Professional Documents
Culture Documents
Preface, vii
Chapter 1 Introduction 1
1.1 Maintenance Defined 1
1.2 Trends in the Evolution of Maintenance 2
1.3 The Challenge of Maintenance 3
1.4 Maintenance Management 5
1.5 Function of Maintenance Work 7
1.6 Classification of Maintenance 9
1.7 Maintenance Objectives, Planning and Control 12
III
...•. -- -.-~ .. _------._-- ----._--".
Table of Contents
Table of Content~
Chapter 5 Elements of Maintenance i
5.1 Attendance (Operation) 76 76 9.7 The case of non constant repair rate 165
5.2 Service 76 9.8 Maintainability for a given restoration time with Weibull times-to-restore
5.3 Repair 77 distribution 166
The teaching material discusses important topics like damages and their remedies in a general
fashion to introduce damage problems in a wide range of engineering discipline; issues of
condition monitoring and on-condition maintenance are treated; it introduces concepts of;
reliability and maintainability in maintenance application; it also touches on aspects of
maintenance management.
It is the earnest belief of the author that users will find this material helpful and appropriate for
the subject matter treated inhere.
Needless to say, the author is indebted to the very many authors and editors of various texts and
handbooks that treat the same subject and whom he has freely referenced.
Acknowledgement is due to the Department of Mechanical Engineering for giving the author
the permission to prepare this material, and to the Research and Publications Office of Addis,
Ababa University for granting financial assistance for word processing of the manuscript. '
Alem Bazezew
Department of Mechanical Engineering,
Faculty of Technology, Addis Ababa University
September 2003
Vll
Chapter L
Introductioni
Manufacturing of goods is closely connected with the means of production. ~very means o~
production is, in turn, closely connected with wear and tear. A few examples are mentioned
below.
If proper action against these wearing out of equipment and materials is not taken, there would
be breakdown in the production processes, and materials deteriorate unduly resulting in loss
or total stoppage of production. Hence, there is a permanent necessity that all means ot
production be
- used
- checked
- serviced
- tended
in order to give the full function which they are designed for. The last three necessities
constitute what is called maintenance, whereas the former is operational.
From the engineering viewpoint, the management of the means of production has two elements
to it. First, it must be maintained, and second, from time to time it may also need to b¢
modified.
The term maintenance is derived from the word maintain which is defined as
Introduction 3
2 Maintenance of Machinery
\
maintenance is . . 1 .
mcreasmg y facmg new challenges. The challe . Introduction 5
managers face can be summarized as follows: nges that modem maintenanC{
1.4 Maintenance Management
- to select ~he most appropriate maintenance techniques
- to deal with each t ff . '
. ype a allure process appropriately ,- -1> Maintenance is related to profitability through e<iuipmentou~ and e~t running cost;
- ~n order to fulfil the expectations of users, '
also' through time taken for maintenance purposes. With increasing industrialization and
- m the most cost-effective and sllstainable m d complexity of machinery, the importance of maintenance increases as downtime and 'costs
.I a e,
WIt 1active support of people involved. related to downtime become increasingly prohibitive.
----------
-v>l9-understand maintenance and its various characteristic features, it is imperative to know what
Tllird Genemlion
\
I ~ equipment life-cycle comprises and the factors at the various stages as they relate to .
- Higher plant availability
and rehabil ity \ maintenance. An industrial equipment is considered as passing through a number of stages, the/
- Greater safety /
- Better product quality first being design and the last one replacement. The level of maintenance activity required and
First Generation
Second GeneraJion
- No damage to the
\
- Fix it when it
- Higher plant availabilitv
environment
/ maintenance management involved at the equipment operation stage is affected by factors at
broke
- Longer equipment lite -
- Lower costs - Longer equipment life
) other stages through which the equipment passes. These stages are briefly discussed below
\
1940 - Greater cost effectiveness
1950 1960 1970 indicating how maintenance is affected by the actions undertaken at the respective stages.
1980 1990 2000
GrOWing expectations a/maintenance
'~Commissioning stage:
-
This is a stage of technical performance testing and also a stage of where primary
Third Generation design faults are located and designed out. During commissioning, maintenance
- Condition monitoring
- DeSIgn for relaibility effectiveness can be analyzed and changes can be effected in the system.
and maintainability
- Hazard studies
Second Gefleration
First Generation
- Scheduled overhauls - Small fast computers
- Failure modes and etrects
-\> Operational stage:
- Systems for plannino
- Fix it when it analysis The operational stage is a stage of continued learning where maintenance plays an
and cintroll ing wort
broke - Expert systems (
- BIg, slow computers
1940 - Multiskilling and teamwork! important role. In this stage, mal-operation should be avoided and maintenance
1950 1960 1970
1980 1990 2000 activities are optimized so as to exploit the system reliability and maintainability
Changing Maintenance tech ntques
.
characteristics.
Fig.I.I Trends in the Evolution ot' A,r .
:/ IVlazntenance*
(* Source: John Moubray, Reliability C t d .
en ere Matntenance 2nd d I .
, e., ndustnal Press Inc., 1997.)
6 Main~enance of Machinery
Introduction 7
--t>Dpring the operation period or useful life of an equipment proper maintenance management
can influence' resource utilization and profitability of an industrial plant. Maintenance
management is the direction and organization of resources in order to control the availability
and performance of an industrial plant to a specified level. Normally, to meet the workload in
a timely and cost effective manner, any maintenance management is faced with a two-
dimensional problem and these are
.-.- -
i) determination of size and nature of the maintenance work load, and
ii) organization and control of resources, i.e. men, spares and equipment.
c»--;P1.5 Function of maintenance work
@The maintenance department influences plant availability directly through preventive and
corrective maintenance tasks.
Top
Availability = ----'---
Top + Tdawn
where Top cumulative time of operation, up-time
Tdown = cumulative outage time, downtime
Downtime does not consist only of the time taken for repair but also includes delays due to lack
of resources and information.
~ Delays are influenced by organization of maintenance resources and flow of information and
~ this can be expressed as
The maintenance
of maintenance
manager
can only be removed by engineering
department.
those outages
Causes of low
re-design which is not the
which occasion
r
CM
--=F?----.
~ epa ir Tune)
PM
(Off-line Time)
1-__
DELAYS
(Waiting for M)
1 -\
maintenance actions. The outages constitute downtime. Fig. 1.3 shows equipment time and
its constituent parts including the activities involved during maintenance.
RESOURCES INFORMATION
Fig. 1.4 shows downtime and its classification including the various features involved.
EQUIPMENT TIME
ENGINEERING TECHNIQUES
MAINTAINABILITY MANAGEMENT
(Logical fault-finding: Diagnostics)
I
ACTIVE TIME INACTIVE TIME
Fig. 1.4 Downtime and its constituents
I
UPTIME
I I
DOWNTIME
.----1-
MAINTENANCE MODIFICATION DELAY
1.6 Classification of Maintenance
r MAINTENANCE \
PREPARATION PROCU MENT FAULT
CLEANUP
I
TIME CORRECTION
TIME TIME
TIME
[Shutdown M \ [Shutdown M
I
I
INSPECTION SERVICING REPLACING MINOR OVERHAUL MAJOR OVERHAUL
\
TIME TIME TIME TIME TIME
(aging units)
Servicing: Servicing of subsystems ~d_ components includes care along with other activities
Preventive mainte nance helns i prolonging the life of e ui
e ps m . "
system failure rates from exceed' desi ~ q pment by limiting component and such as filling in of oil and fuel, readjustment, re-setting, adjusting, checking
mg esign levels Prev ti . without instruments.
accuracy of equipment. . en ive mamtenance also ensures
Maintenance objective is minimization of the resource and unavailability costs. 1.7.1 Work control
This is a function of the maintenance organization a~d it.sobject is to match men, spares and
Unavailability cost = loss of in-service material and production loss while in repair . kl d This function mcludes
equipment to the mamtenance wor oa .
or undergoing preventive Maintenance.
_ location of plant failure,
_ determination of the necessary corrective action,
Resource cost = corrective maintenance labour, preventive maintenance labour,
- the setting of priorities,
maintenance equipment, spares usage and holding costs.
coordination and control of resources.
,." n:.tUIh.entnrCl! oj'Machinery
. I
1.7.3
Mamtenance cost control To deal with maintenance on a scientific basis, it is necessary to study the reasons for and
forms of damages, and the possibility for reducing the influences of damages.
The objective of maintenance control as the n ' Ii ,
' ame Imp Ies IS to " ,
re Iated to maintenance activities The f ti f ,mmlmlze the sum of costs 2.1 Classification of Damages:
, unc IOns 0 maint
- to identify high cost areas of plant, enance cost control is:
- to mon~tor ,the trend of maintenance effectiveness, The use-value of an equipment or a means of pro~uction is affected by two processes.
to pro,v,Ide mformation for maintenance decision makin These are technological processes. and technical and economical proce§ses.
- to facIlItate maintenance budget' g,
mg.
Processes Reducing
use-ralue
Technological
(Change r Processes
State)
Technical-Economical
proceres
I
D1 GES Obsolescence
Overload Others
WT (fire. pest, etc.)
I- I
Wear Wear Wear Wear
These two processes reduce the use value of means of production. Technological processes
are related to change of state of an equipment which cause damages, while technical-
,'U u.menance of Machinery
' ••
The process of corrosion takes place"due to direct chemical action when the metal enters
~ ------------------------------_1'_"_"_W-W-".---"-"-'--~~~--------------------
into a chemical
. reaction with 0th er eIements to form no - . _ usually it results in localized destruction of material (surface); and
electrochemical action' Metalli I . n metallic compound or due to
. .. . ICe ements when placed in . ' . _ it can take place below the surface affecting the strength of the component
have definite inherent tendencies to go .. t th " contact With water or a solutIOn
. III 0 e solution IIIthe fi f electri
particles. In general, the metal and particularl iron whi orm 0 e ectrically charged (invisible).
as rust. This formation of rust affect th ~ ~ which enters a solution is thrown down
s e continuation of the . .
of possible ways two of which are th £ II . corrosion process in a number Iii. Inter-crystalline corrosion ./.
, e 0 OWIng. -Ns type of corrosioritakes place below the surface and occurs at the grain boundary
of metal alloys usually causing sudden crack. .,...- -
i. Direct chemical corrosion:
This corrosion is limited to conditions involvin hi ,.
temperature or both E I g ghly corrosive environments or high jv, Trans-crystalline corrosion v'
. xamp es are: metals left open in darn . As in the case of inter-crystalline corrosion, trans-crystalline corrosion also takes place
temperature; metals in contact ith tronz aci p environments and at high
WI s rong acids or alkalis. below the surface. But unlike the inter-crystalline corrosion it takes place across the
2.6 Wear i. Depending on the relative motion of mating parts, there are three kinds of wear.
va. Kinematic wear which may possess anyone or a combination of the following
motion characteristics:
T~e phenomenon of wear is treated under the subject matter oftribology. Tribology is the - sliding
SCIence and technology of interacting surfaces in relative motion which embraces the
- rolling
gen~ral ~oncepts of all aspects of the transmission and dissipation of energy. Friction, wear,
lubrication come under tribology, - drilling
- fretting
- mixed
.we~ mechanisms that are frequently encountered in practice are schematically represented c> b. Static wear
m FIg. 2.6. The figure shows the system structure, interaction between th ti
th ib I . I . e ma mg parts v c. Impact wear
e tn 0 ogica action, the type of wear that ensue" and th ff . .'
takes place. .. e e recnvs wear mechanIsm that
ii. Depending on the time behaviour of wear there are two kinds of wear.
Wear is an undesired change of surface of machi a. Stationary. wear in which the wear intensity remains constant over a long period
. . ne components by the removal of little of time.
particles caused by mechamcal reasons and/or trib h . al
I oc enuc reasons. Mostly, wear is a. Non-stationary wear in which the wear intensity depends on time.
Fundamentals of the Theory of Damages 23
2.6.2 Mechanisms of wear:
a. Surface fatigue wear mechanisms: This phenomenon may occur mainly due to the
Recent investigations in wear phenomenon . di th . action 0 stresses·-;- or below the surfaces without needing a direct physical solid
. III icate at wear f terial
different mechanisms depending 0 th . 0 ma en s occurs by many contact of the surfaces under consideration. Surface fatigue effects are observed to
n e matenals the envi I
conditions, and the geometry of th . ' rronmenm and operating occur in journal bearings. The effect of fatigue wear is especially associated with
classified into two groups: e weanng bodies. These wear mechanisms may be
repeated stress cycling in rolling contact, and is accompanied by the generation and
- those p~imm:ilYdominated by the mechanical behaviour of solids and propagation of cracks.
j
I
l
1 Heating
I
1I Material Interactions
(interatomic Forces)
I
I )W»S~ /7 /7 /7 /
soft material
/Surface Fatigue
I /
Abrasion
1 [ Tribochemical reactions 1 l Adhesion
I
Stress Cycles
I I I I ---
Fig. 2.4 Abrasive wear
Micro-cutting
Microstructural Changes Micro-ploughing t<ibocl<m"" film, due -\) ii. Material interactions
Transferred material
Crack Formation Micro-cracking to material/invironment
due to adhesive joint
Delamination
mteratlOns
formation and rapture
These are due to intermolecular forces either between the interacting solid bodies or
between the interacting solid bodies and the environmental atmosphere and/or the
interfacial medium and lead to wear processes described broadly as tribochemical
reactions and adhesion.
l Material removal process
I
~Tribochemical wear mechanisms: Surface fatigue and abrasion wear mechanisms
I Fatigue Wear
Particles
I Abraded Wear
Particles
I C'ribochemiCal Wear
Process Adhesive Wear
Process
1 U are described mainly in terms of stress interactions and deformation properties.But
in tribochemical wear the dynamic interactions between the ma!e,rial~9mpon;rt;
and the environment determine the wear process, where the environment is the third
Fig.2.3 Tribological interactions and wea- m h . * partner.
(* S
ource:
M·
ichael J. Neale, The Triboio Hand
. r rnec antsms
')nd
Publishing, 1995) gy book;': ed., Butterworth - Heinenemann
a. Adhesive wear mechanisms. Adhesion is the ability of atomic structures to hold
i. Stress interactions themselves together and form surface bonds with other atoms or surfaces with which
These are due to the combined action of load f they come into contact. The adhesive wear processes are initiated by the interfacial
wear processes described broadly c. orc~s and frictional forces that lead to
as surrac- fatIgue and abrasi T adhesive junctions which form if solid materials are in contact on an atomic scale.
mechanisms are stress interactions and teri 1 . , rasion. hese wear Material is then transferred due to adhesive joint formation which leads to rupture.
ma ena IllteractIOns.
A simplified description of adhesive wear is shown in Fig. 2.5.
l(! (b)
Classification
System
tructure
of wear pbenomena
Tribological
action
(symbols)
1)pe of wear
Adbesion
Effective mechanisms
(individuallY or combined)
Ab •.•••ion
Surface
fatigue
.
Tribo-
chemical
reactions
Fig. 2.5 (a) sliding occurring between surface films; (b) Surface films raptured
with direct interaction between materials
Isol id
in torfacial
medium (full
ftuidfilm
sliding
rolling
impact lL~
I~I
,
X X
separation)
solid
Wear mechanisms that are frequently encountered in practice are schematically represented Solid sliding sliding wear ,
I
solid t X x X X
in Fig. 2.6. The figure shows the system structure, interacting or mating parts, the (witbsolid ~~ I I
friction,
tribological action, the type of wear that ensues and the effective wear mechanism that takes bonndary
place. rolling
8
lubrication, rolling wear
mixed X X X X
lubrication) I
I
cp
I
2.6.3 Wear process / impact
impact wear
, X I X X X
c=:J I
The wear process is a complex one being dependent on a number of factors: load, velocity, osc "' atio~ freting wear
intermediate materials, ambient conditions, etc. Wear processes are accompanied by X X X X
heating in the micro-range as well as changes in the physical and chemical material ~olid sliding
solid and sliding abrasion
properties of the wear partners. Wear processes can be differentiated into the fOllowing. I ~\..., I
particles
C=J X
i. Shearing process j
Roughness points will be sheared off if the acting forces are greater than the shear
strength. This leads to the reduction of roughness and increased percentage of contact
area which reduces energy concentration and wear velocity.
sliding
rolling
~~
8
t
t
sliding abrasion
(three body
abrasion)
X
I
ii. Elastic deformation....( !'olid flow
particle erosion
ftuid witb
particles ~ (erosion wear) X X X
Big surface roughness results In low percentage of contact area and high energy Solid flow
c gas with fluid erosion X X X
concentration in contact point. This may result in high local stresses. In the elastic range particles ~ (erosion wear) i
this causes small flattening or bending of rouglmess points. Repetition of this process impact !
~
IIIII
drop erosion
1 I
X
I
X
h = h + h'ta
i. Wear by solid friction . ~ ~ ~/
ii. Wear by liquid friction" Depen dimg on <1, assum m'g the initial wear h 0 = 0 ' the wear behaviour with time . can
• be
increasing, decreasing or constant. These three wear behaviours with time are shown m the
In the case of liquid friction the two mating bodies are completely separated from each
figure below.
other by an intermediate material, mostly a lubricant. Friction occurs in the lubricant,
and wear is influencedby load, relative velocity, temperature, viscosity oflubricant, the
lubricating gap and the force of inertia are neglected.
wear, [h] a - inceasing wear
b - decreasing wear
iii. Wear by mixed friction: a
c - constant waer
Simultaneous action of solid and liquid friction, caused by high roughness or high load
for the lubricating film causes wear by mixed friction, This results in metallic contact
at times.
time, [t]
The main protection measure against wear is lubrication o~the mo~ing parts. A lubricant
Liquid friction
is the intermediate material between two parts with relative motion for the purp~se of
re duci
ucmg ./.':..
tnction an d/ or wear between them . Proper
'. .. lubrication. with timely
addition/replacement of lubricant plays a vital role in mamtammg machine ~ccuracy and
increasing its working life.
Lubricating oils are of two types: m.YJ~raland synthetic oils In additi . , and contamination. Oxidation is the process offorrning oxides by some chemical process.
, , " _._ . I IOnto preventing or
mmuUlzmg wear, lubricating oils perform the foIlowi;"g duties: Factors that influence oxidation are:
- cooling by reducing friction and removing excess heat generated; rise in temperature: rate of oxidation doubles for about 10 Crise;
0
- protection by inhibiting corrosive processes caused by air and water - access to oxygen:
- cleaning by flushing dirt particles away from lubricated surfaces. ' presence of catalysts
- type of oil (compounds)
a. Mineral oils
- top-up rate
Mineral ~il~ are basic~llY hy~ocarbons often with some additives to introduce specific
charactenstic features in the OIl. Mineral oils are classified as: Mineral oils are relatively stable to thermal decomposition in the absence of oxygen. But
at high temperatures over 330 C oils will decompose into fragments. The effects of
0
- Paraffinic: which contain significant amount, of waxy hydrocarbons with little or no thermal decomposition is to produce light hydrocarbons and carbonaceous residues which
asphaltic matter; reduce flash point and viscosity of oil and formation of hard residues which accentuate over
heating.
