You are on page 1of 16

Client: INJAZ Development Co.

Project: Al Marina Development PAGE


PACKAGE 1 DW / 1
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

DAYWORK SCHEDULE

DAYWORKS RATES FOR LABOUR

Payment at labour Dayworks rates shall apply to labour


authorised by the Engineer to be employed on Dayworks,
calculated from the actual hours certified by the Engineer as
having been worked by such labour on the authorised
Dayworks.

The rates inserted shall include for Contractor's overhead,


profits and the items listed below:

• Recruitment charges, including in respect of imported labour


the cost of transportation to and from country of origin, and all
other associated costs;

• Establishment charges;

• Statutory requirements in respect of the employment of


labour, labour permits, Workmen's Compensation Insurance
in accordance with the Conditions of Contract, training levy,
non-contributory sick pay, gratuities;

• Obligations under contracts of employment;

• Housing costs;

• Subsistence allowances;

• Food allowances;

• Medical treatment;

• Travel allowances (fare and/or time);

• Transport to or from the Site or about the Site;

• Contributions to redundancy payments;

• Payments in respect of time lost due to


inclement weather;

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 2
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR
Total - SAR N.A.
Carried to Collection

DAYWORKS SCHEDULE (CONT'D)

DAYWORKS RATES FOR LABOUR (CONT'D)

The rates inserted shall include for Contractor's overhead,


profits and the items listed below (Cont'd):

• Reduced productivity during Ramadan;

• Public and other holidays with pay;

• Overtime;

• Incentive bonuses;

• Executive superintendence;

• The cost of foremen and gangers employed on supervision


only;

• Time keeping;

• Protective clothing and safety equipment;

• The use and maintenance of small tools (such as picks,


shovels, spades, wheel barrows, trowels, crow bars, hand
saws, buckets, trestles, hammers, chisels and all items of
a like nature), appliances and small plant;

• Extended use of standing scaffolding and plant;

• Any cost of overhead charges in respect of camp


administration, welfare, and any other costs or allowances;

• Head office charges and profit;


Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 3
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR N.A.


Carried to Collection

DAYWORKS SCHEDULE (CONT'D)

DAYWORKS RATES FOR LABOUR (CONT'D)

A Chargehand hr Rate Only

B Ganger hr Rate Only

C Crane driver hr Rate Only

D Carpenter hr Rate Only

E Steel fixer/bar bender hr Rate Only

F Welder hr Rate Only

G Pipe Fitter hr Rate Only

H Painter hr Rate Only

J Labourer - semi skilled hr Rate Only

K Banksman/Greaser hr Rate Only

L Steel erector hr Rate Only

M Watchman hr Rate Only

N Mason/concrete finisher hr Rate Only

P Heavy vehicle driver hr Rate Only

Q Light vehicle driver hr Rate Only

R Electrician hr Rate Only

S Cable jointer hr Rate Only

T Plant operator (Heavy) hr Rate Only

U Plant operator (Light) hr Rate Only


Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 4
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR N.A.


Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 5
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

DAYWORKS SCHEDULE (CONT'D)

DAYWORKS RATES FOR LABOUR (CONT'D)

A Scaffolder hr Rate Only

B Drainlayer hr Rate Only

C Plasterer hr Rate Only

D Plumber hr Rate Only

E Diver hr Rate Only

F Mechanic hr Rate Only

Total - SAR N.A.


Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 6
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
Total - SAR SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 7
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

DAYWORKS SCHEDULE (CONT'D)

DAYWORKS RATES FOR MATERIALS

The item for the cost of materials shall apply to payments


for materials produced by the Contractor or purchased
materials authorised by the Engineer for use on Dayworks.
The net quantities and weights verified by the Engineer in
accordance with his instructions shall be measured.

