4m2 x 4
1 3.4
x 23.8=3.4= = 97.14= 97 bags 9.6m2 this is the area of one column
7 0.035
The number of columns we have is 6
Cost of cement: 97 x $ 9 = $873
6 x 9.6m2 =57.6m2
2. Sand
Area of beams
6 20.4
x 23.8 = 20.4 = =10.2=10loads
7 2 2(3.2m x 0.4) + (3.2 x 0.3)2
Cost of sand: 10 x $25 = $250 2.56m2 + 2.88 = 5.44m2
3. Water (5.44m2 + 4 beams)
97 x 100 21.76m2
= 48.5 = 49 barrier
200 The other beams are
Cost of water: 49x $1.5 = $73 (0.4 x 4) x 2 + (0.3 x 4) x 2
Labour Cost: 2 x (1.6m2) + (1.2m2)2
One man can plastering = 24m2/day 3.2m2 + 2.4m2 = 5.6m2
190.75 (5.6m2 x 4 beam)
= 7.9 = 8 skilled labours
24
22.4m2
Cost: $8 x 8 =$64
The total area is
190.75
mason 2 = 7.5 = 8 mason A= 99.3m2 + 57.6m2 + 22.4m2 + 21.m
25.6 m
Total area= 201.2m2
Cost:$18 x 8 =144
Material cost:
1. Mixers
1bag contains 35kg and coat 50m2
1 8/6 = 1.33 mixers = 2 mixers
Number of bags 201.2m2/50m2 = 4.02 =4 bags
Cost of mixers: 2 x $10 = $20
Cost: $5 X 4 = $ 20
Total cost: $1424
1424 Stucco:
= 59.8 = $60/m3
23.8 Applying two coats of external wall surface

PROJECT: ELEVATED WATER TANK ESTIMATIONS 28


Base of the building size 201.2 x 2 = 402.4m2
Description : Construction rubble stone One tin can coat = 152m2
foundation if the areas of height o=0.4m Number of tine = 402.4m2/152m2
and 0.8 width and total length of 7.6m 2.647 = 3 tin
,mixed ratio 1:6 Cost: $6 x 3 = $18
Quantity = 7.6m*0.8m*0.4m= 2.56𝑚3 Distempering: apply two coats of distempering
35% of mortar ,65% stone on external
Volume of stone = 2.43𝑚3*0.65=1.58𝑚3 201.2 x 2 = 402.4m2
We use truck load capacity of stone 2.5𝑚3 One tin can coat = 152m2
Number of loads stone = Number of tin = 402.4 m2/152m2 = 3tin
1.58𝑚3/2𝑚3=0.79 Cost: $9 x 3 = $27
1 loads Labour cost:
Cost of stone = $35*1= $35 One skilled labour: can do 50m2
mortar = 2.43𝑚3*0.35=0.85𝑚3 201.2m2/50m2 = 4.04 so is 4 skilled labours
1. Cost of materials Cost $16 x 4 = $64
1. Cement Mason: 1
1 0.14 Cost: $18 x 1 = $18
x 0.85=0.14= = 4 bags
6 0.035 Total Cost: $147
Cost of cement: 4 x $ 9 = $36 147 .
= 0.7 = $1/m2
2. Sand 201.2
6 0.72
x = 0.85 = =1=1 loads
7 2
Cost of sand: 1x $25 = $25
3. Water
4 x 100
= 2 = 2 barrier
200
Cost of water: 2 x $1.5 = $3
Unskilled labour: 4 unskilled
Cost: $8 x 4 = $32
helper labour: 2 helpers
cost: $8 x 2 = $16
mixers
1mixer $10

PROJECT: ELEVATED WATER TANK ESTIMATIONS 29


1 mason $20
Total cost:$177
Rate :$210

BOQ PREPARATION

PROJECT: ELEVATED WATER TANK ESTIMATIONS 30

You might also like