- Naphthenic: which contain asphaltic matter in least volatile fractions with little or no
wax; Contamination is probably the most common reasonfor changing oil. Contaminants can
be one of the following or a mixture thereof:
- Mixed base: which contain both waxy and asphaltic materials. - gaseous, like air, ammonia, etc.,
- liquid, like water, oil of another type or viscosity or both
Th~ most important physical property of mineral oils is viscosity which is a measure of - solid, like fuel soot, road dust, wear products
. ~esIst~c~ to fl.ow. ?epending on viscosity lubricant oils are also classified by the change
in their ~ISCOSItywith temperature, which is given by Kinematic Viscosity Index (KVI). Additives are added to plain mineral oils to improve their properties and/or for the purpose
Depending on the KVFs lubricating oils are classified as: of imparting new properties. These additives improve the oxidation stability of oils result
Low viscosity index -' (LVI) below 35 KVI in increased operating temperatures and induce higher wear prevention ability. The main
Medium viscosity index '·(MVI) 35 - 80 KVI types of additives and their functions are given below.
High viscosity index (HVI) 80 _ I I 0 KVI - Acid neutralizers: neutralize contaminating acids formed by combustion,
Very high viscosity index (VHVl) over 100 KVI decomposition, etc.
- Anti-foam: reduces surface foam.
T~e viscosity of mineral oils reduces with increasing temperate and increases significantI - Anti-oxidants: reduce oxidation as inhibitors, retarders, catalyst
Withpressure. y
deactivators, etc.
- Anti-rust: reduces rusting of ferrous surfaces swept by oil.
Other important lubricant properties are the following: - Anti-wear agents: reduce wear and prevent of scuffing of rubbing surfaces
- anti-wear and EP ( extreme pressure) properties; under steady load conditions.
- oxidation resistance; Corrosion inhibitors: protect metallic surfaces from corroding due to
- anti-corrosion properties; combustion residues.
- anti-foaming properties; and Detergents: reduce or prevent deposits formed at high temperatures.
- demulsibility (ability to separate from water). Dispersants: prevent formation of sludge by dispersing fine suspensions.
- Viscosity index improvers: reduce' the decrease in viscosity due to increase in
Lubricating oils can become unfit for further service by oxidation, thermal decomposition temperature.
- Pour-point depressants: lower lubricant freezing temperatures.
Fundamentals of the Theory of Damages 31
,30 Maintenance of Machinery
ii) Greases:
These. additives are...combined with oils in various ways so as t 0 0btai
tam the performance
~equITe~. The mixmg, If done indiscriminately, however, may result in undesired A grease may be defmed as solid to semi-fluid lubricant consisting of a dispersion of a
interactions. thickening agent in a lubricating fluid. The consistency of grease depends on the
percentage of thickener in the grease. Depending on the degree of consistency, greases are •
/ h)\Synthetic oils
/
classified as:
Synthetic oil~ ~e products produced under controlled conditions industrially from chemical
_ Semi-fluid
b~e and additives. These are pure, idealized lubricants whose molecules are uniform in
- Soft
weight and shape. Synthetic oils are engineered to perform under rigorous conditions and
- Stiff
extreme temperature. This classification is based on the NLGI class which is a measure of penetration by a ball
in the grease when released from a certain height.
The most important properties of synthetic oils are the following:
- Added lubricity: the uniform diameters of molecules allows the molecules to slide Types of greases are normally determine by thickener type used and these are classified as
~ore easi~y over each other resulting in free and smooth movement. Thus synthetic conventional soap greases, complex soap greases or non-soap greases.
Oils are shcker than petroleum based oils resulting in much less wear moving parts
and better performance and cooling of moving parts. In selecting a grease for use considerations must be given to conditions and nature of use.
- Higher film strength: the strength that pushes away molecules from each other is The first thing to be decided is the consistency range. Next comes the operating
higher resulting in higher film strength. temperature. Use of greases is limited to very low speeds upto 2 mls. They find good use
- Good engine start-up properties: Synthetic oils begin lubricating at very low where sealing against dirt is sought or for intermittent low speed motions.
tempera~e and as such have good resistance to thickening at low temperatures.
- Go~d resistance to thinning: Molecular uniformity of synthetic oils gives them good Application of grease in machinery has their relative advantages and disadvantages over
resistance to thinning at high temperatures.
using oils. Advantages of using greases include the following:
- Improved energy efficiency: this is due to the added lubricity of the oils.
. Convenience: grease is easily retained where it is applied.
- Le~s sludge or deposit formation: synthetic oils contain more detergent additives _ Persistence: lubricating film is retained on surface during shutdown.
WhICh protects formation of sludge inside the moving parts. Protection: minimum leakage thus encouraging the formation of protective
- Good th~~al properties: synthetic oils have good low-temperature properties, i.e. coating against corrosion.
good fluidity at low temperatures and low pour point. They also possess good high _ Cleanliness: greases do not leak nor splash thus maintaining cleanliness of surfaces
temperature property of high flash point.
where they are applied.
- Stability: Synthetic oils are stable under extreme pressure and temperature.
The disadvantages of using grease are the following:
Good fire resisting properties. _ Poor cooling properties: greases do not dissipate heat generated easily.
_ Contamination: greases can easily get contaminated by dirt, wear debris, oxidation
Bec~use ofth~~rproperties, synthetic oils are used for high speed lubrication under extreme
products, etc.
loadmg conditions, _ Low speed of application: greases can not be applied where working speed are
over 2 mls.
However, synthetic oils have some disadvantages and these are:
- compatibility problem with paints, elastomers and certain metals'
- reactive
.' in the presence of water resulting' m h y dr 0 I'
YSIS an d corrosion;
' .
high potential for toxicity;
- disposal problem due to undegradable molecular structure'
more expensive. '
32 Maintenance of Machinery Fundamentals of the Theory of Damages 33
I
ineffective. Fluid lubricants are undesirable if they are liable to contaminate product as in SURVEY Separate cards
food machinery, electrical contacts, etc. Fluid lubricants are ineffective in hostile - Frequency CENTRAL preferable to give
- Grades RECORDS ease of records
environments, high temperatures, extreme pressures and fretting conditions. A common (Inventory )
- Plant description modification
type of solid lubricant is graphite. _ Application types
- Route order
The following are some properties of solidlubricants. - Time factors Sorting route,
- Workload PLANNING Workload
- Solid lubricants are incapable of carrying away heat.
- Accessibilty
- Solid lubricants are immobile and they must somehow be bonded to the surface.
- Solid lubricants are capable of retaining their lubricating effectiveness at high
temperatures.
ii Circulating lubrication \
There must be a circuit of lubricant without leakage. In this case all lubricating points
must be tight. This action is a continuous circuit where the lubricant is forced to flow Fig. 2.10 A model of planning for systematic ~ubrication
and the lubricating points are continuously supplied with lubricant. In the circulation
type, tank, admission, lubricating points, re-circulation are needed.
- moving parts like grind ways, screws, feed shafts should be lubricated ;
- oil level should be checked.
Periodically
3.1. Sliding Bearings
- oil reservoirs, containers of oil including systems should be cleaned and filled
I the damage in sliding bearings is wear plus fatigue. Static loads cause wear whereas
up to level; In genera , . . ti ulating
dynanuc. '10ads cause wear plus fatigue. Incases where lubricant ..contains corrosion-s
. t un . ,
- replacement of oil should be done. Topping up of oils should be discouraged
substances like acids produced by aging lubricant, water leaking m lubncant, e c., corrosion
as much as possible.
also becomes an important damage.
iv. Lubrication points should be marked differently for the working ease of operator.
In a shaft bushing system, normally, the bushing is designed as the desired element of f~ilure.
2.7. Fatigue But when dealing with damages of the system, the whole system has to be considered
especially with respect to
- alignment and shape of bush hole or bore,
Fatigue is the failure (or reduction in strength) of a material under fluctuating stresses,
- lubrication, and
which are repeated a very large number of times. Fatigue failure begins with a hair-line
- deformation of shaft under applied loads.
crack which develops at a point of discontinuity in the material (notches, groves, fillets, ... ).
Once a small crack develops, it propagates under load to cause failure.
3.1.1 Factors influencing damages of slide bearings
Typical slide bearing failures and their characteristics are outlined in the table below along with
their causes. The remedy for these failures is eliminating or reducing the causes for the failure
by proper lubrication, assembly, manufacture, operation and maintenance.
- Proper fits and tolerances should be provided (basic hole/basic shaft systems).
-- _welding a new shank at the end sections
3.2 Antifriction Bearings: (Roller and ball bearings): ii. Housing bore loose on shaft:
The bearing gets heated up.
Ball and roller bearings normally fail by fatigue. In the case of tightening and lubrication Corrections:
_ housing bore knurled (temporary);
problems, wear also can occur. Rarely failure can occur by random damages like overload.
_ installing a sleeve.
Bearing tracks and rolling elements are loaded with periodic reversed loads which cause iii. Bearing running dry
In the absence of lubrication bearing gets heated up.
fatigue of these elements. This loading condition causes cracks (which are detected only after
a long time) . The cracks develop to form pitting which in turn leads to abrasion of parts.
iv. Mis-alignment
High contact pressure causes damage of inner and outer races. In case of over load and
v. Damage of one or more balls/rollers
assembly problems failure takes place in a short time.
Wear of bearing elements increases axial and radial play, which can be a cause for vibration vi. Damage of running race
leading to increased fatigue. Continuation of lubricants causes abrasion Impact loads in
standstill produces chatter marks causing vibration. vii. Deformed separation
Due to one of these defects bearing runs with a continuous knocking sound.
Due to damages bearings will either get heated up or will run with abnormal noise and/or viii. Radial play
Radial play causes vibration of the system on which the bearing is mounted.
vibration.
- Heating can be felt by touching with hand. Correction> .
Angular contact bearings, taper roller bearings, and ball/roller bearings with conical-
- Abnormal noise can be detected by taking a rod ( screw driver oflength 200-300 mm)
bore can be corrected by tightening the regulating nuts.
and placing one end on the bearing housing and listening from the other end. A good
_ Other types have to be replaced.
bearing runs noiselessly, and a defective bearing will run with a continuous knocking or
rubbing sound.
3.2.2 Characteristics of rolling bearing damages
Rolling bearing defects can be anyone or combination of the following.
Rolling bearing damages as recognized by their operational behaviour are outlined as follows
i. Bearing inner race loose on shaft:
III Bearing running with such a defect gets heated up. in the table below.
I Correction: -
- Knurling of shaft (temporary repair only);
- chromium plating;
- metal deposition by welding
- installing of a sleeve
42 Maintenance of Machinery Typical Damages of Machine Parts 43
Table 3.3. Rolling Bearing damages and their operational behaviour 3.2.3 Typical damages of rolling bearings
2.2 Unequal noise: rattling, too big bearing clearance Characteristics Causes
- Bearing failure
scrabbling - damage on racing tracks - flaking with ripple pattern - fatigue due to repeated
Fatigue flake
(Pittings, troughenings, impressions) across the loaded part of the stressing
- contamination race
- too viscous lubricant
Atmospheric - numerous irregular pits with - exposure to moist conditions
2.3 Gradual change of noise - changing of effective bearing clearance (caused corrosion irregular bottom - insufficient grease
by change in temperature) - reddish brown or dark protection
- fast fatigue process brown in colour
- fast arising of impressions corrosion in
RoUer staining - formation of dark patches - bimetallic
3. High Temperature - too small bearing clearance on rolling surfaces and end storage
3.1 Overheating - insufficient lubricant faces of rollers - poor storage conditions
- excessive lubricant - insufficient cleaning during
3.2 Sudden increase in manufacturing
- lack of lubricant
temperature - fast arising of pittings - formation of dents or - rolling elements brought
Bruising
4. Difficulty in running - deformed bearing due to: (True brineling) grooves in the bearing track into violent contact with
4.1 Uniformly conforming to shape of race during assembly
• mounting failure
• use of strong seals rolling elements
• tight sealings False brinelling - depression in the tracks - vibration while the bearing
- too much lubricant (overfilling) ,. varying from shallow marks is stationary
- too viscous lubricant to deep cavities - small oscillating movement
4.2 Non-uniformly - contamination caused by large foreign material - depressions have roughened while under load
- limited local damage of tracks surfaces
Typical Damages of Machine Parts 45
44 Maintenance of Machinery
--------~----~~---------------------------
Fractured flange - pieces broken from the - bad fitting
--
smearing
_ discolouration of bearing - heavy loads
- poor lubrication
surfaces
inner race guiding flanges _ presence of abrasive
- dull working surfaces
- damage to cage and shields Abrasive wear particles in lubricant
Outer race fretting - a patchy discolouration of - insufficient interference _ presence of hard wear
the outer surface between race and housing particles
- presence of reddish brown - thin outer race _ lubricant failure on high
debris Molten cage ,
speed bearings
- cracks extending inward
from the fretted zone
Generally, the grease should not fill more than three-quarters of the total available free space
in the cover with the bearing packed full. For dirty environments with low to medium speeds,
- Maintenance of Machinery
the grease must completely fill bearing and cover. c. ilure occurs rarely. A gear pair has not failed until it can no longer be run. This
Gear lID 1 . h urred:
·on 1· s reached when anyone or both -of'the fol owmg as occ .
condit1 . . . .
When oils are applied to lubricate bearings, bath or splash system may be used for low speeds; one or more teeth have broken away preventmg transmission; .
oil flingers or drip-feed lubrication is used for low speeds; pressure circulating and oil mist teeth are so badly damaged.or worn-out that unacceptable vibration and norse are
systems are used for high speeds. set up when the gear runs.
During assembly of bearings, the following general procedures have to be followed. In gener al ,gear c.raiilures can be classified in one of the following. Surface
. fatigue (pitting)
Pits start forming on teeth contact surfaces with the runnmg of the gear.
i: Washing The cause is over stressing of gear material.
Before assembling a bearing unit, the bearing must be washed thoroughly with a mixture The remedy is removing the causes of over stressing.
or petrol and lubricating oil/or with kerosene and allowed to dry. After drying all bearing
surfaces are coated with a film of oil by dipping it in oil. ii: . Scuffing . .
- This is the result of disruption of the lubncant film.
ii Assembly The tooth surface are severely roughened and tom as a result of unchecked
A small bearing is mounted on the shaft by hammering its inner ring uniformly through a adhesive wear. ..
copper or a steel tube/pipe of bore slightly bigger than the shaft. Direct hammering on Cause is the rise of temp. for contacting surfaces above the critical temp. for the
bearings is not recommended. lubricant.
The remedy is to use high grade oils with high critical temperature.
Large bearings are installed on the shaft by heating bearing in an oil bath and slight
hammering where necessary. iii: Abrasive wear
During normal operation, if hard foreign material dimensionally. larger than the
iii. Two Radial bearings: film thickness in the range 1.00 - 0.6 um contaminates the lubncant, the tooth
Two radial bearings should be installed with axial clearances on the outer ring of one of surfaces are affected by abrasive wear.
the two bearings to allow for thermal expansion of the shaft. Working surfaces become dull and scratched in the direction of sli~ing ..
The remedy is protection of oils from contamination and preventmg dirt from
3.2.5 Storage of bearings entering in.
Bearings must be stored with packing materials on as otherwise moisture might cause
corrosion. ii Plastic deformation . . . .
With ductile materials, heavy loading exceeding the elastic limit, produces plastic
- Upright position may cause deformation of bearing rings, therefore, bearings must be
kept in a flat position. deformations.
The remedy is to avoid overloads.
v. Tooth breakage
If a whole tooth breaks away the gear has failed .
The cause of fracture has to be assessed for the future performance of the gear.
48 Maintenance of Machinery Typical Damages of Machine Parts 49
, e- • ,
Typical Damages of Machine Parts 51
50
b.
Maintenance of Machinery
a. - at the fracture the surface - sudden shock load - eliminate depends on the specific application. In general, greases are used for low speeds.
Brittle is rough or crystalline. which exceeds the causes of
fracture - usually more teeth are impact shock i. Functions of gear lubricants
affected. characteristics of the loading
- presence of hard material Lubricants applied to transmission gears have the following functions.
materials a. Lubrication: The lubricant is used as a medium for separating the moving surfaces
b. - broken tooth tips - excessive local - limit use to
thereby reducing friction and wear.
Tooth end loading caused by rated torque
and tip high transmitted - proper
b. Cooling: Lubricants applied, particularly in enclosed gearing, are used for cooling
loading torque, incorrect meshing and
meshing aliznment purpose in that they are used for dissipating heat generated.
c. Protection: Lubricants have important characteristics that protect the meshing parts
from corrosion.
52 Maintenance of Machinery
TypicalDamages of Machine Parts 53
d. Maintaining cleanliness: Lubricants flowing through
.
bin -
mes g parts remove Wear
-------------------------------~~----~~~-----------
3.3.4 Repair of transmission gears
debns and external contaminants thereby keeping the parts clean.
ap~lication ~f.lubricant to meshing gear teeth is preferably applied at the parting pair in ii. Bevel gears
which the oil IS used for cooling and at the same time d . The correct meshing of such gears is decided in the same way as for spur and
re uces amount of 011 at the next
engagement cycle. Types lubrication application for gears are the following. helical gears with 50% covered area.
observing the blue marks after several turns on the worm wheel.
Gap between gears can be checked by rotating a paper tape between the teeth. For normal ii) Friction lining
working gap, the paper will take the form of the teeth and will be torn at places.
Brakefiriction lining failures, their characteristics and causes
Table 3 ..7
Note: The most prolific sources of trouble in gear assembly are faulty lubrication and
misalignment. Both can be corrected if present, unless scuffing has occurred. 1 Beat spo mg -
. hard spots on drum resulting heat spotted metal.
in rapid lining wear member
3. 4 Damages of friction surfaces.
_ Randomly oriented cracks on - overheating of the
2. Crazing
the lining resulting in a high braking surface from
Friction surfaces of clutches and brakes usually fail by wear and/or deformation. The
rate of wear overloading
damage of the friction surfaces affects the performance and shortens the life of the _ overheating from brake,
component and in exceptional cases results in complete failure.
dragging
grooves formed on the - using new friction
3.4.1 Brake damages: 3. Scoring
frictional material in the line material against metal
of movement resulting in a member which need re-
In subsequent tables, damages of metal surfaces and friction lining of brakes will be grinding
reduction of life
discussed. - over heating caused by
4. Fade material degrades or flows at
the friction surface resulting excessive braking or
i) Metal surfaces brake dragging
in decreased and loss in
perfomlance
Table 3.6. Brake metal surface failures, their characteristics and causes unsuitable combination
5. Metal pickup metal plucked from the
Failure Characteristics causes mating member and of materials
1. Heat spotting - heat spotted areas with reddish - distortion causing heavily embedded in the lining
brown colour loaded contact on a small linings contact at ends only incorrect radiusing of
6. Grab
area noisy brake lining (fault in assembly)
- uncomfortable mating erratic performance
2. Crazing - randomly oriented cracks on - overheating excessive grooving and wear incorrect fitting of lining
7.
the rubbing surface of a - repeated stress cycling at preferential areas of lining to the shoe platform
mating component from comp. to tension surface
(heating and cooling)
3. Scoring - scratches of the rubbing path - too soft metal for the
in the line of movement friction material
- abrasive material
embedded in the lining
material
56 Maintenance of Machinery -
3.5. Seals
Table 3.8. Clutch failures, their characteristics and causes ii) Static seals
Sealing takes place between surfaces which do not move relative to each other.
Failure Characteristics Causes
iii) pseudo-static seals
1. Dishing - clutch plate distorted into a - lack of conformability Limited relative motion is possible at the sealing surfaces, or the seal itself allows
conical shape. - difference in limited motion; e.g. swivel couplings for pipes, flexible diaphragm.
- dragging of plates in temperatures over the
iv) Exclusion seals
disengaging the clutch. lining causing shrinkage, Devices to restrict access of dirt, etc., to a system, often used in conjunction with
2. Buckling - clutch plates become - lack of comformability
dynamic seals.
buckled into a wavy (inner areas hotter that
pattern. outer area causing
3.5.2 Characteristics of dynamic seals
- preferential heating occurs. shrinkage). The basic characteristics of dynamic seals, which are the main sealing items in moving
- thermal damage and machinery, are represented schematically in Fig. 3.2.
failure.
