Professional Documents
Culture Documents
S h e l l EP Le
Le a r n i n g Copyright 2001 SIEP B.V
z The Tools
z Running Procedures
z Connections
z Packers
z SSSVs
z Well Hand-Over
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
1
Wellsite Preparations
Wellsite Preparations
S h e l l EP Le
Le a r n i n g
2
The Tools
z The Rig
Hoisting
Rotating
Pumping
Well Control
Drilling Rig
S h e l l EP Le
Le a r n i n g
3
Land Rigs “Abu Dhabi/Canada”
S h e l l EP Le
Le a r n i n g
4
HELI RIG
S h e l l EP Le
Le a r n i n g
5
Fulmar Production Platform
S h e l l EP Le
Le a r n i n g
6
DRILLSHIP – Neddrill-2
S h e l l EP Le
Le a r n i n g
7
The Hoisting System
• Derrick
• Draw-works
• Crown
Block
• Traveling
Block
• Hook
• Anchor
S h e l l EP Le
Le a r n i n g
8
DRAWWORKS System
S h e l l EP Le
Le a r n i n g
9
Kelly & Rotary Table
Top Drive
1 Compensating Link
2 Rotary Swivel
3 El. Motor
4 Gear Box
5 Gear Lock
6 Swivel coupling
7 Link Tilt Actuators
8 Link Hanger
9 Knuckle Links
10 IBOP
11 Torque Wrench
12 Links
13 Drill Pipe Elevator
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
10
ROTARY
SLIPS
Slips
Elevator
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
11
Circulation
System
WASTE
PIT
S h e l l EP Le
Le a r n i n g
12
Mud Tank System
z Tubing Elevator
z Tubing Slips
z Stabbing Guides
S h e l l EP Le
Le a r n i n g
13
Tubing Tongs
z Hydraulic tongs
Electric / diesel powered hydraulic power-pack located in safe area
z Variable speed
z Torque controller
z Soft-torque features
z Safety features
Minimum interface
Interlock on jaw covers
BOP Preparation
S h e l l EP Le
Le a r n i n g
14
Preparing the Completion
z Numbering
Different options but be consistent
Number sub-assemblies A… and B…
Number Pup Joints
z Cleaning threads
No diesel or wire brushes
Fast cleaning solvents (Shellsol)
High pressure steam cleaners and air dryers
Clean pin end thread protectors as well
z Drifting
Use non-metallic API drifts (42” long)
Always drift from pin end to box end (avoids box seal damage)
Use softline or air to move drift – avoid steel cable / rods / wire
z Inspection
Check threads for galling
Check seal areas for smoothness
Ensure anti-galling treatment applied
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
15
Measurement and Pipe Tally
S h e l l EP Le
Le a r n i n g
z String Lowered
Single joint elevator removed, main elevator
installed
String picked out of slips
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
16
Mechanical Handling of Tubulars
Handling Tubulars
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
17
Tubing Elevators
Side Door
Centre Latch
Slip-Type
S h e l l EP Le
Le a r n i n g
18
Flush mounted slips
S h e l l EP Le
Le a r n i n g
19
Single Joint Compensator
S h e l l EP Le
Le a r n i n g
20
Stabbing Guides
z Over-torquing may
damage threads or seals
Cause crimping of the pin
Cause belling outwards of the box
S h e l l EP Le
Le a r n i n g
21
Tong
Features
Dual Completions
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
22
Dual Completion Tong
Torque vs Turns
S h e l l EP Le
Le a r n i n g
23
Premium Thread Requirements
z Problem:
how to determine the amount of torque going
into the seal / shoulder area.
z Solution:
accurately identify the point of initial seal
/shoulder contact and supply sufficient torque
from that point.
S h e l l EP Le
Le a r n i n g
24
Recommended field make-up torque
Size (O.D.) Nominal Wall 55 75 - 80 - 95 105 - 110 - 115
Weight Thick- ksi ksi ksi
ness
in. lb / ft in. min. opt. max. min. opt. max. min. opt. max.
