Professional Documents
Culture Documents
Ref. no:
Name: Silver Chuah Revision: 00
Date:
Contact no.:017-9269891
Reviewed by Tialoc
Submitted by Package QA/QC SHE Manager Construction Approved by
Contractor Manager Manager Manager Tialoc Project
Manager
Signature:
Name:
Date:
Time:
1 of 6
OSRAM KULIM
Commissioning and Test Plan for
AHU & DOAS
Ref. no:
Name: Silver Chuah Revision: 00
Date:
Contact no.:017-9269891
1.0 Introduction
This document shall address the typical works for all AHU & DOAS start-up and T&C
No Description Quantity
1 Digital Power Meter (KYORITSU KEW SNAP 2002PA) 1
2 Pitot Tube micromanometer (TESTO 440 dP) 1
3 Temperature & RH Meter (Pro’s Kit MT-4616) 1
4 Digital Clamp Meter (KYORITSU 1009) 1
5 Barometer 1
6 Thermohydrometer 1
Skilled worker
Supervisor
Safety supervisor
2 of 6
OSRAM KULIM
Commissioning and Test Plan for
AHU & DOAS
Ref. no:
Name: Silver Chuah Revision: 00
Date:
Contact no.:017-9269891
I. To identify the actual location for equipment start-up and T&C as per approved shop drawing.
III. Ensure all material, equipment and tools are ready prior to commencing AHU/DOAS start-up and T&C
I. All equipment needs to be stored with proper cover to prevent any affect to the quality of material.
II. Storage area shall not obstruct any access and property barricades with proper signage with PIC and
barrier ownership.
II. Workers shall practice minimal safety procedure with the use of safety helmet, safety vest, safety
III. Ensure all permit to work and related documents was approved before start installation work.
3 of 6
OSRAM KULIM
Commissioning and Test Plan for
AHU & DOAS
Ref. no:
Name: Silver Chuah Revision: 00
Date:
Contact no.:017-9269891
Safety briefing of the day’s job will be done by supervisor 15 minutes prior to operation
All units at site shall be inspected and ensured it is as per submittal and are thoroughly cleaned. With the
Check that all air filters are in place and positioned properly.
Remove all foreign material from the drain pan and check drain opening and condensate line for
obstructions.
Ensure all dampers are open (both supply and return duct)
M5, F8 and carbon filter (if applicable) to be remained installed during T&C and flushing.
Acknowledge the AHU/DOAS start-up check list by Tialoc before start-up the AHU/DOAS (referring
4 of 6
5.2 Start-up procedure
After completing all start-up checks and procedures, the unit may be started. The following checks and
adjustments should be made during initial start-up:
Bump-start unit and observe the fan wheel for proper rotation, as indicated by rotation arrow located on
fan housing.
Measure the motor voltage and amperage on all phases to ensure proper operation. The readings
:
should fall within the range given on the motor nameplate.
Pay particular attention to any vibration, noise or overheating of the motor and fan bearings.
(Bearings may run warm during break in).
Supply and return dampers must be in good condition. ]
3. Air velocity / Air Volume (adjust the potential meter to get the air volume as design)
(a) The air velocity shall be measure at the measuring port at the discharge duct using pitot
tube micromanometer. The location of the measurement will be subject to system design
and site location availability.
(b) Calculate the air volume by using the formula
below Air volume = air velocity * Area
(c) Adjusting the potential meter to increase air volume to meet
specification Air volume = air velocity * Area
4. Motor Amps
(a) Measure the motor running amps for each EC fan by using the power meter
5. Motor Voltage
(a) Measure the main incoming voltage by using the power meter
8. Fan section limit switch testing (Cut-Off power when door is open)
(a) Open the fan section door when the unit is running.
(b) Observe if the EC fan can be cut-off and record the result
5 of 6
10. Light checking
a) to switch on the marine light to check on the light functionality
12. Emergency push stop button and Main disconnection switch checking
a) Check the functionality of emergency stop button and main disconnection switch
6.0 Housekeeping
I. The PPE required for this task is safety helmet, safety boot, hand gloves, electrical protection glove, eyes
protection and safety vest.
II. Please refer to Risk Assessment (HIRARC) attachment
Inspection and Test Plans (ITP) shall include inspection at the following stage.
ITP shall also address the “Hold Point”, where approval on the work activity is required.
4. Calibration certificate
6 of 6
Project Name : Location :
Serial Number :
1 Belt Tensioning
4 Fan Rotation
5 Fan Wiring
11 Temperature Gauge
14 Drainpipe Connection
7 of 6
15 Test Instrument Calibration Certificate
8 of 6
9 of 6
10 of 6
11 of 6
12 of 6
13 of 6
14 of 6
15 of 6
16 of 6
17 of 6
18 of 6
19 of 6
20 of 6
21 of 6
22 of 6
23 of 6
24 of 6
25 of 6
26 of 6
27 of 6
28 of 6
HAZARD IDENTIFICATION RISK ASSESSMENT AND RISK CONTROL
Contractor Company Name: Project Title: Activity Assessed:
SPECIFIC DIMENSION SDN.BHD
Probability
Effects Measures
Ranking
Severity
Risk
To inform & get approval from Miscommunication Non compliance Workers compulsory to 1 1 low Other than project
project Coordinator and Area attend SHE training coordinator, area owner
Owner & EHS on the nature of required for the activities and EHS, please get an
work to be carried out prior to work before execute work. approval from the system
commencement Foreign Workers and owner as well. Ensure they
management staffs with understand the scope and
valid work permit. the risk(s) of work to be
SIC training and on job carried out.
training by task
management team.
Workers to communicate
through TBM
29 of 6
Conduct Toolbox Meeting to brief Mis *Non compliance All workers and 1 1 low
the job sequence and possible communication management staffs
hazard encountered before start Steps of work involved must be briefed
work prior start to work.
Tool box meeting shall be
conducted by supervisor
before start work.
All workers shall perform
according to TBM
instruction. Get approved
Motorola site badge and
display full time at site.
30 of 6
SEVERITY OF IMPACT
Severity Group Rank People Equipment/ Facility Property
Minor 1 Near miss Near miss Near miss
Superficial injuries, minor burns, cuts & No serious equipment or facility damage Chemical spill requiring only routine
bruises; eye irritation from dust. Losses up to RM10,000. cleanup.
Losses up to RM10,000.
Major 2 Lacerations, severe burns, concussions, Equipment or Facility damage (repairable) Chemical spill. Internally controlled.
serious sprains, minor fractures, electric Losses more than RM10,000 and up to Losses more than RM10,000 and up to
shock. RM100,000. RM100,000.
Hearing loss, work related CTD, ill health
and minor disability.
Critical 3 Major fractures, multiple injuries, fatal Major equipment or facility damage (need Chemical spill require external help and
injuries, amputations & poisoning. replacement). expertise.
Life shortening and/ or acute fatal disease. Losses more than RM100,000. Losses more than RM100,000.
PROBABILITY OF OCCURENCE
Probability Group Rank Expected Rate of Occurrence of Each Hazard
Unlikely 1 No more than once per year.
Possible 2 No more than two to three per year.
Frequent 3 Four or more per year
RISK RANKING
Probability Unlikely (1) Possible (2) Frequent (3)
Severity
Minor (1) Low Low Medium
Major (2) Low Medium High
Critical (3) Medium High High
31 of 6