3. Material transfer - Friction material adhering - overheating. Contact seals Clearance seals ~
to opposing plate giving - unsuitable friction Surfaces loaded together Predetermined separation . I
Sealing interface I
rise to excessive wear. material. I
mw~
4. Bond failure - material parting at the - poor bonding. (i) (ii)
.% -----
Hydrodynamic operation Boundary lubrication
bond to the core plate - overheating, the high (normal loads, speed (high loads, low speed V/
causing loss in temp, affecting bonding and viscosities) low viscosities) ~
performance. agent.
~W~
5. Grooving
6. Distortion
- grooving of the facing
-
material on the line of
movement.
facings out of flatness
-
-
material transfer to
opposite plate.
unsuitable friction
I~:~"mn·lg~ m
FLUID MOLECULAR PRESET
giving rise to erratic clutch material. FILM FILM GAP
engagement.
(i) (ii)
t_L_ifi_e
Moderate Sealing interface
(a)
SEALING CONTACT
(O.2S-I.Onlml STATlON"RY
ROTATJIlG SHAFT GASKEt·· SEALING' HEAD
Fig. t, Rotarylip.u'
PISTON SEAL
Fig. 2. Fee•• u' ROD SEAL
PUMP ADJUSTMENT
HOUSING NUT
1'51 •
Fig. 4. Squsrs-b.clcad 'V' saals u pilSton and rod
5eels in • hydraulic cylinder .
lal lbl
FIg. 9. Matal baflows: (a) formed; (b) wflldad
-Seal motion irregular - Stick-slip phenomena - Higher or lower speed iii) Lip seals
Jerky
may avoid problem
. Vibration Table 3.11. Symptoms of lip seal damages, their causes and remedy
- Change fluid
temperature
- Change rubber Symptoms Cause Remedy
-Seal friction very high on - Static friction (time - Probably inevitable Rotating lip seals -Damaged lip -Remove cause of
starting
dependent) - Effect slowed by (during assembly) damage during assembly
- Excessive leakage
- softer rubber or more
viscous fluid - Lip cracked in places -Excessive speed -Improve lubrication
- Seal permanently deformed - Poor lubrication - Reduce environmental
-Permanent set (characteristic - Change rubber
- hot environment temperature
of rubbers) compound
- Consider using
alternative rubber
compound
- rubber
3.6 Shaft Failures
Typical Damages of Machine Parts 63
Shafts function in a wide ranging operation conditions which include Fatigue failure is an insidious because the stresses at which crack initiates and propagation
corrosive environments, take place are much lower than the nominal yield strength of the shaft material. These
stresses occur at stress raisers where the crack initiates. Some typical shaft features that act
high and low temperatures, and
as stress raisers are
abrasive environments.
comers, fillets, notches, etc.,
Moreover, shafts are subjected to various types of loading conditions and experience
key-ways, grooves, splines, etc.,
tension, compression, bending, torsion, or any combination of these loading' condition
s. press- or shrink-fits,
These loads can be stationary or may vary with time introducing. In addition, shafts are
subjected to vibratory stress conditions. Added to the service conditions, these load welding defects,
conditions are sources of shaft failures. The basic causes of shaft failures are wear, fatigue metallurgical defects introduced by metal working such as forging, machining,
and misalignment. heat treatment, etc.
3.6.1 Shaft failures due to wear Other service-related factors that are very important factors in fatigue initiation are damages
caused by corrosion and wear. These problems cause reduction in the cross section and/or
change of shape and local areas may be created which act as stress raisers.
Wear is a common cause of shaft failures. The wear process takes place by abrasive wear
mechanism which is followed by removal of material from the surface of the shaft.
Abrasive wear normally occurs due to hard particles of protuberances sliding along the Another service-related problem that results in fatigue crack is fretting where contact occurs
surface. Presence of foreign particles such as sand, dirt, metallic particles, wear debris in between journal and bearing. Fretting is a minute oscillatory tangential relative motion
lubricant also results in abrasive wear. Abrasive wear reduces shaft size and destroys commonly known as slip. Fretted surfaces show shallow pits filled with debris. Escape of
shape of the shaft and causes shaft failure. debris eventually results in loss of fit which aggravates the fretting process. And, debris
trapped may cause seizure of motion. Fretting initiates fatigue cracks over the fretted area
3.6.2 Fatigue failure ffil:dreduces fatigue strength appreciably.
?~~
of the more common causes of shaft failure is fatigue. Fatigue failures commonly
3.6.3 Shaft failures due to misalignment
imtiate at stress raisers. The mechanism of fatigue requires the simultaneous presence of
three things: Another common cause of shaft failures is misalignment. Misalignment can be introduced
there must be cyclic stresses on the shaft:, due to the following problems:
these stresses must be tensile in nature; and mismatching of mating parts,
there must be plastic strain. original assembly error of equipment,
any maintenance activity resulting in maintenance-induced alignment problems,
The process of fatigue is considered to consist of three stages: deflection or deformation of supporting components,
initial fatigue damage involving plastic' strains leading to crack initiation; deflection or deformation of the shaft itself.
crack propagation that continues to grow across the part until the remaining cross Misalignment imposes unexpected bending moments on journals which are responsible for
section of shaft becomes too weak to carry the imposed loads; and increasing cyclic stresses necessary for fatigue crack initiation. Misalignment also induces
vibratory motion which is a typical cause for development of cyclic stresses.
final and sudden fracture of the remaining cross section, due to overload.
64 Maintenance of Machinery
Other
Chapter 4
. shaft. failures which need attention from assembly ,or
operation and! . t enance
mam
points of VIew are the following. Determination of State of Damage
Accidental overload
Corrosion due to working environment The state of damage of a machinery or one of its elements is the undesired deviation from the
Creep stress rapture required state fixed in the design procedures. Knowledge of the state of damage of a
component in connection with the determination of the survival probability is essential for
Brittle fracture
settingthe date and kind of maintenance measures to be taken. For the phase of testing of new
Bearing failures
components or equipment (means of production), knowledge of the state of damage provides
Metallurgical and manufacturing defects a collection of data ~ information about the state of damage, which in turn can be used for
Fits and tolerances between shaft and hub setting meaningful maintenance routines.
Hydrogen embrittlement
Excessive belt tension, overload. :7{ e state of damage of an equipment depends on
_kind and conditions of damage, and
3.6.5 Remedies of shaft failures _duration of operation of equipment.
•.~ -----
These measured quantities can be absolute or related to duration of operation.
Absolute measurement gives the amount wear as an average worn out thickness.
crack detection;
leak detection;
Related measurement gives amount of wear per unit time of operation. vibration testing ;
corrosion monitoring.
Direct measurement gives dimensions of parts. If the wear is not constant over a surface, the
measurement should be done in different planes with different orientations. Direct 4.4 Condition Monitoring Techniques
measurement is usually done after disassembly. But it can also be made without disassembling
provided there is easy access to the measured qua~ti!ies. Most failures give some warning before they occur. This warning is called potential failure.
.••... ----- Potential failure is defined as an identifiable physical condition which indicates that a
4.1.2 Indirect measuring quantities functional failure is either about to occur or it is in the process of occurring; this is indicated
as point P on the P-F diagram. A functional failure is defined as the inability of an equipment
During the operation of a machine or parts of it, certain signals are produced which are related in meeting a specified performance standard; this is represented by point F on the P-F diagr~.
to the state of operation of the machine. These signals, which are known as the diagnostic Techniques of detecting potential failures are known as on-condition maintenance tasks. This
parameters, if properly analyzed provide some information regarding the state of the machine. -isso because equipment is left in service on the condition that they meet specified performance
It should be noted that influence from the environment introduces errors in the measured standards.
results.
68 Maintenance of Machinery
point where
-----=.:::_~~~~/- - - - -+----
Deviation for ~
I Deviationfor ~
Component has ~
failed I
~ ~~FL_:(Functional Failure) i
lime ! L~~~nterval
Fig.4.2 The P-F diagram I
~_~~ interval
'----" - F interval As can be observed from the P-F intervals shown in the figure, the deviation for P,. from the
o-J
I normal is smaller and this requires sensitive monitoring techniques and equipment. But gives
p a longer P,. - F interval. The larger deviation for P.z from normal results in a shorter
~ - F interval. But the monitoring equipment/techniques need not be as sensitive as in the p,.
case.
From the above discussion it can be concluded that the P-F curve is an important tool in
time
determining the condition monitoring techniques and setting the equipment for conducting the
Fig.4.3 The P-F interval
monitoring task.
--
70 Maintenance of Machinery
beloW.
Atomic emission spectroscopy
Condition monitoring technique~ are designed to detect specific symptoms which are related
X-ray fluorescence spectroscopy
to the state of damage. of the equipment. The monitoring techniques are classified according
Infrared spectroscopy
to the symptoms monitored. These can be classified as follows.
Electro-chemical corrosion monitoring
Exhaust emission analyzers
v 4.6.1 Dynamic Monitoring
Colour indicator titration
Dynamic monitoring detects potential failures which cause emission of abnormal ener
in the.form of waves such as vibration and noise. Equipment which contain moving p!
4.6.4 Physical Effects Monitoring
that vibrate are monitored dynamically. This is done by measuring how much the system Physical effects monitoring includes changes in the physical appearance or structure 0)
vibrates. equipment which can be detected directly. The monitoring techniques involved detect
There are various techniques that belong to this category, examples of which are: potential failures in the form of cracks, wear, corrosion, etc. Some of the techniques
employed are:
broad band vibration analysis
Liquid dye penetrants
(changes in vibration characteristics are monitored)
Magnetic particle inspection
constant bandwidth analysis
Ultrasonic techniques
(changes in vibration characteristics are monitored by using accelerometers)
X-ray radiography
real time analysis
Light probes
(measurement of vibrational signals; shock analysis)
Deep-probe endoscope
ultrasonic analysis
Oil odor
(changes in sound pattern are monitored)
Strain gauge
Viscosity monitoring
J 4.6.2 Particle Monitoring
Particle monitoring detects potential failures which cause particles of different sizes and
4.6.5 Temperature Monitoring
~hapes to be released into the environment in which the component is operating. These These techniques look for potential failures which cause rise in temperature of an
mclude wear particles and corrosion particles. Among the various particle monitoring
equipment itself. Monitoring techniques included in here, among others, are:
techniques the following are some examples.
Infrared scanning
Ferrography
Temperature indicating painting
(Wear and corrosion particles are monitored by taking a representative sample of oil)
Real time ferromagnetic sensors
4.6.6 Electrical Effects Monitoring
Graded filtration
These techniques look for changes in r<:.sistance,conductivity, etc. Electrical Effects
Sedimentation
Monitoring techniques includes the following.
Electrical resistance monitoring
J 4.6.3 Chemical Monitoring
Chemical monitoring detects potential failures which cause traceable quantities of chemical
Determination of State of Damage 73
72 Maintenance of Machinery
Potential monitoring ---darkened colour of oil is caused by oxidation of oil, excess temperature, combustion
Power factor testing or other chemical products reacting with the oil used.
Breaker timing testing
.. . that can be detected by lubricant monitoring are the following.
MalfunctIOns .'
4.7 General Purpose monitoring techniques damages of transmission components like gears,
__ shafts, beanngs, etc.
blockage of ducts, pipes, etc.
Thermal, lubricant and vibration monitoring techniques are considered to be general purpose
monitoring techniques. In each of these three techniques, the parameter being monitored . 7 2 Thermal monitoring
contains information that has been transmitted through the machine. 4. .. . the temperature of a component in a machine is undertaken for one of three
Monttonng
4.7.1 Lubricant monitoring p~~se;~ enable the t.e~p. of a process to be controlled ~l1y, or to check that it is being
The oil which circulates through a machine carries with it evidence of the condition of parts controlled properly; .'
encountered. Examination of the oil and any particles it has carried with it allows monitoring To detect an increase in heat generation due to some malfunction such as damage of
11.
of the machine on-load or at shut-down. bearings; .
11 T~ detect a change in the heat transmitted through and out of the body of the machl~e
Lubricant examination can cover debris deposited, debris in suspension or condition of oil. caused by a change in some component such as failed coolant circulation or ash build
up in a boiler.
Debris deposited are the larger particles carried along by the lubricant which can be collected
by filters or magnetic c~liectors. Examination ofthe debris under the microscope to establish Temperature monitoring can be carried out at a point within the body of the plant (~g.
size and shape provides a good information regarding the state of damage of the machine. measurement of water temperature in a boiler) or at the surface of a component (eg. beanng
housing). Temperature monitoring devices are diverse and can be classified as contact sensors,
Debris in suspension are the smaller particles collected by the lubricant which remain in non-contact sensors temperature points, pellets (pyrometers), etc.
suspension. The examination of the debris in suspension gives the earliest warning of
component damage. A wide range of malfunctions are monitored thermally. Prime function of t~~perature
monitoring is checking the system that the controls are working properly. In.additIOn, s~me
A change in the rate of debris collection indicates the change in the condition of the machine range of general faults can also be detected by thermal monitoring. The followmg are possible
as related to wearing out. Shape of debris collected carries information as to the wear areas where thermal monitoring is applied.
mechanism taking place. Bearing damages which result in heat generation and heating of the bearing unit and
r
') - Normal shape of wear particles tends to be flat; other units that come in contact with the bearing unit.
\ -_ cutting or abrasive wear results in spiral shaped debris; Failure of coolant or lubrication can be detected by a temperature rise of appropriate
Lsurface fatigue failures produce larger angular particles. bodies', such failures could result from pump failure, drive fault, blockage in piping,
valves or filter, or damaged heat exchanger.
Condiiion of used oil itself can be examined for indication of other malfunctions. To mention Incorrect heat generation like in internal combustion engines.
a example: Build-up of unwanted materials such as sediment is pipes, ash in boilers or ducts, etc.
foaming of oil - cause is excessive churning or passage under pressure through Damage of insulating materials.
restriction. Action to be taken: checking the system. Faults of electric components.
74 Maintenance of Machinery
Changes in noise or vibration characteristics are indicative of trouble. The causes ofvibrati
-
Table 4.1. General purpose mom ortng techniques
are unbalanced rotating and reciprocating parts, looseness in the fit between componen~
deflection of load carrying members, misalignment, damages in transmission components, etc, Thermal Lubricant Vibration
I--
Medium for -solids: casing, shaft, -oil used for lubrication -any solid par of
Vibration monitoring is generally used in preference to noise monitoring. The equiPllle~ transmission of etc. and! or oil machine
employed are vibrometers and accelerometers of wide variety. -Liquids: lubricant,
information
through cooling water or oil Depends on lubricant Depends on elastic a
Yrhe possible faults that can be detected by vibration monitoring are: machine being pumped round mass characteristics of
!-- wear or failure
I
of bearings; Depends on thermal the machine solids
" presence of unbalance in moving parts; conductivity
\ - changes in clearances; -Components any heat generating any component which any component that
~ - cracks in shafts and other moving components subjected to cyclic loads. monitored device such as is lubricated such as moves
. - condition of bearings - bearings, pumps - surface between
The table below discusses in brief the general purpose monitoring techniques showing the - fluid flow in heat - transmission components with
exchangers components relative motion
medium for transmission, components monitored, faults that can be detected and equipment
required for monitoring. - lubricants - clearances
Faults detected - failure of drives -any form of wear or change in any moving
- blockage of ducts failure that results in component
:
- loss of cooling, lubricated surface - wear or failure of ,!
fouling of coolers failure bearings i
,
- overuse -leakage of other - unbalance ,
contaminants in to - changes in clearances i
I
lubricant j
I
Monitoring - thermometers -on load removable -accelerometer and I
-pressure gages
j
Frequency - Continuous and - Primarily periodic - Periodic put also
I
,
periodic continuous :
Maintenance of Machinery
environment should be given due attention. Accessories like water jet, steam jet or
In applying lubricants, taking good care of filters is of great importance. The task of filters
The fundamentals for the use of any technoica I means of production are' is to separate wear products and contaminants from the lubricant to reduce wear process.
proper use of operating instruction provided im operators manuals'.
Different types of oil filters, air filters, restrainers can be used.
proper
c. II .use of service instructions given in se rvice
.. instructions:
. and'
~o .owmg prop er maintenance
. procedures and . tru . '
maintenance manuals. ins ctions as outlined in S.3 R pair
Repair is the totality of measures of restoration with the aim of determined final state, or
Kno~ledge of these instructions is essential is attendin the .
quahfication of operators maint g machine. In this respect quality, or condition of equipment.
, enance personnel and man .
Proper attendance avoids subjective d . . . agement IS a requirement.
amages and rrnrurmzes objective damages. Classification of repair activities is based on various considerations. These considerations
For cleaning purposes detergents can be used, but compatibility with the workinz
'"
Kinds of Repair
~---- __l _
Preventive
Corrective
(Restoration)
Time related to Chapter 6
breakdown
Decision Making
,-----L _
of a system involved range in importance from a major equipment replacement to minor repair option.
Decision making is directed at the objectives, organizational structure and actions of the
Medium Repair maintenance function.
(One or Several Elements) General Overhaul
(Nearly All Elements) Number of elements
of a system involved
AA decision problem exists when:
I
Minimum Repair
'tj - there is a desired objective,
Emergency repair
- at least two courses of action are available,
I
Exchange Repair Assembling of already
- there is uncertainty as to which course is the best, and
repaired elements / - external factors are present which can affect the outcome and which are outside
the control of the decision maker.
Single Repair
Repair in Series Influencing factors in decision making and in identification ofthe most suitable action
are the following:
- Cause of failure
Decentralized
»o - Failure incidence with respect to time
Centralized
Territorial
J - Costs of maintenance or re-design
------ __ 1 _ Maintainability
Manual In decision making, in place of forwarding decision rules it is always of primary importance
Industrial Division and type
to keep the maintenance objective clear, and information systems clearly designed and
of labour involved
Fig. 5.1 Classification of repair understood. This is so, because maintenance tasks that require decisions at various levels
are diverse in nature, and each task may have many alternatives.
The flow chart shown in Fig. 6.1 demonstrates a decision making procedure, in general.
80 Maintenance of Machinery
Maintenance Decision Making 81
----------------------------------------~~~~~~~----------~---=
L
I fdentit: ~e e~stence of a
decIsIOn situation
I
In applying a decision making procedure in maintenance, there are a few important
questions that need to be answered. Moubray', has explicitly stated these questions as
I Identi~ the real problem and 1
l the mfluencing factors I follows.
In what ways does each failure matter?
What can be done to prevent each failure?
Classify the influencing factors What should be done if a suitable preventive task cannot be found?
into
i) those that are within the
decision maker's control In answering these questions, a maintenance decision procedure should take the following
and those that are not issues into consideration:
j
Make a
DECISION
based on the forecast
and allowing for the
non-quantifiable factors
n ;>-.
; """"'-- ~ .- tr: '" <1.! .-
•.- - § tl ~ .:l
Q)
''-; 0;
"'" Q., '"dQ)", '" ;>-.;j
~
Q.,=
~ '>:E'
:.s0o..
~ Q)
S s z'5
Vl
~ UO .S
Q)"-<
J3 ~ P
~;j
~ ...;
-S"5
U >,
•••..•..• .J:: 0
Q).p 0 0
Q) .-
;jQ) '"
•••• '"dS:.s .- SI-<
::: ~ 0 ~ ~ "en ~
.c
~ ":-"-<0
'" 0 '"
'" 5.:l Q)
(J.l. ~
- "" ~ 0 H 0 0.. 0
'0 "'0...,S 0.. 0..