5" 13.0 .253 3780 4200 4620 4110 4560 5010 4370 4850 5330
15 .296 4230 4700 5170 4630 5140 5650 4820 5350 5880
18.0 .362 5140 5710 6280 5540 6150 6760 5800 6440 7080
20.3 .408 6190 6870 7550 6840 7590 8340 7170 7960 8750
20.8 .422 6320 7020 7720 6840 7590 8340 7170 7960 8750
21.4
23.2
.437
.478
ple6470 7160 7870
24.1 .500
5½" 15.5
17.0
20.0
.275
.304
.361
ex 4230 4700 5170
4560 5060 5560
23.0 .415 6390 7090 7790 7170 7960 8750 7470 8300 9130
S h e l l EP Le
Le a r n i n g
Min
Copyright 2001 SIEP B.V
Zero
Turns Min Max
S h e l l EP Le
Le a r n i n g
25
TORQUE / TURN GRAPH
Target Torque/Turn Zone
Max
Torque
Min
Min
Copyright 2001 SIEP B.V
Zero
Turns Min Max
S h e l l EP Le
Le a r n i n g
26
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
Torque applied to
Shoulder
Torque
MSP
Shoulder Engagement
Ref
Turns
S h e l l EP Le
Le a r n i n g
27
Typical 'Non-Tapered Connection' Profile
Max
Opt
Torque applied to
Shoulder
Torque
MSP
Shoulder Engagement
Seal Interference
Shoulder Engagement
Ref
Turns
S h e l l EP Le
Le a r n i n g
28
Shoulder Detection
Max
Opt
5
Torque
4
3
1 2
Ref
S h e l l EP Le
Le a r n i n g
Max
Opt
Torque
MSP
Ref
Turns
S h e l l EP Le
Le a r n i n g
29
Minimum Shoulder Position
Max
Opt
Torque
MSP
Ref
Turns
S h e l l EP Le
Le a r n i n g
30
3rd generation torque-turn system capabilities
S h e l l EP Le
Le a r n i n g
31
Over Turns
Max
Opt
Torque
MSP
No Shoulder Detected
Max
Opt
Torque
MSP
Copyright 2001 SIEP B.V
Ref
Turns
S h e l l EP Le
Le a r n i n g
32
Shoulder below LSP
Max
Opt
Torque
MSP
LSP
MSP
Copyright 2001 SIEP B.V
Turns
S h e l l EP Le
Le a r n i n g
33
Shoulder above MSP
Max
Opt
5
4
3
2
1 5
4
3
Torque
2
1
MSP
Over-torque
Max
Opt
Torque
MSP
Copyright 2001 SIEP B.V
Turns
S h e l l EP Le
Le a r n i n g
34
Good Connection
Max
Opt
5654
0.94
2132
Torque
0.89
MSP
S h e l l EP Le
Le a r n i n g
35
Torque Poor Profile
S h e l l EP Le
Le a r n i n g
36
Torque
S h e l l EP Le
Le a r n i n g
37
Torque Turns after shoulder
Insufficient Data
Torque
S h e l l EP Le
Le a r n i n g
38
Quiz
Max
Opt
No. 1
Torque
MSP
Copyright 2001 SIEP B.V
Ref
Turns
S h e l l EP Le
Le a r n i n g
39
Max
Opt
No. 2
Torque
MSP
Ref
S h e l l EP Le
Le a r n i n g
Max
Opt
No. 3
Torque
MSP
Copyright 2001 SIEP B.V
Turns
S h e l l EP Le
Le a r n i n g
40
Max
Opt
No. 4
Torque
MSP
Ref
S h e l l EP Le
Le a r n i n g
z After Stabbing
tubular speed gradually increased by the computer until the required RPM is
reached
If torque exceeds preset safety limit, the process halts
protects the connection from excessive torque during vulnerable stage of the
make-up process.
z Running In
computer controls RPM at desired value until a preset torque below reference
torque, is reached
make-up is interrupted in a controlled manner to enable gear changing (manual).
S h e l l EP Le
Le a r n i n g
41
Computer controlled make-up …(2)
z Shoulder Point
Shoulder point identified by computer – determines if it has occurred
between LSP and MSP
If OK make-up is allowed to continue
If outside limits make-up is aborted to prevent damage to connection.
z Approach To Target
computer decreases tubular RPM as the torque value approaches the
target make-up value
When target torque is reached, the computer can either terminate the
make-up with a controlled release of the torque or go into torque hold
mode.
z Torque Hold
Computer controls torque at a constant preset level for a preset time
period.
S h e l l EP Le
Le a r n i n g
Leak Testing
S h e l l EP Le
Le a r n i n g
42
External Testing
z Leakage detected
pressure drop in water
Internal Hydro-Test
S h e l l EP Le
Le a r n i n g
43
Internal Gas Test
z Safety Note:
beware use of high gas pressures
ensure gas can escape should the connection leak
severely
Ensure wrap-around sleeve cannot be blown off
z Non-marking jaws
S h e l l EP Le
Le a r n i n g
44
Non-marking Tubing Slips
Non-Marking Jaws
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
45
CRA precautions
S h e l l EP Le
Le a r n i n g
46
Packers
SSSVs
S h e l l EP Le
Le a r n i n g
47
Reopening an OTIS DLS TRSSSV with pressure
trapped below (example only!!)
