Professional Documents
Culture Documents
1 PURPOSE 3
2 SCOPE 3
3 REFERENCES 3
5 RESPONSIBILITY 5-7
10 HOUSE KEEPING 11
1. PURPOSE:
2. SCOPE:
3. REFERENCES:
The following reference documents to the extent specified herein form a part of
this method
Manufacturer GA drawings
2 For Lifting
Lifting equipment fork lift
10 For Drilling
Drilling Machine
5. RESPONSIBILITY:
Manager:
Site Engineer:
Quality Personnel:
Safety Engineer:
The materials received at stores / site shall be checked for manufacture details,
as per delivery note and as per approved material submittal to ensure delivery
is correct.
Unload Fan coil units with manually and store in the designated place.
Ensure HSE permit is taken before starting the lifting.
Always be careful to avoid damage when handling.
The installer will receive a set of installation drawings from the factory with tag
numbers and installation shall be executed as per manufacturer
recommendations.
All the materials used for this activity of method statement shall be checked &
inspected by contractor QA/QC Engineer and approved by engineer prior to
Installation.
Ensure that the fan coil units shall be vertical type for floor mounting, horizontal
type for ceiling-suspension as per project specification.
Floor-mounted vertical units shall have vertical top discharge; and horizontal
units mounted within ceiling space shall have horizontal discharge and shall be
ductable as per specifications.
Fan coil units shall be complete with chilled water coil, centrifugal fans and
motor, cleanable fabric filters, double-wall insulated condensate drain pan.
Ensure that the ends of the Coil and Drain pipe are capped properly.
Ensure proper follow up is done with civil people for the installation of FCU’s.
The site engineer and supervisor shall identify the location of FCU’s installation
with reference to approved shop drawings and co-ordination drawings.
It is recommended not to remove the plastic covering materials during and after
delivery to avoid corrosion and deterioration
Vibration Isolators are installed as per the load calculations done during MAS
approval.
Lift the FCU and hang it to the installed vibration isolators and tight the nuts
provided.
Inspect Chilled water piping for flow direction and correct connections in to the
Unit.
Ensure that Flushing of chilled water system is done before leaving the water
into the Unit.
Check all the valves for Supply and return Chilled water pipes are open.
Check all the Filters are cleaned and placed as per Manufacturer
Recommendations.
Ensure BMS connections and Fire alarm connections are done and terminated
properly as per project requirements.
Check for the motor RPM as designed for the unit. Motor speed should not
exceed to the designed RPM.
Measure the intake airflow and adjust to the designed set value.
Check the condensate drain water goes out freely without staging.
Record all the parameters in the commissioning report and submit for
Engineer’s approval
All the works shall be inspected for the conformance towards project
specifications
All the inspection requests which is a witness point as per the ITP shall be
submitted one day prior to the client.
RECORDS:
All inspection formats and other records shall be as per project approved forms.
Safety
All activities will be executed in accordance with contractors HSE Plan and HSE
guidelines.
Safety risk assessment shall be performed for every job or task, which has the
potential for harm.
Ensure Personal Protective Equipment (PPE) is available with all the workers.
All required equipment and tools should be checked before start of work for
suitability and integrity.
All safety Guidelines shall be adhered as per approved HSE Plan.
Necessary permit to work to be obtained as per the site requirement.
Before commencing any works, all employees will attend a safety induction
training to ensure all safety measures are understood and implemented and to
cover Specific procedures in case of emergency and if necessary practical
training .Exercises will be conducted on escape routes, signage, evacuation
and rescue
10. HOUSE-KEEPING:
Effective housekeeping can eliminate some work place hazards and helps to
get job done safely and properly.
The work area shall be maintained neat and tidy as reasonably practical all the
times