I "'" «:I;j;j '"d «:1;>-'
. ~ 1l ~ .S! § -;, §
CJ ~ ~ ~ e-, ~ •....• ~
•••• «:ISo.. Q) '" P-o
~~
.~.g°P«:I
<.Q
~
:=:
8g ~ 8. g
~Q)
~
'" 0 "'.;>-. '" E ~ .•..• Q) ""'''' ;:.
t> ~ ".0 'E::::: ~ 0 ::::, ~ 0 ~ "'''' ~
.~.-
.D' 0
~ ~
•••
~
~;>-.
Q).
E
o ~
-.
'" § ..-
;:. «:I 0
-,-,
-,"
~
;:.
o 0 ~ Q) g' .D 0 S It ~ 0 0 'r;:;
,,-<<t:.:l§ ,,-<P 00 ~;>-.O ;:!
o o.:i .i!l 0 ~ S ~ ~ .- .8 .8 1:1 U
1l .•.......
P .•.• -
o ~s:: tf)...-
•...r;:::
;j.- Q)
U'J
en -
O.D
(l)'{ii....
rIl
'" ~
"
C
~
-.'-l ._ §
.•..•.•..• 0
"-< rJ'J.
~
~
, o
Q)~,,-<
!:: ~ 13 (l)'~
-Q)
{lHo..0 ~
\;:;
i" ~ ?:,..o Q) ~ :::::
<::s
::::: -. 0 '" 0 - ;:l "-< 0 " ;:.... 'c;; •.•
, 0 ~ ......; ~ ~ 0 0 B c.... ::::: ;j U s::
0
;s;:!
o Q) «:I ? I-< ;>"';j '"d <::s U ~ .... "'"
'"d~15~ «:I;j ~] 0 s:: !l.c ~ 0..'" ~
Q)o;;j? 2 4-<8;>-' cd =;:! Q) ~
,S 0 '" Q) S (Ii 0::s P 4. ~ !:: ;>-. ~;j _ '""
--
~
I
Q)
ii:l ~.;::::
.•••• E-oO"
Q) '" 0
<.t::
t;.:i
Q)
H
]
•••
8
c
cd
"-<
0
"
-.
It
~
••
6
~'..:::,::Sl-<o
-;j
0; ~
'"
~
,"
•.•• t-:
ell
•
•••
ti .£
Q)
-e 0
~ a
Q)
"-< 0
0 B
~~
,,<110
a
"-< VI eo
-i-;'"
= s::
.0
:0
Cd
Q)
o
d ;>
.••••
5
~ .D .cd Q);j --. 0 d 4.. =..::: '" ~Q) Q)
d~Oii:l 00 Q) 0 'il c.... ::I~~ (l)
\;:;.J::",-
Q) .•••• ...;j
0"-<
cd 0
eo
0
.••..
~
-;~«lo;>
'<!" ~ '" o '{ii
-B i:!
~
S .~ ~
.s .g
.i!l 'Q$.g
.8
a
«:I
,g:p,
E-o
'Q$
~
]
E-o
.E
E-o
uf ~
~
e-
'-.:- dOE
&~ ~ (l)
I
~ l!!. Will Ibe /0" oUuRd/OR ~ Does 'he (al/ure mode l!.. Do••• he f.llu~, mode .au e l2... Does 'he .• 1use mode
caused by thIS failure mod y cause a loss of function N a loss offunchonor other N bave a direct adverse N
on its own become eviden es or other damage which ~ damage which ~ould brea 0 effect ~~ operational . 0
to the operating crew und~ could hurt or kill any known environmental capability (output, quahty
normal circumstances? someone? standard or regulation? other non·repalr costs )?
SCbed~led
oD~nditioD task
I SChedluled
on-condition task
I SChed~led
on-condition task
I SChed~led
on-condition task
I
~ Is a scheduled restor.ation ~ Is a scheduled restoration ~ Is a scheduled restoratio ~ Is a scheduled restoration
task to reduce the failure task to avoid failures task to reduce the failure task to reduce the failure
rate technically f~asible technically feasible rate technically feasible rate technically feasible
and worth domg? and worth doing? and worth doing? and worth doing?
SChed~led
on-condition task
I SChed~led
restoration task
I SChed~led
restoration task
I SChed~led I
r.res=IOrr-:a,-ti_on-,la,-s..,k:-:--:-:-:-_-:-,-,
~ Is a scheduled discard ~ Is a scheduled discard ~ Is a scheduled discard ~ Is a scheduled discard
task to reduce the failure task to avoid failures task to reduce the failure task to reduce the failure
rate technically feasible technically feasible r ate technically feasible rate technically feasible
and worth doing? and worth doing? and worth doing? and worth doing'!
Yes I No Yes I No Yes I No Yes No
- I
Scheduled I I.
Scheduled I I
Scheduled I
No scheduled I
Scheduled I
No scheduled
on-condition task discard task discard task maintenance discard task maintenance
.5
~ ~ Is a failure-finding task to
detect the filure technically
~ Is a combination of tasks
to avoid failures technicall .
I I
.
.;:: feasible and worth doing? feasible and worth doing? Redesign may Redesign may
<.,) be desirable be desirable
::§~ Yes I No Yes I No
Probability of drawing 11 is Pc', = 3~ a) What is the probability that the rivet will have type A defect or type B defect, or both?
b) What is the probability that the rivet will have type B defect or type C defect, or both?
r.E,arE, =2
36 c) What is the probability that the rivet will have no defect?
Solution
7.2 Not-Mutually Exclusive Events:
(Addition Theorem)
Probability of type A defect is P(A) = 0.060
Probability of type B defect is P(B) = 0,035
When event EI or event E2 or both can occ .
exclusive events i e when I ur sImultaneously, we have not mutually Probability of type C defect is P(C) = 0,015
. . . severa events are involved, at least one of the events will occur. Probability of type A and type B defect is P(A nB) = 0.008
Probability of type A and type C defect is P (A n C) = 0.006
Probability of type B and type C defect is P(B nC) = 0.003
Probability of type A, type B and type C defect is P(A nB nC) = 0.002
a) Probability that the rivet will have type A detect or type B defect is
b) Probability that the rivet will have type B defect or type C defect is -
7.4 Conditional Probability:
Basic Probability Concepts 87
(Multiplication Theorem)
P(B uC) = P(B) + P(C) - P(B nC)
Event E2 is said to be conditional on event E1 when the probability of occurrence of E2
P(B uC) = 0.035) + 0.015 - 0.003 = .0497 depends on the prior occurrence of E,. The probability that E2 will occur provided E, has
occurred is denoted by PE 1E,
2
, which is read as "P of E2 given E, ". Here, the
c) Probability that the rivet will have no defect is
possible events are those in E1' and the favourable events are those in E2 which are also in
P(atleastonedefect) = 0.060 + 0.035 + 0.015 The probability that both events will occur is
- 0.008 -0.006 - 0.003 + 0.002 = 0.095 PE, and E, = PE, X PE,I E,
PE, and E,
= FE
z
X PEIE
"
P(no defect) = 1 - 0.095 = 0.905
Event E1 is said to be independent on event E2 if the probability of occurrence of E1 is not good; one unit in the second is good; both units in the third are bad. A technician selects
affected by the occurrence or nonoccurrence of E2• a box and a unit from it at random. A test check shows that the unit is good.
a) What is the probability that the second unit in the same box is also good?
The probability that both events will occur in a trial for independent events E1 and E2 is b) What is the probability that the second unit in the same box is bad?
PE andE2 = FE J X P'E2
Solution
I
a) Having selected a box with one good unit, the probability of selecting the box with the
Example 7.3
other good unit is ~, for there are only two boxes that contain at least one good unit.
Three identical, independent machines are connected in series. The probability of survival
Having selected a box with one good unit, the probability of selecting the box with the
of each machine is 0.98 for 1000 h of operation. What is the probability that failure will other bad unit is 1/3.
not occur in the arrangement for 1000 h of operation?
Hence, having selected the box with one good unit, the probability of selecting thebox
Solution
with the other good unit is
PE, and s, and E, = 0.98 x 0.98 x 0.98 = 0.94
P (good unit/prevous selection good) = ( ~) + ( 1) x~
2
3
b)
P (good unit/prevo us selection bad) = ( ~) x ~ = ~
3 2 6
88 Maintenance of Machinery
0.375 ----1-1
7.5.1 Discrete probability distributions
I I
I I
When the events are discrete, i.e. when countable number of values are assigned to th 0-125 -i-I--\---I
results ~~ a ~an~om.experiment, the probability distribution is referred to as discret: I
p~obabllzty distribution. Examples of such distribution include: flipping a coin, rolling a 2 3
Number of tails
dice where the number of events are finite.
As can be noted from the example above, the probability distribution is discrete in which
Example 7.5 the outcome of the random event is flipping a 0, 1, 2, or 3 tails, nothing in between.
Determine the probability of obtaining at least one tail when flipping three coins
i. Binomial probability distribution
simultaneously.
The binomial experiment is any experiment that can be regarded as a sequence of n trials
Solution
in which:
i) n is defined before the experiment begins;
Let p be the probability of flipping a head and the q be the probability of flipping a tail.
Therefore, ii) the result of every trial can be classified into one of two mutually exclusive
categories, success and failure;
p=0.5, q=0.5
iii) the result of any trial is independent of the results of other trials; and
The possible outcomes and their probabilities are shown in the table below.
iv) the probability of success p does not change from trial to trial.
Possible Outcomes Probability
H H H 0.125 The binomial probability distribution is obtained from the binomial expansion which is
H H T 0.125
given by
H T H 0.125
H T T
T H H
0.125
0.125
(x +v)" =xn +(~)xn-ly +_ .. +(:)Xn-kyk +--- +yn
T H T 0.125
T T H 0.125 The n-k coefficient, denoted by (:) is given by
T T T 0.125
Total 1.000
( n)k = k!
n!
(n -k)!
. 90 Maintenance of Machinery
-- d dr . g a black one be failure. The probability
. king a white marble be success an awm
The binomial distribution is applied to problems where the probability of occurrence P and. Let pIC .
probability of non-occurrence q are unchanged by drawing from the sample. . king a white marble is then glVenby
of pIC
Example 7.6
Number of white marbles
Chances in 1000 tries
Suppose that we have ajar with three white and seven black marbles. While blindfolded in one draw
we draw three marbles, one at a time, replacing each marble in the jar before drawing the 27 chances to win $3
3
next and win $1.0 for each white marble. How many chances in 1000 tries are there of 189 chances to win $2
2
winning 0, 1, 2, or 3 dollars? 441 chances to win $1
1
343 chances to win $0
o
Solution
This problem can be solved by using the binomial theorem:
The possible outcomes are represented below.
p = n! pr(J _py-r
(r,n,p) (n - r)!r!
OW,3B and win $0
lW,2B and win $1
2W,IB and win $2 where n =3, p = 0.3 and r, number of occurrences, is 3, 2, 1 or O.
3W,OB and win $3
92 Maintenance of Machinery
-
Basic Probability Concepts 93
The probabiiity for three succe~s r = 3 is
For draws in replacement, this is:
P(3,3,0.3) =
3'
O!~!0.33(0.7)° = 0.027 (2.x~)
10 10
+ (~x 2.)= 04200
10 10 .
2(07) The multinomial distribution is a generalization of the binomial distribution in which the
P(2,3,0.3) = 20.3
Il2! .
- 0 189
-. occurrence or non-occurrence of an event can take place in more than two ways. For
instance, in considering an operating unit, it may malfunction in more than two ways. Such
The probability for r = 1 is cases are easily handled by using the multinomial distribution.
31
P(1,3,OJ) = _. 0.3 (07)2 - 0441
2!1! . -. Let n be the number of independent trials, in, each of which only one of the events E J '
E2,··,Em can occur. Let the probabilities of these events be Pt> P2' , Pm. The
The probability for r = 0 is probability that EJ will occur is kJ times, that E2 will occur is k2 times, , that Em will
3!
occur is km times in n trials is given by
P(0,3,0.3) =: 310!(0.3)°(0.7)3 =: 0.343
Note: In thi
s example the process is called drawing items with 1
I rep acement.
iii) The Poisson distribution:
Drawing Samples Without Replacement:
In the previous exam 1 ifth In applying the Poisson distribution, events are assumed likely to occur in a continuum of
p e, I e random experiment is drawi .
the probability of drawin hi mg marbles WIthoutreplacement time, length, volume, etc. The Poisson distribution, unlike the binomial distribution, is
g a w te marble will vary with h. '
on the outcome of the previous dr F I eac SuccesSIvedraw depending used to deal with events in which the value of n is not known before the experiment begins.
. aw. or example the ch fd .
white marbles is expressed as: ,ance 0 rawmg thee successive
In deriving the Poisson distribution knowledge of the expected or average number of
occurrences 0 f an event IS
. require
. d . Let the expected number of occurrences of an event be
p _ 1 2 1
three white -- X - X - c: 0.0083
10 9 8 Q. The expected number of occurrences Q can be evaluated as follows from the probability
of an occurrence.
The probability of drawing one white marble and one black in 2 tri .
nes IS:
If the probability of an occurrence is P and the sample size is n, then the expected number
of occurrences is
a = np.
Basic Probability Concepts 95
94 Maintenance of Machinery
~e -a = (At) k e -It
a = np = 50 x 0.1 = 5. Probability of k occurrence k! k!
Like the binomial distribution, Poisson distribution consists of a number of probability tive poisson distribution, i.e. the probability of k or fewer occurrences is given
ThecumU la
terms that sum up to 1.000.
by
X2 3 k a i
x
eX = 1 +x +- + + ... P = E-e-a
2! 3! f i~O if
b bility of k or fewer failures
e" e ° -x = 1 . bility calculations with constant failure rate A, th e pro a 1 1
Forre 1ia 11
x2 3 is given by
or, e -xl 1 +x +-
2!
+
x
3!
+ ...J = 1
i (Atr -A[
P
f
= --e
./
i~O I.
Hence,
x2 3 Example 7.7
e -x + x'e -x + _oe-x +
x
-'e
-x
+ ... = 1
2! 3! - 0 5 h t is the probability of zero
lfthe expected number of occurrences of an event a - . ,.w h b bility of up to 2
In reliability considerations, the event is failure and the average number of failures in time 1 2 3 urrences? What 1S t e pro a 1 1
occurrences of the event; , , occ .
t is At for a constant failure rate A. Thus, the expected number of failures in time t is occurrences?
a = At.
Solution
Substituting a for x, a being the expected number of occurrences of ~ event, we get the
following distribution. Po = e -a = e -{).5 ,~0.6065
For 0 occurrences
e -a + a'e -a +
a2
-'e -a +
a3
-'e -a + ...
ak
-'e -a + .... = 1 PI = ae -a = (0.5)e -{)5 = 0.3033
For 1 occurrence
2! 3! k!
= (0.5f e -{)5 = 0.0758
Each Poisson term represents a probability of an occurrence. For 2 occurrences 2!
= (0.5)3 e -{)5 = 0.0126
Probability of the occurrence of Event Poisson term for 3 occurrences 3!
a2 (At)2
Probability of 2 occurrence _e-a -_ --e -At
2! 2!
96 Maintenance of Machinery
The normal curve has the bell shape shown in Fig. 7.3. The area under the curve is 1.0.
Solution
The mid-point u, the mean of the population, occurs under the highest point on the curve.
The number of expected failures is
Sincethe total area under the curve represents all possible events, portions of the area under
the curve represent the relative frequency of events falling within this portion. In
a = A.t = 0.0065x100 = 0.65
determining the significant portions of the area under the normal curve, the standard
deviation (0) is used, which is a measure of the deviation of the data from the mean. The
The probability that no failure will occur is given by the first Poisson term
standard deviation is determined for two cases.
Po = e -a
a2
= e -a + ae -a + -e -a
2!
= 0.972
P>2 = 0.028
a. When grouping is not feasible
Or, the probability that the equipment will function for 8400 h or more without failure is
Z-Scale
6.68%.
Example 7.9
c) The probability that the equipment will operate without failure for more than 3900
Solution
A certain Amplifier company purchases transformers for a medium-power amplifies from
a Transformer company. The amplifiers require transformers whose excitation current must
a) Using the Z-scale associated with t = 8400 h fall between 150 and 225 mA. The Amplifier company uses a statistical sampling scheme
,
Which assures that a lot which is 3% or more defective will in 9 out of 10 cases be rejected.
Before shipping a lot of 280 transformers, the inspection department at the transformer
where» := 1J20 hand t- = 6720 h Company selected 32 transformers at random from production and recorded the following
~ --,e~xcitatinn l'l1M"<>nt~ ;~ _ A
200 160 210 175 ]95 205 190 205
-
from tables: area between 0 and z, = 0.4857
area between 0 and Z2= 0.4726
LJaSICrrooaonllY cOnc:ep~3' II] 1'------
155 184 202 180 200 154 Total area between Z1 and Z2 is 0.9583
190 192
170 172 164 178 180 157 198 222
180 178 Therefore, 95.83% of the 280 transformers or nearly 268 transformers will fall within the
176 165 175 190 211 212 limit of 150-225 mA and 12 transformers are likely to be outside these limits. i.e the
Based on these readings is the sam Iin . percentage of defects is
transformers? p g scheme hkely to accept or reject the lot of 280
percent defects = ~ x 100% = 4.3% :> 3%
280
Solution
Thus, the probability of rejection of the lot of 280 transformers is 90%.
This problem falls under the catego h '.
deviation is given by ry were groupmg ISnot feasible. Hence the standard ii, The negative exponential probability density function (pdj)
a == j! (X-i)2
n-l
A given item is likely to fail in a given time shortly after installation as in a given time
many months latter. The item is always 'as good as new'. The cause of failure is external
~ to the item. In this case, the pdf of time to failure is given by the negative exponential
probability density function
x
- =-;;-=)2=
Lx 5920 185mA !(t) = A. exp( - A.t)
a == j! n-l
xl {i03T8
(x -
=V~ == 18.25 hyper-exponential pdf
Z; =~ _ ]20 - 185
- (J - 18.25 = - 1.92
Fig. 7.4 Negative exponential hyper-exponential probability
density function
The probability of failure in time interval fr
Withmany types of equipment, the probability of failure is found to be much higher during
The reliability, or the probability of survival for time tis theperiod following installation than during the useful life. This pdf exhibits two phases:
_an initial rapid exponential fall, and
R(t) = J -F(t) _a later slower exponential fall.
Or,
R(t) = e -(J.I)
This is given by the hyper-exponential pdf
A device has a failure rate of 05% f '1 This is a useful semi-empirical expression developed by W.Weibull for use in his studies
c. . . 0 ill ures per J000h. What is th l' bili .
lor an operatmg period of 500h? Ifth . ere ra I ity of the deVIce of the strengths of steel. Its usefulness to R and M lies in its providing the following
. ere are J000 Items . .
are expected in 500h? in operation, how many failures
advantages.
Solution
1. A single probability distribution can be made to represent any of the three types
ofp.d.j of times- to-failure.
2. Meaningful parameters of the failure pattern, such as the probable minimum time
= 5 jailureslJ06h = 5 x10-6jailureslh
to failure,
3. Simple graphical techniques for its practical application.
• \ I
For an operating time of 500h the probab'l'ty . a. Derivation of the Weibull Probability Distribution Function
• :I•.•.••• ~.,o.~>kJtlU~" ' 1I IS
/ ~ ~_l_,:,:",~~"'-_ ...\ .
'. -: <R(t), =; e -5,IIr"x500 = 0.9975 Consider n links which together form a chain.