1. Pressure up the tubing string until there is an indication that the valve is being
pumped-through. (If the well is plugged below the TR-SCSSV indication of pump-
through may not be noticeable, resulting in an even higher, pressure below the
valve).
3. The pressure rating of the control line may be the limiting factor during this re-
opening operation.
4. Due to the importance of recognising WHEN the valve is pumped off-seat, the use
of a small capacity pump and continuous recorder is considered mandatory. A
wireline run may be conducted to ensure the valve is open, care should be taken not
to run/jar into a closed valve.
S h e l l EP Le
Le a r n i n g
48
SCSSSV control lines
z Control line or cable protectors that straddle the collar reduce the
number of protectors required and give protection to the control
line where they are most susceptible to damage.
z Ensure that elevators, slips, and power tubing tongs are in proper working
order, and correct dies are fitted.
z Do not use pipe wrenches for manual make up of joints. Apply pipe thread
lubricant sparingly to pin thread, and sealing areas.
z Drift each joint of tubing to ensure that no gloves, rags or other foreign bodies
have found their way inside.
z Record the serial number of each item as it is made-up in the string - this
includes the numbers marked on the tubing joints on receipt.
z Confirm the operating envelopes of the equipped are appropriate for the
expected working parameters.
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
49
Completion considerations …(2)
z Supervisors keeping tally should cross-check with each other from time to
time to ensure that the string is being made up according to the programme.
z Running a tubing string with a plug installed in a landing nipple situated close
to the bottom of the string should be avoided.
Problems with debris accumulation on top of plugs are very frequent when applying
this technique making retrieval difficult.
Pump out plugs can help to overcome this problem
z After tagging the packer with its seal assembly, ensure that any pressure
build-up in the tubing can be bled-off when running the seal assembly through
the packer to avoid seal damage.
z When carrying out pressure tests, build-up pressure slowly, in stages to the
maximum figures, maintain pressure for the recommended time, and record
on a suitable pressure recorder.
z Note that test pressures and times may be limited if the well is perforated
below the packer to be tested, since the test pressure may also act on the
formation.
z After spacing out, drift the complete string, using suitable wireline drifts.
Copyright 2001 SIEP B.V
S h e l l EP Le
Le a r n i n g
50
Depth Control
S h e l l EP Le
Le a r n i n g
S h e l l EP Le
Le a r n i n g
51
Tubular Space Out
# 236 (9.4m)
2.4m
Space Out Exercise 9.75m
# 235 (9.1m)
Top of THS
0.3m
z Permanent packer has been run and set on Hang-off Point
electric line
Tbg Hanger Sub-Assbly # 234 (9.6m)
z Completion string including anchor latch, nipple
and ELTSR has been run into the hole (ELTSR
5.4m
pinned in the fully closed position)
1.7m
# 233 (9.4m)
z Anchor latch stabbed into the top of the packer
and tested by applying some overpull (less than
the shear release force for the ELTSR).
2 x 1.5 m
How should we space out the completion?? 2x 3 m Permanent Packer
1 x 9.1m, 1x 8.6m,
1 x 9.6m 3 x 9.4m
S h e l l EP Le
Le a r n i n g
52
# 235 (9.1m)
z Top of joint 234 below HOP: # 233 (9.4m)
Landing
Joint
11.5 - (9.75 + 0.3) = 11.5 – 10.05 = 1.45m.
S h e l l EP Le
Le a r n i n g
53
Pressure Testing
S h e l l EP Le
Le a r n i n g
54
Preparing to install the X-mas Tree
S h e l l EP Le
Le a r n i n g
z tubing back pressure valve (BPV) fitted in the top of the tubing
hanger
S h e l l EP Le
Le a r n i n g
55
Tubing Hanger Valves
S h e l l EP Le
Le a r n i n g
56
X-mas Tree Installation
z Plastic injection and pressure testing should be carried out carefully and
methodically
Adhere to torque and test pressures stipulated in the programme or standard
procedures
Injection of the plastic is considerably eased if it is slightly warmed using hot water,
but it must not be melted
When pressure tests are completed, injection screws should be backed out, ports
filled with plastic packing and screws and plugs refitted in the injection ports
Following testing, the test pressure should be bled off from the test port, the test
apparatus removed and the check valves and plugs refitted.
S h e l l EP Le
Le a r n i n g
57
Well Handover
S h e l l EP Le
Le a r n i n g
S h e l l EP Le
Le a r n i n g
58