For an individual chain link, the probability of fai lure F(x) under a load x must be of the
form shown in the figure. The failure probability increases as the load increases. For zero
The number of expected failures for 500h is load,the failure probability is 0, and with increasing load, the failure probability approaches
1.000. This is shown in Fig. 7.5 where for increasing x the value ofF(x) approaches unity.
.---
F(x)
where N is the total number of devices
H.r is the number of failed devices and
Ns is the number of devices that h~ve survived.
Ns = NXR(t) = 1000 x 0.9975 = 9975
where ¢ (x) , which is some function of the load, determines the precise shape.
Rn(x) = [exp( -¢(x))f = exp( -n¢(x)) In applying the Weibull probability function to maintenance situation, the stressing agent
is not load but running time t, since new or since last overhaul. Therefore, the failure and
and the probability of failure for the chain of n links is survival probability distributions are, respectively,
Weibull suggested the form the first failures do not appear until some significant running time to has
elapsed. F(t) arises after to .
A(t) = _f(t)
R(I)
For components that do not have shelf life, i.e. for components that no deterioration is
Time in service, t
considered before they go into service, the threshold time to is zero and the Weibull
failure probability distribution is given by Fig.7.6 1,
'T'herelationship between fJ and service time tfor 10 = Oand '7 =1
=nLfl(f -tjP-Jdt
"p t"
I -t)P
E(r) =n ( ~
108 Maintenance of Machinery Basic Probability Concepts 109
Using logarithmic transformations yeilds The average cumulative failure rate over the interval of time [to' t J is defined as
E(r) 1 ( t - to) P - 1
}.(t) (t _ t) ,or
IOg( E~)) =fJlog(t - tj -fJlogl]
= = ~ ~
or,
logt
J
= tozn + {IOg(
fJ
i...),
n
or The paired data ((t) - t j , A(t) ) should tend to a straight line on a log-log paper, and
the slope of the straight line is fJ - 1. fJ can be obtained from
This equation is a basic relationship for the graphical estimation of the Weibull process
which can be solved for fJ. The paired data (t}' j) plotted on a log-log graph paper will
tend to be straight line from which fJ and I] can be estimated. In general, the Weibull parameters are obtained as estimates from the plots on a Weibull
probability graph paper on which various paired data like ((t) - t j , A( t)) or (0, j) are
plotted. The Weibull probability graph with its controlling point known as the estimation
point is shown in Fig. 7.7 below.
fJ
logt )
+ I
t »]
- log! ) I
b.2 A second method for estimating the Weibull parameters is to consider the average
cumulative failure rate over the interval [to' tJ .
r-t)fJ
E(r) = ( =:'
110 Maintenance of Machinery .Basic Probability Concepts 111
Example
(j) ESTIMATION POINT
The accumulated development and times-to- failure data for a complex repairable electronic
unit is given in the table below. Determine the fit parameters to describe the Weibull
process.
1 8.5
70
2 56.4
50
3 86.8
30
20
10
m
- 4
7
195.3
242.6
267.2
451.9
5 8 458.5
3 9 757.0
2
10 797.0
11 968.0
2 3 4 5 2 3 4 5
10' ., 12 1201.0
10'
TIME TO FAILURE
13 1618.0
14 1806.0
15 2400.0
Solution
This is a case where a single item is observed to fail. For the data given, n = 1. The paired
data in column 1 and column 2,(t} ,j) are plotted on a log-log paper. These points are made
to fit a straight line with to = o.
112 Maintenance of Machinery
The
. value of 1'/ is the value of t.} when j = n. Therefore," ., is obtained from the plot for
L = 1 which yields 1'/ = 9. 7 h .
n
P is the slope of the straight line plotted on the log-log paper and can be evaluated by The average number of failureSler unit, jln, n = 1
considering two points and using the equation
p
p
...•. 1 .q. q,
..•.
ji+1)
Iog ( - - Iog - (ji) 1\
P
n n
\ ,
logt, 1 - logt.
} + i+l Ji
...•.
From the graph, for L
equation yields n
= 1, t} = 9. 7 h and for L
n
= 10, t} = 900 h. Therefor the above
"
.::S
P
log(J 0) - log(J)
= 0.5083. ..•. -co
II
log900 - log 9. 7 ~ :.....
1\
Therefore the failure rate function is
\
0.5083 ( t) ..•.
,
0.5083-1
J..(t) = - ,or
9.7 9.7 q,
A.(t) = 0.1605 (t) -0.4917 l.
~
The reliability of the unit is
co
R(t)
t)
exp {- ( 9. 7
0.5083}
0 ..
o
o
=
1\
Or, ~
, "
R(t) = exp{-0.3151 (t)05083}
...•.
0
114 Maintenanfe of Machinery
Basic Probability Concepts 115
Example 7.13
The paired data k, A] are plotted on a log-log paper and a straight line is fitted to yield
Using the second method rework the above exam I t = O. The fJ value is obtained by picking two poi nts on the straight line and substituting
p e. o
in the equation
Solution
T_i
j - ;;
here r
.wnerej b
= num er of accumulated failures up to timet. -
J From the graph for tj = 100 h, Aj = 0.033 failures/h; tj = 10000 h,
and the values are entered in column 3 as shown in the following table. i )
= 0.0034 failures/h.
Hence, fJ is
Failure Accumulated Cumulative failure rate
number, development and log (0.0034) - log( 0.033) + 1 = 0.5065.
fJ
j log(J 00000) - log(J 00)
times- to-failure, Aj = 1. [failure /103h]
Ij [h] Ij
45l.9
22.46
= 10000'
05065- 1)_1
0.5065 = 9.47h
15.49 IJ ( 0.0034
8 458.5 17.45
9 757.0 1l.89 From these values of fJ and IJ, the failure rate and reliability functions are, respectively,
10 797.0 12.55
11 0.5065-1 .
968.0 11.36 A(t) =. O 5065. _ t = 0.1622(t)-<i4935,
12 9.47 ( 9.47 ) .
1201.0
9.99
13 1618.0 5065
14
8.03 t ) 0.
R(t) =exp {- ( 9.47 1=exp[-0.3202(t)05065].
1806.0 7.75
15 2400.0 6.25
Basic Probability Concepts 117
116 Maintenance of Machinery
The following examples demonstrate the use of the Weibull probability graph paper.
3
A{T), frl10 hr
..•o ..•o Example 7.14
N One hundred identical pumps have been run continuously and their times-to-failure were
0
'"' r
)" n
:1 r
~n·· II
noted. The times-to-failure in h, the number of pumps that failed
percent failed for to 0= 900 his given in the pump failure data below.
and the cumulative
Determine the
~ I II Weibull fit parameters, fJ and n.
e: 0
(:) P
0
e.
(")
0 (..)
~(,.)
Cumulative %failed t - to
~
_.""
~ I'~ Times-to-failure Number of Pumps
a ~
'"t II '"t
I IJ 1000 - 1100 2 2 200
~
('\)
II ,. I
J/
1100 -1200 6 8 300
....,
0
16 24 400
c+
I:T'
('\) :::1 ..•o 1200 -1300
1300 -1400 14 38 500
S
-;:
"0
~
G
II II . 26 64 600
0 1400-1500
8 II II
('\)
(ti
'"'
CD
-
t:
F
~...,
•
~
1500 -1600 22
7
86
93
700
800
1600 -1700
....,
0
0- j 99 900
S\) "" II 1700 - 1800 6
II .J 100 1000
It 1800 -1900 1
~
0'"
E: J
1I!ij
Solution
"0
0
..•
I
o
a
CD
w
:1 This is a case of a large and complete sample of times- to-failure.
rr The values in column 3 are plotted against the values in column 4 on a Weibull probability
graph paper. A straight line is fitted as shown iri Fig. 7. .
The characteristic life Yffor which 63% have failed is indicated as the Yf-estimator
from which Yfcan be determined.
From the estimation point on the Weibull graph paper a perpendicular is dropped
to the straight line fit which intersects the fJ-scale on the top of the graph to give
the fJ value.
Example 7.15
The failure dataof 10 items tested to failure is given in the table below. Determine the
Weibull fit da9'.8 and 1].
2
Solution
1
2 3 4' 5 'I 2 3 4 5 This is a case of a small and incomplete sample.
10X -, i
10X tiME TO FAILURE
The failure poims are ranked in ascending order and classified as failed (j) or suspended (s).
For the failed items a new increment is calculated using the formula
2
For second failed item,
2 :; 2 3 4 5
New increment = n + 1 - (order of previous failed item) 10 +1 - 1 = 1 ~ 1
.10' 10'"
n + 1 - (number of previous items) 10 +1 - 1 TIME TO FAILURE
8.1 Reasons for interest in the concepts of Reliability and Maintainability (R and M)
Chapter 8
Reliability and Maintainability The major reasons for the interest in R and M are the following:
In discussing the concepts of reliability and mainta inability, two terms must be understood 8.1.1 Complexity:The more complex a machinery is the more intrinsic the failures are.
precisely. These are: These failures may not result from a clearly definable failure of a component part.
') Failures are likely to result from
Failu/ defined as "non conformance to some defined performance criterion fl. - a combination of drift conditions or
- unforeseen characteristics of components.
Quality: defined as "conformance to specification".
Hence failures are more difficult to diagnose and are less likely to be foreseen by the
Based on the definition of failure and quality, we are now in a position to define the two designer. Therefore, reliability and maintainability concepts should be incorporated to
most importantlterms in maintenance. lessen failure occurrences and enhance system performance.
R~liabil~'}iS defined as the probability that an item wm perform a required function 8.1.2 Mass Production: This requires very high degree of control over material
~ under stated conditions for a stated period of time. procurement, manufacture and assembly, engineering changes etc. Along with the
labour involved, these items require sophisticated systems of control and good
It can also be defined as the probability of nonfailure in a given peri~d; and quality assurance techniques to prevent manufacturing- related failures.
~ is an extension of quality in to the time domain.
8.1.3 Cost and Tolerances: A product is designed to meet a production cost objective
Mai~t:;"abi/i~: is)defined the probability that a failed item will be restored to which imposes sever restrictions. These restrictions, in turn, lead to the
, /
-: operational effectiveness within a given period of time when the repair calculation of tolerance margins which must satisfy the requirement. Thus the
actions is performed in accordance with prescribed procedures. probability oftolerance related failure in the field is increased.
It is also defined as the probability of repair in a given time 8.1.4 Maintenance: Field diagnosis and repair costs are much greater than those
incurred in the factory. As a result, reductions in failure rate and repair time
Why do we need to talk of reliability and maintamability? The following are among the justify a reasonable investment, hence the interest in reliability and
reasons. ' maintainab~lity.
a) Reliability - determines frequency of repair; These major reasons, put together make reliability and maintainability factors which have
- fixes spares requirements; to be considered properly during the design, manufacture and operation time.
- determines loss of revenue.
8.2 Activities involved to achieve good Rand M
b) Maintainability - affects training, test equipment
downtime, manpower The achievement of good reliability and maintainability of a system results from
activities in three main areas:
124 Maintenance of Machinery Reliability and Maintainability 125
8.2.1 Design
In the design stage very many parameters have to be assembled together to
introduce reliability and maintainability features to the system at this stage.
During the design stage the following have to be considered adequately in order - Duplication
to introduce good design reliability and maintainability. DESIGN - Derating
DESIGN - Component Selection
RELIABILTY
Reduction in complexity - Design Qualifiction
Use of standard proven methods
Duplication of modules to increase fault tolerance
Derating practice of using components of higher stress rating than
- Quality Assurance
minimum requirement
- Production Testing
MANUFACTURE
Prototype Testing - Training
Subsequent feed back of information in to the design - Process Instruction
8.2.2 Manufacture
- Failure Feedback
The following considerations have direct effect on failure rate and should be well
ACHIEVED - Replacement Strategy
OPERATION/
accounted for during manufacture. RELIABILTY - Preventive Maintenance
FIELD SERVICE
Control of materials, methods, etc. - User Instruction
Control of work standards
Assembling procedures Fig. 8.1 Activities involved to achieve good reliability and maintainability
Installation and commissioning procedures
The activities undertaken to introduce good reliability and maintainability during design,
The costs ofR and M the relation between these costs along with the cost of maintenance,
manufacturing and operation periods are inter dependent as shown in Fig. 8.1 below.
form a complex interaction about which it is difficult to generalize. Money spent on
maintainability reduces repair time which in turn enhances reliability. Improved reliability
As can be observed, the design reliability is never achieved in practice, because activities
reduces maintenance costs whereas money spent on preventive maintenance may enhance
of manufacture, operation and serviceability are always less than the theoretical design reliability.
level.
Reliabilityand Maintainability 127
This interdependence between reliability ' maintainah] ty and
11·
n mai t . h . th
main enance IS S own ill e
diagram below. Operational conditions vary from one piece of equipment to another, so it is important
that these conditions be fully specified.
Careful considerations of reliability and maintainability factors at the design stage help in
predicting the expected life of a plant, the availability of a plant, and the expected
maintenance work load.
Any equipment must fulfil all the functions as set by the user and must also satisfy the
performance standards. The function can be split into two categories: primary and
l_- Fig. 8.3 Equipment performance standard determination
secondary functions.
8.6.2 Secondary functions: This category includes such functions like safety , control , and maintenance people working together.
3. The performance standard defines the proactive maintenance required to avoid
operational efficiency, compliance to environmental regulations, etc. These are the
functions which the equipment is expected to fulfil in addition to the primary failure.
functions.
8.7 Failure Mode:
The occurrence which is likely to stop the equipment from performing to standard all the
A failure mode is defined as any event which is likely to cause a functional failure of an
functions expected is some kind of failure. The failed state of an equipment is known as
equipment. The failure mode shows the connection between the failed state and the events
functional failure, and this occurs when the equipment is unable to fulfil a function to a
standard of operation which is set by the user. which cause them. Failure modes are classified into three groups.
8.7.1 Falling capacity: when the capability of the equipment falls below the desired
The performance standard used to define a functional failure is set by the user. And to
performance, we have falling capacity of the equipment. The main causes for
determine this performance standard there should be a common understanding among
various people, not only maintenance people working on their own. Who should set the reduced capability are:
standard is a question for many to participate. For example, consider a leak problem in a - deterioration due to wear and tear,
hydraulic system. The safety officer has his own definition of failure, so also the - lubricant failure,
maintenance man and the production manager. This is shown diagrammatically below. - dirt,
When do we say the system has failed? Is it when due to leakage there is a pool of oil - disassembly (falling apart),
formed around the machine? Or, is it when the consumption of oil increases, or the - human error.
equipment stops functioning properly? To answer this question a standard of performance
130 Maintenance of Machinery
~
Reduced Capability ~
Time
Initial Incapability
Fig. 8.4 Falling capacity Fig. 8.6 Low initial capability
8.7.2 Increase in desired performance: when desired performance rises above initial 8.8 Failure Effects:
capability of the equipment, there is failure of the equipment. The reasons! for
increase in desired performance are: Failure effects describe what happens when a failure mode occurs. In describing failure
- sustained, deliberate overloading, effects the following must be noted.
- sustained, unintentional overloading,
- sudden, unintentional overloading, 8.8.1 Evidence of failure:
- incorrect process materials which are out of specifications. Is the failure evident to operating crew?
Is the failure accompanied by obvious physical effects?
Does the equipment/machine stop functioning as a result of the failure?
Increased Desired Performance
-..~
--I---------
- -----
~arly failure
t2 time ••
The whole-life of equipment (failure) may be divided into three major distinct periods: F·19.•8 7 The bathtub curve
a) infant mortality period, or early failure
b) useful life period 8.9.1 Reasons for burn-in failures
c) wear-out period _ inadequate quality control
_ inadequate manufacturing methods
During the infant mortality period the failure rate is high owing to the presence of weak and _ substandard materials & workmanship
substandard components. As these component dropout one by one, the failure rate keeps _ wrong startup & installation
decreasing until a relatively low more or less constant level is obtained at time t.. Time _ inadequate processes and human error
tl is the beginning ofthe useful life period. For the time interval between t, and t2, which _ inadequate handling methods
is known as the useful period, only random failures occur which are unpredictable and
cannot be prevented. The wear-out period, beginning with time t2, is characterized by a 8.9.2 Reasons for useful life failures
rapidly rising failure rate as more and more components breakdown. - unexplainable causes
_ human error, abuse, natural failures
The failure rate curve, commonly known as the bathtub curve, is the sum of three separate - undetectable failures
over-lapping failure rate distributions known as burn-in (early failure), random failure, and - low safety factors
wear-out failure. _ higher random stress than expected
The decreasing failure rate known as early failures, of infant mortality, or burn-in,
is usually related to manufacture and quality assurance. 8.9.3 Causes for wear-out failures
The constant failure rate known as useful life or random failure is stress related. - inadequate maintenance
The increasing failure rate known as wear-out is due to damages causing wear - wear due to friction
processes - wear due to aging
- wrong overhaul practices
the superposition of these failure results in a curve which is commonly known as the - corrosion failure
bathtub curve.
Reliability and Maintainability 135
134 Maintenance of Machinery
As a result of inserting a new module into the system, adjustment
8.10 Down Time and Repair Time Alignment Time:
may be required. Some or all ofthe alignment time may fall outside
Failure is the cause for outage of machinery which prompts the need for repair the downtime.
This is the time consumed waiting for spares, test gear, additional
undertakings. Downtime and repair time, though they overlap greatly, they are not the LogistiC Time:
same. In order to be able to distinguish between these two times, the following definitions tools and manpower to be transported to the system.
Typical activities involve failure reporting, allocation of repair tasks,
must be understood. Administrative Time:
decision making, etc. which constitute administrative time.
Mean Down Time: (MDT) or outage is the period during which an equipment is in the
~) See attached figure for the various times and their superposition.
failed state.
Downtime may commence before repair
The different time intervals which form part of repair time and/or downtime are defined
here under. DOWN
Realization Time: This is the time which elapses before the fault condition becomes
apparent. This time element is pertinent to availability but does not Realisation Access Diagnosis Spares Replace Check
T = tl + t2 + ... + t k + (N - k)t
Downtime
~JLjl
;
Deti .. i
~~ II Fig.8.9 Mean time betweenfailures
F or a stated period in the life of an item, the ratio of the total number of failures t~ the
total cumulative observed time is defined as the observed failure rate. / 8.11.3 Observed Mean Time to Fail (MTTF)
I
I
observed failure rate total number of failures I
A=- For a stated period in the life of an item, the ratio of cumulative time to the total number
T offailures is defined as MTTF.
A
Definition
MTBF and MTTF can be calculated over any period of time. Mean life must include
For a stated period in the life of an item, the mean value of the length of time be een the failure of every item.
consecutive failures, computed as the ratio of the total cumulative observed time t the
total number offailures is defined as the MTBF.
Example 8.1
T
MTBF= o =-
A
k Determine the failure rate in % 11000h for the following test for no-replacement case
From equation (1) and (2), it can be seen that test duration: t = 1000h
A 1 number of units tested: n = 12
() = "
A, number of failed units: k =5
The failure history for the test is given in the table below.
138 Maintenance of Machinery
Reliability and Maintainability 139
For the case with no replacement the total tiune T' is given
. by Consider the probability of an item failing in the interval between t and t+dt. Given the
failure rate A.(t) , the probability that the item may Jail in the interval t to t + dt , provided
T= tj+···tk + (n- k)t it has survived until time t, is given by the conditional probability P E IE .
1 I
.;- ,......,'"
PE IE = A(t) dt
T == 620 + 390 + 780 + 860 + 950 + 7 x 1000 == 10600 1 I
where E I is survival up to time t with survival probability which is given by the reliability
A = Failure rate = Number of failures PE = R(t), •
Total time- I
5
A = 10600 = 0.0004716 failures/ hr and, E2 is item failing between time t and t+dt.
6 The probability offailure in the interval t to t+dt unconditionally is f(t)dt where l(t) is
,1,==
0.0004716 X 10 == 47.l6%failures /103 h
6 the failure probability density function. This probability is obtained by the multiplication
== 471.6failures/10 h ()
theorem which states that
Example 8.2
f(t)dt = PE I1E
I 2
A 1000-h life test is performed 10
. on components. One component failed after 400 h
another faded after 620 h and still another one failed after 780 h. The..restsurvi d th t t. PE
J
I1E
2
is given by
Compute the failure rate for the case of no replacement. rve e es .
Solution
Therefore,
The total cumulative time is
f( t) dt = R ( t) .A.(t) dt
A(t) = f(t)
R(t)
To determine MTBF, consider the (N-k) items that survived at t. Let (N-k) be NJt)
The probability that the item may fail between the runni ti 0 dt. . b
" ng imes an IS grven y
Substituting for f(t) in the equation of A(t) we get Hence MTBF will be given by
Integrating both sides yields from which one obtains the MTBF to be
-loIA(t)dt lotdRR(t)(t)
= MTBF = /"
io
N (t)dt
S
N
= f~
io
R(t)dt.
where A(t) is integrated with respect to time from 0 to t, and 1 For the case of constant failure rate A
is integrated with
respect to R(t). R(t)
MTBF = ;;~ R (t) dt = e -At
1
A
Wh~n t = 0, R~t) = 1 .i.e. the itej is 100% reliable; at time 1 , the reliability is R(t). Hence
the Interval of IntegratIOn for -- is between 1 and R(t) Example 8.3
R(t) .
Integrating the above equation yields What is the highest failure rate, expressed in faih ires/I 06 h, that a piece of equipment can
have if it is to operate with a probability of survival of 90% for 5000 h?
Solution
from which the reliability function is obtained to be
The reliability is given by
0.104
Or, R(t) =e-At A. = 5000 = 0.000021 failure / hr.
•
= 21 failures z l Ot h.
The MTBF of a piece of equipment is 1000 h. W hat is the probability of survival of this A bearing unit operating in an equipment has a Wei oull times-to-failure distribution with
equipment for a) 200 h of operation? b) 500 h of operation? c) 1000 h of operation? the following parameters
From the MTBF of the equipment we obtain the Iailure rate to be i) Determine the reliability of the bearing unit for operating time of a) 100 h, b) 250 h, c)
500 h, d)750 h, and e) 1000h.
1 1
A = -- = -- = O.OOlfailures/h ii) Plot the reliability versus operating time.
MTBF 1000
a) for 200 h of operation Given the threshold time to = 0, the reliability fun .tion is given by
b) for 500 h of operation For the various operating times t, the reliability of the bearing unit is tabulated below.
100 0.9976
R(t) =e -At = e -o.aot nooo = 0.368
250 0.9846
500 0.9394
8.13 System Reliability with Weibull Failure Probability Distribution 750 0.8691
1000 0.7792
In the Weibull probability distribution of failure. the failure rate varies with time. The
failure rate and reliability function are given by, respectively, 1500 0.5702
2000 0.3682
A(t) = Pp (t - to)P -/
R(t) ":XP[ -( ~ ) 'I These values are plotted against operation time in t he graph shown below.
For values of P > 1, the failure rate increases with time resulting in decreasing reliability
with time. This id explained in the following exa nple. •
Reliability and Maintainability 145
1
MTTR =-.
p
8.14 Maintainability
Hence, the time-to-restore probability density function is given by
Maintainability is a characteristic of design and installation which is expressed as the
probability that an item will conform to specified c( mditions within a given period of time, g(t) = _1_ e MTTR
MFTR
when maintenance action is performed in accorc ance with prescribed procedures and
resources. This case of exponential times-to-restore distribution applies to corrective maintenance
when the duration of repair, replacement or restoration times is exponentially distributed.
The objective of a maintainability program shoul j be to influence equipment design to
assure that maintenance of the equipment can be accomplished efficiently and safely. The maintainability function for the exponential time to restore distribution is
Maintainability requirements are usually contractual, and in such cases it is essential that ['g(t)dt
·0
the test method and the conditions under which it is to be carried out are carefully defined. [Ilpe -pldt
Achievement of specified Mean Time to Repair i~ rather expensive. ·0
- e -pI]
- I]
Since MTBF of an equipment defines the average time between failures, we can easily - e MTTR
estimate the probable number of failures in a give n time period.
where M(t,) is the probability that repair will be successfully completed in time t, when
Maintainability design features include: the time starts at time t=O, and
- access to replaceable assemblies p is the repair, replacement or restoration rare for which M «.) is to be determined .
•
If the time t I = MTTR, an equipment with an exponential times-to-restore pdjhas 63.2% 8.17 A-priori and a-posteriori maintainability determination
probability of being restored in the given time. i.e.
The a-priori maintainability function M(t J is predicted from
Mtt , = MTTR) = J - e -I = 0.632
M(tJ = P(t s tl) = ;;'g(t)dt
tl = 2.9957xMTTR The a-posteriori maintainability is determined from actual data collected and is given by
The 50% probability of accomplishing any repair or restoration activity is obtained in time
A piece of equipment is composed ofthree replaceahle subsystems. System failure rate and
For the exponential case, the mean time to repair is given by replacement time are given in the table. Estimate the equipment mean time to repair.
1 Estimate the probability that the equipment repair will be accomplished in 3/2 hrs.
MTTR= -
f.l
where is the repair rate. In many practical applications, determination ofMTTR is not
Jl Subsyste Failure MTTR(ll)
easy. m rate
MTTR is the mean of the distribution of equipment repair time and can be estimated from I 0.005 2
II 0.01
III 0.02 3/2
= 1- exp ---
1.5)
( 1.429 This can be defined as the probability that an equipment, when used under stated conditions
in an actual environment, will operate satisfactorily at any time.
M(t) = 0.650
MTBM
A=------
o MTBM+MDT
8.18 Availability:
A = _P-
ss A +P
A = MTBF
ss MITR + MTBF
In the calculation of A", preventive maintenance down time, supply downtime, queuing
downtime, administrative downtime are excluded.
Block diagrams are logic diagrams which show the functional relationship among the
Chapter 9
system elements. To be able to predict reliability of a system, the system is represented as
Reliability and Maintainability Prediction a number of functional blocks that are interconnected according to effect. The
interconnection of blocks can be one ofthe possible three types. However, there are cases
Reliability prediction is the process of calculating the anticipated system reliability from
when these interconnections may not represent a system.
assumed component failure rates. Reliability calculation is an imprecise calculation but
provides a quantitative measure of how close a design comes to meeting design objectives
9.1.1 Series-connected components
and ~e~~s ~omparisons to be made between different design proposals. Reliability For such a system to work all components must work. For a system of two blocks
prediction ISImportant for the following reasons:
failure of either block prevents operation of the system.
b) It enables an assessment of life cycle costs to be carried out. Fig. 9.2 Series connection
c) It enables establishment of areas which contribute major part system unreliability.
d) It enables the achievement of a given availability.
9.1.2 Parallel-connected components
e) It provides prior knowledge as to the magnitude of expected maintenance work load.
For such a system, system failure constitutes failure of all components. The system of
two blocks fails if both blocks fail.
For the purpose of analysis, a large and complex plant is regarded as a hierarchy of parts
ranked a~c.ording~otheir function and replaceability. The figure below shows how a plant
can be divided to ItSbasic components.
-Performing major
plant functions
9.1.3 Composite connection
This is a combination of series and parallel connections. For the system shown, the
system fails if block A fails or if both blocks Band C fail. Failure ofB or C alone is
-Non-replaceable
ITEMS -Replaceable complex not sufficient to cause system failure.
-Replaceable simple
COMPONENTS
-Individual parts
-Simple replaceable
--1 A
Rsy
3. Blocks should be mutually independent in that failure in one block should not affect
n increasing
the probability of failure in other blocks.
For a series-connected system, the entire system fai Is if anyone of the subsystems fails.
For series connected units and constant failure rates, the system MTBF is given by
The survival probability of a system consisting of n components in series is given by
1
n
Example 9.1
where Rsy(t)= survival probability of system, and
Rlt) = survival probability of a component.
An electronic system consists of a power supply, a receiver and an amplifier with failure
rates of 25 failures/IO" h, 30 failures/In" h and 15 failures/IO" h respectively. The
The reliability of a component is given by
equipment is to operate for 1000h. What is the pro bability of survival of this equipment?
Solution
Hence, for the series system of n components, the system reliability is given by
A power supply = 25 failures/l (f h
6
A""Cei",r = 30 failure 110 h
~ R receiver
. exp[- 30 10-6 1000] 0.97045
Or, Rjt) = exp[ -io E A/tJ -
l
1=1
Aamplifier
=
= 15 failures
x
I 10 h
X
6
=
For constant failure rate case, i.e. for the useful life of components where the failure rate => R . = e-15xIOO<;XIOOO == 0.98511
amplifier
remains more or less constant,
-,l t -i, I
= e I
"', RitJ = e 1/
Requipment = Rpower . RReceiver . Ramplifier
= 0.97531 x 0.97045 x 0.98511 R.
equipment
= e-J..I = e-O.00067x500 = 07153
.
Requipment= 0.93240
9.3 Reliability of Parall~1<;onnected Systems:
Or,
Requipmenl = exp[-(25X 106+ 15x 10-6) x 1000= 0.93239J Parallel-connected can be in parallel active redundancy where all systems are activated, in
standby, or partial active redundancy where system is allowed to function until a
Example 9.2 predetermined number of components are left for successful operation.
Calculate the probability of survival of a piece of equipment that is to operate for 500h and 9.3.1 All systems activated
which consists of four subsystems connected in series having the following MI'BF's.
In this type of parallel connection all components art: functioning simultaneously. Consider
Subsystem A: MI'BF 5000 h = the system shown in Fig. 8.15.
Subsystem B: BTBF = 3000 h
Subsystem C: MI'BF = 15,000 h
Subsystem C: MI'BF = 50,000 h }-
Failure rate for a component is given by
1 Fig.9.6 Parallel connection of two components
--1=--
MI'BF
There are three possible ways in which the system is able to operate:
Hence failure rates of the subsystems are - subsystem A and B are working;
1 - subsystem A is working, B has failed; or
AA = 5000 failure / h
- subsystem A has failed, B is working
1
AB = 3000 failure / h The system fails if only both subsystems fail.
J
--Ie = 15,000 failure / h Assuming the failure probabilities of components A and B to be FA (t) and FB (t) ,
respectively, the probability that the system fails is given by
1
A. D = 50,000 failure / h
1
A = A. A + AB + Ac + AD = --1500 = 000067
.
failure/ h
Therefore, the survival probability of the system is
System reliability is given by
R(t) = J- F(t)
For n redundant components in parallel, the survival probability of the system is given by
Since A and B also C and D are in series, their respective probabilities are given by
If R1(t) = ~(t) =. ··l\(t), the system reliability is given by
RAB = RA· RB
The reliability plot of identical-unit parallel system in which all units are activated is RSYS = 1- (1- RAB)·(l- ReD)
s.; = 0.9639
Rsy n increasing
o.o~
1.00
__ l
0.0
In many cases of active redundancy, the number (ofunits permitted to fail before system
failure occurs is less than full redundancy. For example, in a system of three units, full
Runil redundancy requires only one unit to function, whereas partial redundancy would exist if
Fig.9.7 Parallel system reliability for increasing n two units were required with only one allowed to fail.
For a parallel connected system where all components are activated, the MTBF is given by For three identical units, each with reliability R, and failure probability F = l-R, the
binomial expansion of(R + F)3 yields the various probabilities offailure.
Assuming that RA = RB = ~: = Ro = 0.9 , determine the overall system reliability for the
arrangement shown in the figure. Partial active redundancy is also known as r-out-of-m unit network. At least r units out
of m active units must function successfully for the system success. The system reliability
is given by
- --~-~----- J
where
Rsy t (7) (e -ll)i(J - e -J.t)m =i 9.3.3 Parallel Redundant System in Standby
(7) = i!(mm~i)!
In the standby configuration one or more subsystems are standing by to take over operation
upon failure of the basic unit. The standby units are not operative until a failure-sensing
The MTBF of partially active redundant systems is given by device senses the failure of the basic unit and turns on and connects the standby unit.
Should failure take place in subsystem A, B is switched in its place, and should B fail C is
MTBF=~fl
/L i=r C .& "'--l.--
Example 9.4
An aircraft has four independent, active and identical engines. At least two ofthe engines Fig.9.8 Redundant system in standby
must operate successfully for the aircraft to fly successfully. The constant failure rate of
each engine is 0.009 failures/h. Compute the reliability of the aircraft for a seven-hour
In parallel systems in standby, the following assumptions are initially made.
flying mission.
i) The means of sensing that failure has occurred and for switching from the defective to
Solution
the standby is assumed to be failure free.
ii) The standby subsystems are assumed to have identical, constant failure rates to the main
This a case of 2 out 4 event.
subsystem.
iii) The standby subsystems are assumed not to fail while in the idle state.
The failure rate is given as A = 0.009 failures / h. The system reliability can be obtained
iv) Defective subsystems are assumed to remain so. No repair is effected until the system
from the relationship
has failed.
The Poisson distribution is used to determine the reliability of stand by systems since they
display the constant At characteristic of the Poisson process.
where m = 4, and r = 2. Therefore, the system reliability is
If the probability of no failure is e-)'I , the probabihty of one failure is given by At· e-AC ;
Rsy = (;) (e -0009 x 7)2(1 - e -0009x7)4-2 +
the probability of two failures is (At)2. e-A1 ; and so on. These terms may be arranged
( ;) (e -0009 x 7)3 (1 _ e -0.009 '7)4 -3 + 2
to represent the reliability of various standby configurations.
( ;) (e -0.009 7)4 (1 _ e -().009 7)4-4
x x
For the arrangement where one subsystem operates and another is in a standby, the
Rsy = 0.9991 reliability of the system is given by:
-AI
R sys = e -).1 + 1
/I,{. e
For a system with two standby units, In general for n-l standby units ready to take over if the basic should fail, the MTBF of the
system is
Rsys = e-J.I + At. e-~ + (At/ . e-J.I
n
2 MTBF=-
A
For a system with n standby units,
Example 9.5
(At)n-l
R =e-A1 +At·e-A1+ .. + . -A'
sys (n-I)! e An electronic device has a failure rate of 500 failures/I 06h. One identical standby unit is
used to increase the reliability of the basic device. The operating time is 1000h. The
When it cannot be assumed that the fault-sensing and switching device is lOO% reliable
reliability of the failure-sensing and switching element is R,w = 0.97. What is the system
the reliability of the system is affected by the switch reliability. Assuming that th~
reliability .
switching process does not affect the basic unit, for one standby unit, the system reliability
is given by
For the basic unit and the standby unit, the expected number of failure is
= e-A'(l + R,w'(AI»)
MTBF of Standby Systems:
= e -05 (1 + 0.97 x 0.5)
Consider the block diagram shown in Fig. 9.9 below. The connection of the blocks in this
The MTBF of a system consisting of the basic unit and one standby unit is case is neither parallel nor series.
2
MTBF= - To ensure the reliability of the system, i.e. for the system to operate successfully, at least
A
on of the paths AA' or BB' should function. However, since neither A nor B is fully
reliable, a third element C is added to supply either ..\' or B'. Hence four paths are possible:
The MTBF of a system with two standby units is AA', BB', CA' or CB'.
3
MTBF=-
A
Example 9.6
For the system connection shown in the figure below, determine system reliability given the
reliability of each component.
System reliability for this arrangement can be calculated from Baye's theorem.
Solution
In this connection, the three elements A, B, and C are connected in parallel in the upper
row. This parallel connection is in series with the lower row of two elements, A' and B',
This system reliability is arrived at in the following procedure. The system success requires
which are parallel to each other.
at least one of the paths AA', BB', CA' or CB' to be successful.
R sys =R .
sys/C;
+ R sysIC".,
Maximum repair time is the repair maintenance (restoration, replacement) time t M which
max
should not be exceeded or exceeded only with a small probability.
9.7 The case of Jl(t) not constant
For example,
For Ii(t) not constant, the pdfis given by
-i,'fl(l)dl
if tM = 2.3026 MTTR, then
max g(t) = Ii(t) eO. dt
M(t) = J;lg(t)dt
or,
- Pfl(t)dt
M(tM ) = 1 - 0. = 0.90 = fli(t) e iu . dt
• max
In general,
Let
I
_( M.ua) -f Ii (t)dt = v - -li(t)dt = dv
M(tMmJ = 1 - e MITR = 1 - 0.
then the maintainability probability function is gi ven by
from which we obtain
M(t) - J;le "dv
Into) =
MTTR -e VI 0t
-1.' fl(t)dt I
or, = e 0 10
MTTR
In (a) Upon simplification, the maintainability function is obtained to be
-i,'fl(l)dl
M(t) = 1 - e Ii
166 Maintenance of Machinery Reliabit ity and Maintainability Prediction 167
Given M(t) and g(t), to determine the non-constant failure rate p(t) multiply the equation
for M(t) by p(t) to get tj - y)P
-.£'p(I)dl - In(1 - M(t)] = ( -rt-
utt)« a x: [1 - M(t)] p(t)
from which we obtain
or
from which the repair rate p(t) is evaluated to be As an example, consider the case for which M(t) = 95%. Then,
or,
9.8 Maintainability for a given restoration time with a Weibull times-to-restore t, = y + n (2.99573 YIp
distribution
In the maintainability function The median time to restore t/ is obtained for M't/) = 50% and is obtained from
M(t) z: P(t s t) z: £llg(t)dt
t/ = y + n (0.69315 )IIP
the Weibull times-to-restore probability density function is
P - j - (I - yr Example 9.8
g(t) z: ~ t ~ Y . e -1/-
( )
Given the Weibull times-to-restore pdf of an equipment with distribution parameters
from which the maintainability function is obtai. led to be f3 = 3.5, rt = 4.0 h, y = 0.25 h,
Solution
For the Weibull distribution, the time to restore t j f Ira desired maintainability probability M(t)
is obtained by solving the above equation for tj a)
D) .For t == 5 h
M(t==5) z: 1 _e (~4(i25rJ
M(I-==5) == 083875 Chapter 10
Maintenance Planning
c) The me ti
an ime to restore for the Weibull ti
rrnes. to-restore pdf is given by
Maintenance plan is needed to lay down a rational basis for formulating a programme of
MTTR = r + 77 r (; + 1) . preventive maintenance and to provide guidelines fOI'corrective maintenance by the adoption ,.t
of the proper maintenance policies for the constituent items and components. Any rational
maintenance plan should be related to the production programme of the plant. This
MlTR = 0.25+ 4.0 r( ~+3.5 I) interrelationship is shown in Fig. 10.1.
PREVENTIVE CORRECTIVE
PRODUCTION
rC~5 + I) = r(1.2857) = 0.8998 PROGRAM --,---- MAINTENANCE
PLAN
---------- MAfNTENANCE
GUIDELfNES
MTTR = 3.8492h
t/ == 3.8523 h The reasons for introducing a maintenance planni ng system are numerous, a few of the
important ones being the following.
Maintenance Difficulty of collecting statistical data should ie seriously considered in adopting this
ITEMS management policy.
responsibility for
repair/replacement
10.1.2 Condition -based maintenance
ICOMPONENTS I Condition performance monitoring techniq .ies which /are costly in t~ and
----._-
instrumentation form the basis for condition-cased maintenance. The proper time for
Fig. 10.2 Subdivisions of a complex pi int according to responsibility performing preventive maintenance is determin ed by monitoring condition/performance
if some parameters that can be monitored are isolated.
Th~ above division of responsibility is obligatory be cause replacement strategy for units (or the
~aIn plant itself) is influenced by external factors (I Jbsolescence, sales, capital cost) as well as 10.1.3 Opportunity maintenance
Internal factors, mostly short term such as maintenance cost, operating cost. Therefore This term opportunity maintenance is used for maintenance actions directed at items other
replaceme~t strategy at this level is considered as a part of the corporate strategy. In the lower than those that are the primary cause of the repair. This policy is most appropriate for
level, repaIr/replacement strategy is the responsibility of maintenance management. complex-replaceable or continuously operating terns of high shut-down or unavailability
costs.
Pro~er maintenance planning has some benefits, ev .n in the simpler plants. These benefits are
obtained as:
10.1.4 Operate-to-failure and corrective maintenance
reduction in downtime, '(f)
I~ adopting this policy, no predetermined actic n is taken to prevent failure. Corrective
efficient and optimal resource utilization ,
maintenance arises not only when an item fails but also when indicated by condition-
prolonged machine life, and /
based criteria. The basic task is establishing the most economic way of restoring a unit to
good maintenance cost control. ( an acceptable condition. Cost of unavailability, time of repair with that of replacement
(and source of cost) influence the repair-replac : choice.
10.1 Maintenance Policies
0
1- A plant should be classified in to units, items and components Expensive =
g...,
Classification of items:
Complex ./
replaceable /"
.,
=
Q.
l~/ -
nature of the process:- chemical, mec ianical, etc.;
manufacturer's maintenance recomm ~ndations:- actions, periodicities, etc.;
equipment factors which assist prediction of maintenance work :- failure
){,10.4 Assessment of Potential Effectiveness of Maintenance Actions
( characteristics, meantime to failure, mode of failure, failure rate, etc.; The potential effectiveness of a maintenance action used has to be assessed if it can meet
( - economic factors which assist predici ion of main critical units :- consequences the requirements. An example for assessing the effectiveness of a plan adopted is given in
\ of failure, cost of replacement pnor to failure, momtormg cost, etc.; the sketch below, Fig. lOA.
safety factors which place constraints on the decision :- internal, environmental,
statutory regulations, etc.
The selection of the 'best' maintenance policy is affected by many factors, out of which
minimum cost is the criterion generally adopted for selection of the appropriate policy
given that the safety criteria are met; i.e. The b-est policy for each item is determined from
among identified applicable policies based on minimum cost criterion, given that the
safety criterion is satisfied. An example is given below in Fig. 10.3 for the selection of
maintenance policy for complex plant items.
Maintenance Ptanning 175
10.5 Summary
NO
Is there an adverse
relationsh ip between YES
List actions
age and reliability?
/NO
No Preventive Maintenance actiorJ
will be effective, operate to failure
11.1.2 Trade force location: The trade force Iocation must reduce the time of plant
unavailability.
If the work load is widely distributed ill d contains a large proportion of high cost
Chapter 11 emergency maintenance, permanent decentralization of the trade force reduces
Organization of Maintenance Resources the cost, both direct and indirect.
For a localized work load centralization of the maintenance improves utilization
of resources.
Maintenance organization can take an infinite numb er of forms, the best form for particular
For infrequent, but anticipated, highly specialized work, the use of contract
situation being determined by systematic consideration of the influencing factors. Organization
labour must be considered.
of maintenance resources for a multi-trade maintena nee work load is a difficult managerial
problem which involves three areas of organization cecision making.
The aim of trade-force location is to balance the advantages of centralization against the cost
associated with travelling. The solution is often a partially decentralized system. In this case,
1- Those concerned with the mix. Location, and siz e of the maintenance resources
the maintenance gangs carry-out the emergency work as priority and also as much of the
2- Those concerned with the nature and type of adrrinistrative procedures
scheduled work as possible, while the functions of the main workshop are:
3- Those concerned with the type of work planning and scheduling systems necessary to
match the level and supply of resources to the work load.
1. to act as a reserve of labour for the areas g.ige:
11.1 Maintenance Resource Structure: 2. to undertake the major reconditioning anc overhand work;
3. to act as a base for those trades men who ire better centralized;
Here, the objective is to set up the mix, location and size of resources which will best
4. to coordinate the externally contracted we rk
respond to the expected maintenance workload. The workload in general falls into two
categories:
A partially decentralized maintenance structure is shown in Fig. 10.1 below. As indicated in
(a) The deterministic work load: which can be rlanned and scheduled in the long term.
the figure, each area gang is responsible for mainte .iance activities within the section. Major
(preventive maintenance, modifications project)
overhaul and complex repairs are taken care of by the central workshop. For a few
(b) The probabilistic load: those which can be scheduled only in the short-
specialized maintenance workload which is beyond the capability of the central workshop,
term.(Corrective and emergency maintenar.cej The fluctuating nature of the latter
contracted labour is utilized.
makes the organization of maintenance resc urce a difficult task.
11.1.3 Trade force size: If the workload is deterministic, it is not difficult to determine the
11.1.1 Trade force mix: The work load is usually divided according to trade in addition to
best size of the trade force. However, in rnr.st manufacturing situations the work load
the above classification. This demarcation a::cording to trade influences the range of
usually contains a large probabilistic components which renders setting of trade force
plant equipment that can be effectively dealt with by an individual tradesman. This
demarcation: size a difficult task.
determines the number and size gangs;
The basic aim should be to achieve a tade force size and structure which will
minimize the total cost of labour and waiti ti
•.•• If g ime. Utilization of trade force need
to be optimized.
11.2 Administrative Structure:
Maintenance workload
I Su~tore - Complex repair work
- Major reconditioning
2. The administrative
resource structure.
structure should be designed in conjunction with and to suit the
Maintenance workload
I Su~tore
1
I
1 CENTRAL
accountable to the mechanical engineer. Maintenance engineers, i.e. mechanical, electrical and
building, are responsible for overseeing and ..upervising all maintenance workload
1 WORKSHOP
_from production area B undertakings directly under them; are responsible for overall maintenance works and are
\
AREA GANG B - - Overhauls accountable to the maintenance manager.
(Repair and ( - Spare parts
Service)
Work completed - -1-, '- - - Reconditioning
1 - Area work overload
1 Maintenance ]
support
Manager
I
1 - Cobtracting outside I
I expertise
Maintenance workload
I Su~tore
I
I
I
. from production area C __ J~
Building Maintenance I Mechanical Maintenar:1
AREA GANG C
(Repair and
I Head I Head J
- Completed work
Service)
Work completed
..
Building
I
Area I
I
Area 2
.I
Are t3 Workshop Electrical
Fig. 11.1 A partially decentralized maintei iance system Foreman Foreman Foreman Forer ian Foreman Foreman
Main function of the maintenance manager and engi neers may include: a) locate the malfunction;
1. Set maintenance objectives and determine maintenance policy. b) diagnose the fault;
2. Assist with technical advice and decision r iaking. c) prescribe the action to correct the malfuncton;
3. Assist with medium term work planning and scheduling. d) decide on the work priority;
4. Look after day-to day personnel problems. e) plan the resources necessary to undertake the work;
g) schedule the work;
11.3 Work Planning and Scheduling h) issue job instructions;
i) check that the work is satisfactory.
The objective of work planning and scheduling is to get the right resources to the right place,
to do the right job in the right way and at the right ti ne in order to carry out the maintenance Such a work can only be scheduled, with any degree of certainty, a short time ahead.
function at minimum overall cost.
ii. The deterministic work load:
11.3.1 Work planning This consists of the preventive maintenance work and the necessary plant modifications.
It can be planned in detail and scheduled some time ahead. The functions of a
In designing a maintenance work planning some be sic rules should be observed. The most maintenance department as regards the deterministic workload is to:
important of these are: a) schedule all preventive maintenance- fixed -time maintenance;
1. The work planner must have the authority to make the necessary decisions (i.e. b) perform'all performance monitoring ar d set schedules based on the condition of
allocation of priorities) which affect the work load and the resources. the plant;
c) determine all reconditioning activities
2. The work planner must have the right information at the right time about both the d) recommend appropriate long tern sol uti on to recurring problems to enhance plant
work load and the resources. Here it is important to note that it is essential to have maintenance and maintainability.
different levels of work planning.
When the total work load for a department is servir .ed from common resources, usually the
3. The areas of responsibility of, and lines (If communication between, the planning preventive maintenance is neglected. Therefore the planning policy should even out the total
levels must be clearly defined. work load while conforming to priority rules.
In setting a workable maintenance plan, the maintena ice workload should be categorized based Proper work planning is facilitated by appropria.e equipment records. Two important
on the nature of the workload. This categorization should include the random and equipment records are:
deterministic workloads. 1.- equipment record card which contains us eful data regarding the acquisition and
installation of the equipment,
and
i. The probabilistic load: 11 - equipment history record card in which all 'aults, corrections, replacements, repairs,
This category consists of the emergency and corr ective maintenance workload which is etc. are recorded during its operation time.
random in nature. This workload fluctuates with tim e. The repair situation can be represented
by queuing mode. Typical equipment record card and equipment histo y record card are shown in Fig. 11.3 and
Fig. 11.4, respectively.
The function of a maintenance department as regards the probabilistic workload is to:
•
1-=
Equipment Accessories
Dimensions Purchase Order no
Weight Work Details
Input: Voltage, current, ... Date of Purchase Performed
Manufacturer on Equipment
1 Agent Price
i
Services Needed
I Installation Cost
.,
Organization of Maintenance Resources 185
184 Maintenance of Machinery
In executing the maintenance schedule, the superviso' must every morning assigns work to equipment, spares, estimated time, sk~llrequired, etc. A typical job order card is shown in Fig.
every worker. "Everyworker has to be informed of the work he has to perform, the time the job 11.7 below.
requires, the expected finishing time, etc.
Job Order no.
Equipment Code
The details of the maintenance work to be done on eacJ1 equipment/item on schedule varies in Type of Job Name of Equipment Location Date
type and complexity of equipment as well as type of maintenance to be performed. The details
CM
PM
--
OU __
are shown on work specification card shown below, Fig. 11.6.
Priority
It should be noted that these forms are available in many different formats and each Details of Defect I Planned Work Breakdown Impact
b) Standby Reduction
Manpower Required
Maintenance Work Details Estimated Time Materialsl Trade Description of Workload
Spares Required
Estimated Duration
Start of Maintenance
Date Time
Completion of Maintenance
Date Time
Ready for Operation
Date Time
Actual Duration
Services Needed
Special Tools Required/Used
Spares/Materials Required/Used
Tradesman Name Total Time Materialsl Labour Material Total
Taken Spares Cost Cost Cost
Job Assignment
Special Services Required/Used
Name
A maintenance job order is a detailed and complete W( rk order by means of which a technician,
Fig. 11.7 Maintenancejob order card
a mechanic, an electrician or any other skilled person is given the authority to attend to a
specific maintenance workload. In addition to the workload, the job order card lists the
Once the maintenance
importance Th work
f h is completed ' an appro pnate . analysis of defects is of utmost
. e nature 0 t e defect ' the caus es an d action
. taken, man-hour requirement and
total downtime
in furthe di aret' entered
th on defect anal y sis r'ecord, This defect analysis record finds its' use
r iagnos ICS at may be conducted on the .
is shown in Fig. 11.8. equipment. A typical defect analysis record
""
Chapter I~,
Equipment Code I Equipment Description Location I Card DO. Spares Inventory Control
The objective of spares inventory control is the mir imization of the sum of the associated costs
which can be classified as direct and indirect. The nterrelation of these costs is a complex one.
I
Direct costs could be reduced to zero by totally eliminating spares holding. The
consequence in availability is obvious and hence affecting the indirect costs.
On the other hand, plant availability would be greatly increased iflarge numbers of
every spare items were always held, rut then direct costs would be enormous.
where Nsp o. - fl) is total number 'IS expected spares requirement during the life-time of
12.3.2 Manually controlled inventory
Items of low usage rate which are not predictable with large percentage of variation to
the component o. - t.);
NT is the number of identic a parts in use during the life-time (f2 - f}). NT varies
which no mathematical approach could be made.
with time t.
Inventory control theory attempts to determine those procedures which will minimize the sum
during the period o, - t}). NT(t) can be determined by monitoring the component for a
stated period of time, or from the maintainability function.
of the costs of:
1.
2.
Running out of stock (production
Replenishing stock (cost of items)
loss due 10 stoppage)
For constant failure rate ),,(f)and wh~reNrrt) is constant in the period o. - t}), a good
estimate of the spares requirement is given by
3. Holding stock (interest on capital, insurance, depreciation)
Inhere, two basic theories are discussed. The first is based on the determination of the number
of expected failures for a given period in the life of the equipment for which a spares holding
is to be determined; and the second is the Economic Order Quantity.
Example
Or,
R (t) = e -,ll( 1 + At + (At) 2 + ... + (), t) k)
21 k!
T
Forthisproblem R(t) = 0.99
'-.-~ Ordering point
1 1 Interval between J
A =-- --- orders
MTBF 1250
Fig. 12.1 The simple economic order quantity
At = __ I _ xt = _1_ x250 = 0.2
MTBF 1250
Hence the reliability is obtained from Let: Demand per unit time q
Replenishment Quantity R
R(t) = e -fJ2( 1 + 0.2 + (0.2)2 + ... + (0.2)k) Ordering cost a
21 kl
Holding cost per item per un:t time b
R (t) for 0 failures is e -).r = e -0.2 = 0.818 Total expected cost per unit time C
Number of replenishment orders per unit time = q/R
R(t) for 1 failure is e -,lI(1 + At) = 0.982 Replenishment cost (qa)/R
R(t) for 2 failures is e -A{ 1 + At + (A;;2) = 0.998 Total Cost per unit time C is
C = qa
R
From the above Poisson of reliability terms, to attain a reliability of 99% two spare parts are where
required for the unit. Rb = average holding cost per unit time.
2
-dC = 0 =>
3(~ + k = 0
The simple Economic Order Quantity (EOQ) determ ines the size of replenishment order which dR R) 2
minimizes the sum of holding and re-ordering costs. For a simplified approach the following
assumptions are made. From which the economic order quant ty R can be determined to be
The following table is filled to give the replenishment cost, the holding cost and total cost for
different replenishment quantities.
12.7 Safety Stock
3500
Random variability of demand and lead time are some of the factors which are not
~
rc
CD
>-
accounted for in the simplified modelof Efn).
~
CD
a.
3000
I
I
<J> There are some methods of providing ;afety stock.
.•.. 2500
Ul
r
0
u
12.7.1 Two-bin system
2000r A fixed replenishment order is placed whenever stock reaches a pre-set re-order level.
This could be seen as storage in two bin in which replenishment order is placed when
I
first bin is empty and service is carried from second bin until order is received.
1S00r
EOQ =7 The value of r depends on
1000 - the rate of demand and its variability,
~:f
the lead time and its variability, and
- the cost of stock out.
replenishment cost
12.7.2 Periodic Review system
0 2 4 6 8 10 12
!
In the two-bin system continu al monitoring of all stock changes is required which is
14 16 18 20
difficult without help of computers. The most common and popular method is the
Replenishment quantity
traditional method which is tho periodic review system. At fixed intervals of time the
T.herefore, the economic order quantity is obtained from the figure to be the number which inventory is reviewed and sto .k is re-ordered in quantities decided as a result of the
grves the least overall cost. i.e., the economic order quantity is 7 items. review.
EOQ = R = ~ 2!a
EOQ 2x150x20
= 7.07
120
As can be noticed from the interconnec tion, logic diagram preparation and activity duration
determination can be done in parallel. Network analysis and management applications then
follow, respectively.
The overall procedure as applied to maintenance activities, networking has four stages:
Stage 1 - Logic Diagram Preparation
Stage 2 - Activity Duration Determination
Stage 3 - Network Analysis
Stage 4 - Management Applications
I
IDummy
I
Fig. 12. I1nterconnection of network acti vities for maintenance work
be assessed for their work content from the jobs and their standard times. At this stage the determining the sequence of events, some activities are arr~ged m senes, while ~thers are
duration for an activity is established. arranged in parallel. The preparation (If logic diagrams require good understandmg of and
experience with the system.
13.4 Stage 3 - Network Analysis (Adding Activity Duration to the Logic Diagram)
The preparation of a logic diagram isoest demonstrated by an example.
At this stage, the duration of each activity is added to the logic diagram from which the
shutdown duration and degree of criticality of the activities within the network are Example
determined. To perform this activity, activity on node method is used.
In a certain chemical plant, it is desired to repair a vessel with its major components. The
The basic node is shown in the figure below. repair work and the time required for' each job are indicated in the table below. °
b) Every activity has two possible finish dares/times: the earliest and latest finish
dates/times The logic diagram for the repair works shown in the figure b~l~w.. In preparing. the logic
diagram, sequence of events as require Iby the maintenance activity I~ fir~t underlined. For
c) The degree of criticality of a particular activity is defined as the total float (TF) where examp Ie, Jiob reference no. 102 cannot be handled without completing Job reference d dno.
i
10l. Job reference no. 100,102 and f O'I, which do not affect each other, are han Ie m
TF = LS - ES parllel.
In the event that TF = 0, then the activity is crit.cal.
Maintenance of Machinery
!I:"
The arrows joining the activities are dependency lines and indicate the sequence of
activities.
a) The frrstpart of the calculation is to work through the network from left to right filling
in the topboxes. i.e. ES and EF .
.Note that activity 106 cannot begin until activities 102, 104, and 105 are finished,
i.e. until 17,h is complete.
c) The last part of the calculation 'is the determination of the criticality of the various
activities in the network. This is done by determining TF.
Therefore, the critical path is defined as that chain of activities which has the least TF.
For this case the chain of activities 100, 101, J 02, 106 is the critical path.
d) The critical path establishes those activities which must start at their earliest start and
finish at their earliest finish if the shutdown is to be completed on time.
e) To reduce the shutdown duration, it is the critical path activities which require
shortening.
Reconditioningof Equipment 203
Replacement of all parts which have a residual life less than some critical useful life
and replacing by matching parts. In marty industrial applications the critical residual
life is 5 to 7 years.
Chapter 14
Replacement of all mandatory components.
Reconditioning of Equipment Inspection and repair of aJIcastings.
Grinding of guide-ways, etc and hardening.
~econditi~ning of eq.uipment plays a significant role in maintenance of equipment, particularly . Assembly and testing of all sub-assemblies.
in d.evelopm~ countries where increasing cost of new equipment makes the acquisition of new Reassembling the machine and achieving specified standards of alignments.
equipment difficult, The need for reconditioning arises from Load testing of machine to specified standards.
a) aging machinery with rapidly decreasing reliability and high risk of failure: Repainting and change of name plate where necessary.
b) increasing and prohibitive cost of new equipment; , Inspecting machine.
c) scarce capital;
d) lack of adequate foreign exchange. Maintenance management is often fac ed with the dilemma of replacement versus reconditioning
of an existing equipment. Rule of thumb that can be applied in this case is:
14.1 Definition
1) Parts which require a corn .iderable degree of specialized skills and costly processes
Re~o.nditio~ng of a worked out equipment after long use may be defined as a systematic planned are best replaced.
~CtIVIty desIg~ed to rest.ore an equipment to its original performance condition. This prOCI!SS 2) If the repair facility available is limited then replacement of certain machines with
mvolves~ renaI~s. t~ certam problem areas in an equipment that may include: technologically superior equipment must take precedence over reconditioning .
.grinding app scrapping; 3) If cheap and fast replacement parts are available, reconditioning is not a right
remo,~~l of slacw€,s~ due to wear; and alternative.
replacement of certain parts .
., ~
.•.~
. ' .... \,~- In general, maintenance management should resort to reconditioning if the following situations
a ~niJ:~e arise.
Reconditio~g;s
.',."t
Replacement costs should include: spares cost; installation; service costs; cost of ordering end
transporting; labour; utilities, etc.
Reconditioning costs should include: material, labour, depreciation, outside contracted services.
Inhere, one thing should be noted which may not be quantified in terms of dollars; and that is,
the experience gained locally in the process of reconditioning. Performing a reconditionng
activity develops local capabilities which leads to increased design and fabrication capability.
There are two aspects to the requirements that must be fulfilled to undertake a recondition ng
action. These are the infrastructure and technical requirements.
References
Appendix
1. A Kelly, M.J. Harris, Management of Industrial Maintenance, Butterworths & Co.
(Publishers) Ltd., London, 1978.
2 M. J. Neale, The Tribology Handbook, 2nd ed., Butterworths - heinmann Publishing Ltd.,
1995.
4. John Moubray, Reliability - Centered Maintenance, 2nd ed., Industrial Press InC., NY,
1997.
10. Charles O. Smith, Introduction to Reliability in Design, McGraw - Hill Inc., 1976.
11. Harry Frank, Steven C. Althoen, Statistics: Concepts and Applications, Cambridge
University Press, 1994.
Table 1- Values of the descending exponential
Table 1- Contd.
....
, •• At· 0.260
(I - At·••:o.OQO
. II· At - a,249
;.." ~.<
,-at At At ,-at
At
0.250 0.77880 0.300 0.74082' 0.350 0.'10469 0.400 0.67032 0.450. 0.63763
0.000, ,1.0סס00.. .o.0~.o,Q.9~m. 0.100.0.90484 o.J,o .o:.a601I.o~200 .0;111873 .' 0.251 .0.77802 0.301 0.74008' 0.351 0.7OJ98 0.401 0.66965' 0.451 0.63699
0.001, .0.99900.. : 0.0$1 .0.95.028' 0.JQL.P.90~9:J ,.0.1$) ;-:<t.8$98S<:O.~l)),·:fj.81~J:' ..' 0.252 0.71724 0.302 0.73934 0.352 0.10328 0.402 0.66898 0.452 0.63635
.0.002 .0.99800.' 0..of2;;.o.949ll· .0.1.02.0.9030~ . ' O.m Qi8$8~: 0.202' '-O.8t109,·. 0.253 0.77647 . 0.303 0.73860 0.353 0.7025, 0.403 0.6683I , 0.453 0.6"72
0.003, 0.99700.,-, o..o~3,..o.94~3g,,; .o.H)30.9Q213" > O. m Q.8m~ . "i 0.20, "'&;Sf.5..28: ' 0.254 0.77569 0.304 0.73786 0.354 0.70187· .0.404 0..6764' 0.4" 0.63S08
.0.004; 0.9961);1
.,.. .o.0$fk,O.94141, o. 104 ,O.9Ql23..' 0. r $4 .0.8$727< .0.204"''0 8~'" ' "
0.255 . 0.77492 0.305 0.73112 U5' 0.70Jl7 0.405 0.66698, 0.455 0.63445
o.OOS..o.9950J.:, o..o55rO.9~9' 0.1050.~3~ ,·o.rss: Q.85642. ,. O;2Q5."'~8;4(i(~ 0.256 .: 0.774t4 . 0.306 0.73639 0.356 0.70047 . 0.406 0.66631'
0.006' 0.9940~. ' o~o~;",O.91$S:( ~ .o.JQ6.o.89942:., .o.B6, ~O.8SS'6' 0.206. iQ.813U' . 0.456 0.63381
0.2570.77337 '0.307 0;73565 0.357 0.'69977 0.407 U6564 , 0.457 0.63318
0.007. .0.993.02 0.9~!' .0,944.59 . 0.1.07 .();898'3'" .0.15'7:"0;85'170' .o.20'j".o.81j()i"
0.00.8 .0.99203 0.0580.94U3 .o"J08' 0.89763 ,O.J~' :.o.8~38f . .o.2Q8:"O.8t221"
0.258 O. m.«» 0.301 0.734920,358 '0.$907 0.408 0."98! 0.458 0.63255
0.259 0.77182 0.3090.73418 0.3D 0.69837. 0A09 O.66·m
o.oos .o.99!04 I 0.0$9 0.94271' . .o.lo9"b.89.6n. .o.1~9~:85:~· .0.209:'.0.8 '*<> . !} 0.459 0.63192
•0.260, 0.77105 0.310 0.73~5 0.360. 0.69768 0.410 0.66365: 0.460 0.63128
O.O.H) . .o.9~~;,..o.06O Q.91.l76. 0.110 ..o:89,5~3 .0.160 0.8.5ZH .0.21.00.81058
.0.26110;77028 0.311 0.73271 0.361 0,69696 0.41J 0.66299:
0.01I " .0.98906.. 0.06.1. O.940~2 0.111 0.89494 0.161. O.S~129 o.zn ;~.8G91'l' 0.262 0.76951 0.312 0.73J98 0.3620.69628 0,412 0.66232;
0.461
0.462
0.63065
0.63002
0.Oi2 . 0.98801" .0.062 0.93988. .0.112' 0.89404 0.J~2 'O;85~ '. 0.212·O,s089~
6.0B .o.987.oS·, 0.063 0.93,894' 0.113 .0.89'315 0.1~3' .0,84'959' .o.2I'j"0.8OB16 0.263 0.76874 0.313 0.73125 0.363 0.69559 0.413 0.66166 0.463 0.62939
0.014 0.98610 .o.~ (}.93800. .0.1'14, 0.89226 .0.164'0.84'874' .o.2i4:' .08073',5' 0.264 0.76797 0.3140.73052· 0.364 0.69489 ·0.414 0.66100 0.464 0.62876
0.265 . 0.76nl 0.315 0.72979 0.365 '0.69420
o.ois o.sssn 0.06' 0.93707 . .0.115 0.89137 .0.165 .0.84789: 0.2J.S' O:s06S4' 0.266 0.76644 0.316' 0.12906 0.366 0.69350
0.415
0.416
0.66034
0.6'968.
0.465
0.466
0.62814
0.62751
0.()16 . 0098413 0.066· 0.93613. 0.U6 ..0.89047. .0.166' 0.8470} 0,2f6' '.0.:80574.
0.017 ,0.98314 .0.067 0.9)520. O.1l7 .0.88959 .o.i67'().84620· 0.21:7''i).80493'· , 0.267 0.76567 0.317 0.n833 0.367 0;69281 0.417 0.65902 0.467 0.62688
0:0)8 0.98216 0.068 0.9342.6 0.1180.88870 0.1.68.·.O.8453~ .' 0.218:'0.80413' 0.268 0.76491 0.318 0.n760 0.368 0.69212 0.418 0.65836 0.468 0.62625
0.01~ .o.9SU8 0..069 0.93333 0.119 0.88781 0.149,"0.84451 .~.0.219: 0.80332 0.269 0.76414 0.319 0.72688 .. 0.369 0;69143' 0.419 0.65770 0.469 0.62563
,0.020 .0.98020' 0.070.0;93239 0.1200.88692 .0.1,70-;0.84366 . 0.220' 0:802'2' ..' 0.270 0.76338 0.320 0.7261' 0.3700.69073 0.420 0.65704 0.470 0.6:mo.
a.oil· -0.97922 6.0'71 0.9.3146. 0.121' .o.88(j'(}j 0.1710.8421;Z ." 0.221 O.s<U:"?2'·:: 0.271 0.76262 0.321 0.72$42 0.3710.69004 0.421 0.65639 0.471 0.62438
0.272 0.76185 0.322 0.72433 0.372 0.68935 0.422 0:65573 0.472 0.62375
0;0220.97824 .0.072 0.930~3.· .0.122 .0.8.8515. 0.112 J>,84\98·.. 0.2~2' q.~6!)$:i<': 0.273 0.76109 0.323 0.72397 0.3730.68867 . 0.423 0.65$08
o..o~3 0.91726 0.~no;n9~ 0.123 O.884.l6 0.173 ,.p.S4114 .o,2l3 0.8~t.r 0.473 0.62313
0.274 . 0.76033 0.324 0.nn5 0.374 0.68798 .0.424 Q.6S442 0.474 D.6ZZ~1
0.024' .0.97629 0.074 .0.9.,2867. 0.t24.o.88338; 0.174 0.84010' 0.224.0.79932 '.'
0.025. 0.975:31., 0.075 ·.0.92774 .0.125 0.8825.0 ... ". .....<' 0.275 0.75957 0.325 0.72253 0.375 0.68729 0.42' 0.6'377 0.475 0.62t89
0026· . e.97434 0.076 ,.0;92682 0.126..0.8'8'161 0.175 :0.83946 .o.2.ZS . .().19~52 ·0.276 0.75881 0.326 O.nlBl . 0.316 0.68660 0.426 0.65312, 0.476 0.62126
O•'Q""' 9 0.l16.0.838~ 0.226 . 0.1977:1. . 0.277 0.75805 '0.327 O.nIOB 0.371 .0.68592 ..0.427 0.65246 0.477 0.62064
",v .0.. 7336. .0..077-·.0.92589 0.127 ..b.8807j.· 0.177' 0.83118 0.2210.796.92.
.0.628 0.97239 0,0780.92496 0.128' 0.87985 0.178' Q,S3~94, 0.2W 0.796.2'. 0.278 0.75730 0.328 0:72036 0.3780;68523 '0.428 0.65181 0.478 0.62002
0.029 0.97142; .0.079 0.92404 ,0.129 0.87897.' 0.1}9, .0.8360 0.229..0.19533'. '0.279 0.75654 0.329 0.71964 0.379 0.68454 0.429 0.65116 0.479 0.61940
.0.030' 0.9.7045: .0.080,..0.923'12 . 0.130 0.87810 .0180 .083~27 023' < -: 0.280 0.75578 0.3300;71892 . 0.380 '0;68386 0.4300.65051 0.480 0.61878
00 . . . J. • ',0. 0.79453 0.281 0.75503 0.331 M1821 '0.38'10;68318 .'0;431 ;0.64986 : 0.481 0.61816
.3h .0,96948 .0.081 .0.9-2219 0.131 .0.87122 0.181 0.83444' 0.23tO.19174'
o.on 0.96851 . 0.082 0.92127 .0.132 0.S,7634· . .0.182, 0.8~36O.' .0.232. 0.7~9~. 0.282 0.75427 0.332 0.1'749 0.382 iO:682SO o.<t32 0:64921 ; 0.482 0.61755
0.033 0,96754 . ~.0830.92035 0.133 0.87$47 0.1.83 O.Snn· 0.233 0.192lS' 0.283 O.7S~U '0•.333 0.7rlm U83 '0:68181 0.433 0.648~ 0.483 0.61693
0.034 0.966'''7 .0.084 0.91943 .0.134 :0.87459;. 0;184 0.83194 0.234 0.791~6 0.284 0.15'117 '0.334 ·,·0.116050.384· '0.68113 0.4340;64791 ' 0.484 0.61631'.
.:
0.035 0.;96561 0.085 .0.91851 0.135 0.81371 0.185 0;S3110 .0.235. .0.79057 0,285 O.15lOt 0.3350.71n.... 0.3850:6W45. 0.4350.64726 ! OAS5 0.61570
.o.Q36 0.96464 0.086 0.91759 0.116, 0.87284. 0.186 0.83Q21 0.236 ".0,78918 .0.286 0.m26 '0.3360.11462 :O~3~ ~9:67~77 0.436 0:64662 ! 0.486 0.61508
0,()3.7< 0.96368. 0.087 0.91666 0.l37 0.87197 0.187. :0.82944 0.237 .0.18899" ·0.287 . 0:7~J 'O.337·0.7tnl OJ87 l«67909 '0.437 '0.64597'; 0.4870.6J447 .'
0.03.8 _J).96211 .0.08.8.0.91576 0.i38.0.871iO., 0.18~.O;82$61 O.23S·0.til820'.c 0.2880.14~76 '0.338 0;1UlO- :0.3~ :0;67841. 0.438' 0.64533 : 0.488 0.61385 ~;
0.039 0,96115 0.089 0.91485' 0.J.39 .o:8·1Q23 0.1~9 '0,~2119 0.239;~.o;?il74( 0.289 0.74901 0.339 .0.1Im· 0.'389 '0.67773 0;439 .~:64468 0.489 0.61324;
.o.04q 0;96079 0.090 0.91393 0.140 0.8693.6 O.i90, .0.82696 .0.240.'.o.,z·8§63 .0.290 0.74826
g:g:~ 0.95983'
0.9;588.7
0.091, .0.91302
0.092'0.91211
.0.141 0.86~Oj'
.0·1420.86162
0.f91 ',0.$2613
0.192, ·,O.82~31·.
.o.24J· .o.iS584
.0.242 '0:18506
0.291
0.292
0.14152
0.74677
0.340 0.71171
0.341 0.71106
0.342 .0.71035
0.390j:i~67706
0.39J0.61638
0.392: 0.67570
0.440
0.441
0.442
.0.64404
0.64339
0,64275
,0.490
0.491
0.492
0.61263 "~
0.61201 "~
0.61140::
0.043 0.9'791
0.044 ·0.95695.
0.093 0.91119
0.094,.0.910~8
0.143 0.86675
.o.,l440.86~89
.0.1.93 0.82448
0.1940.$2~66
0.24Lo:78!li7'
.0.244: 0.7834~
·0.293
0.294
0.74602
,0.74528
0.343 .0.70964
0;3440.70193
0.3~ ~O:61S03
0.394 q.67435
0.443
0.444
0:.64211·
0.64147
0.493.
0.494
0.61079 't
0.61018 '.~
. ;.-, ", " .. '.. '
0.04' 0.9S6oQ, 0.095 0.909.37 .0.145 0.86502 .0.195 0.8228) O.24L 0.78270' .0,295 . 0.7445.3 of
0.345 0.70822 o.J95 O.i7368 0.445 0~64082 0.495 0.60957·
0.046 .o.95S04· 0.096. 0,90846. .o~l46, .0.86416 0.1.96: 0.82201. 0.246' 0.7'8191 0.296 - 0.74379 0.346 0.70m 0.396 ,~.6.7301 0.446 0.64018 0.496 0.60896 .;
0.047 .o.9~90.097. 0,9Q.710, 0.147 0.86;13(} 0.1.97 0.82U9 0.:24.1.',0.'781Iil 0.297 0.74304 0.347 O.~I 0.397U7~3 0;447 Q;6393'" ,0.497 0.60835:
0.048.' 0.953.]3 0.098 0.90665 0.148 0.86243 0.19.8. 0.8203.7' .0.248,0.780311 0.298 0.74230 0.348 0.70610 0,3.98.0.67166 ,0.448 0.63890 0.498 0.60774 i
0.049'- .0.95218 p.099 .o.90S74 o.wi 0.86151 0..199. 0.8(95." 0.t49'''Q.17~8 0.299 0.74156 0.349 0.70539 0.399' 0.67099· .0.449 0.63827 0.499 0.60714 .
-- - (
LIV
uJ --
-
Table 1- Contd.
r
Table 1- Contd.
-
212 Maintenance of Machinery
z 0.00 0.01 0.02 0.03 0.04 .0.05 0.06 0.07 0.08 '0.09
0.0 0.סס00 0.0Q40 0.0080' 0.0120 0.0159 0.0199 0.023.9 0.0279 0.0319 0.0359
0.1 0.0398 0.0438 0.0478 0.0517 0.0557 0.0596 0.0636' :..0.0675 Omt4 0.0753
0.2 0.0793. 0.0832 <t0871 0.0910 0.0948 0.0987, 0.1026 0.1064 0.1103 ' 0.1141
0.3 0,1179 0.1217 0.1Z35 0.1293 0.1331 0.1368 0.1406 0.1443. 0.1480 '0.1517'
0.4 0.1554 0.1~1 0.1628 0.1664 0.1700 0,1736 0.1772 0.1808 0.1844 0.1879.
-0.5 0.1915 0.19,50 0;1985 0.2019 0.2054 0.2088 0.2123 0.l157 0.2190 . 0.2224
0.6 0.2257 0.2291 0.2324 0.2357 0.2389 0;2422 0:2454 0.2486 0.2518 0.2549
0.7' 0.2580 0.2612 .0;2642 0.2673 0.2704 0.2734 0.2164 0.2794 0.2823 0.2852
0.8 0.2881 0;29,10 0.2939 0.2967 0.2995 .0.3023 0.305} ,0.3078· 0.3106 0.3233
0.9 0.3159 0.3i86 0.3212 0.3238 '·0.3264 0,3289 0;3315 0.3340 0.3365 0.3389
1.0 0.3413 0.3438 0.3461 a.3485 0.3508 0.3531 0.3554 0.35n 0;3599 0.3621
1.1 0.3643 0.3665 0.3686 0.371-8 0.3729 0.3749 0.37700.3790 . 0.3810 :. 0.3830
U 0.3849 0.3869 0.3888 0.3907 0;3925 0.3944 0,3962 0.3980 0.3997 0.4015
1.3 0.4032 0.4049 0.4066 0.4083 .0.4099 0.4115 0.4131 0.4147 0.4162 0.41n
1.4 0.4192 0.4207 0.4222 0.4236 0.4251 0.4265 0.4279 0.4292. 0.4306 .0.4319
1.5 0.4332 0.4345 0.4357 .0.4370 0.4382 0.4394 0.4406 0.4418 0.4430 0.4441
1.6 0.4452 0.4463 0.4474 0.44&5 ' 0.4495 0.4505 0.4515 0.4525 0.4535 0.4545
1.7 0.4554 0.4564 0.4573 0.4582 0.4591 0.4599 0.4608 0.4616 0.4625 0.4633
1.8 0.4641 0,4649 0.4656 0.4664 0.4671 0.4678 0.4686 0.4693 0.4699 0.4706
1.9 0.4713 0.4719 0.4726 0.4732 0.4738 0:4744 0.4750 0.4758 0.4762 0.4767
2.0 0.4713 0.4778 0.4783 0.4788 0.4793 0.4798 0.4803 0.4808 0.4812 0.4817
2.1 0.4821 0.4826 0.4830 0.4834 . 0.4838 0.4842 0.4846 0.4850 0.4854 0.4857
2.2 0.4861 0.4865 0.4868 0.4871 0.4875 '0.4878 0.4881 0.48!!4 0.4887 0.48~
2.3 0.4893 0.4896 0.4898 0.4901 0.4904 0.4906 0.4909 0.4911 0.4913 0.4916
2.4 0.4918 0.4920 0.4922 0.4925 0.4927 0.4929 0.993'l 0.4932 0.4934 0.4936
2.5 0.4938 0.4940 0.4941 0.4943 0.4945 0.4946 0.4948 0.4949 0.4951 0.4952
2.6 0.4953 0.4955 0.4956 0.4957 0.4959 0.4960 0.4961 0.4962 :0.4963 0.4964
2.7 0.4965 . 0.49~6 0.4967 0.4968 0.4969 0.4970 0.4971 0.4972 0.4973 0.4974
2.8 0.4974 0.4975 0.4976 0.4977 . 0.4977 0.4978 0.4979 0.4980 0.49800.4981
2.9 0.4981 0.4982 0.4983 0.4984 0.4984 0.4984 0.4985 0.4985 0.49860.4986
3.0 0.49865 0.t9~7 0.4987 0.4988 04988 0.4988 0.4989 0.4989 0.4989 0.4990