The rates inserted shall include for the cost of local


transport and handling from place of procurement or place of
arrival in the country to a central store on Site, the cost of
storage, insurance, superintendence, and any other costs or
allowances. Nails, screws, tying wire and the like shall not
be measured separately and the cost shall be held to be
included in the rates.

The cost of the distribution of the materials from the


Contractor's store or stockpile on Site to their position in
Dayworks shall be measured and paid under the provisions
for labour, Construction Plant employed on Dayworks with
the Engineer's authority.

A Ordinary cement to BS 12 GGBFS to BS 6699 T Rate Only

B Sulphate resisting cement to BS 4027 T Rate Only

C Mild steel plain bar reinforcement to BS 4449 sizes 12mm to Kg Rate Only
32 mm dia.

D Cold worked high tensile square twisted bar reinforcement Kg Rate Only
to BS 4461

E Steel fabric reinforcement to BS 4483, square mesh B1131 m2 Rate Only

F Steel fabric reinforcement to BS 4483, m2 Rate Only

G 40 mm coarse aggregate for concrete m2 Rate Only

H 20 mm coarse aggregate for concrete m2 Rate Only

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 8
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR
Total - SAR N.A.
Carried to Collection

DAYWORKS SCHEDULE (CONT'D)

DAYWORKS RATES FOR PLANT

The item for the cost of Construction Plant shall apply to


Plant authorised by the Engineer to be used on Dayworks.

Payment shall only be made for the time the Plant is


actually working on Dayworks as authorised by the
Engineer and certified by him. Idle time, where due solely to
the nature of the Dayworks or authorised method of
procedure, shall be paid for at one half of the rates stated in
the Plant and Marine Plant Schedules. Idle time due to
breakdowns, inefficiency or incompleteness of the Plant
shall not be paid.

The rates inserted shall include for the cost of electric


power, water, fuel, oil and other consumable stores and
equipment, power cables, delivery or suction pipes and
fittings, steam or air hoses and tackle and all other
appurtenances of whatever nature required for the efficient
and safe working of Plant, including maintenance, spare
parts, drill bits and points and all costs of repairs,
depreciation, insurances, superintendence, and any other
costs or allowances and inclusive of the cost of operators
and drivers.

Contractor to indicate type, size or capacity as appropriate.

A Excavators
Hydraulic excavator back hoe......…….. hp hr Rate Only
Digger and loader ....................................… hp hr Rate Only

B Tractors
Tractor, including dozer attachments …….hp hr Rate Only

C Loaders
Wheel-loader .................................................hp hr Rate Only

D Graders
Grader ...............................................hp hr Rate Only
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 9
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR N.A.


Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 10
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

DAYWORKS SCHEDULE (CONT'D)

DAYWORKS RATES FOR PLANT (CONT'D)

A Trenchers
Trencher hr Rate Only

B Rollers & Compactors


Vibrating self-propelled ..........................… hp hr Rate Only
3 wheel smooth tyred roller .........................hp hr Rate Only

C Rollers & Compactors


Vibrating self-propelled ....................… hp hr Rate Only
3 wheel smooth tyred roller ...................hp hr Rate Only

D Cranes
Mobile crane lift capacity 30 t or greater hr Rate Only

E Dump Trucks
Dump trucks 14m³ body hr Rate Only
Dump trucks 9 m³ body hr Rate Only
Dumper, capacity 1 m³ hr Rate Only

F Mobile compressor; capacity ......... m³/ min


including tools and hoses hr Rate Only
Pneumatic breaker, including steels hr Rate Only

G Pumps
Portable pump, capacity 2" hr Rate Only
Submersible pump 20 kW hr Rate Only
Dewatering pump day Rate Only
Dewatering pump week Rate Only

H Generators
Generator set, size 35 kVA hr Rate Only

J Concreting plant
Concrete batching plant, wet capacity 25 m³ hr Rate Only
Concrete poker vibrator hr Rate Only

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 11
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR
Total - SAR N.A.
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 12
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

DAYWORKS SCHEDULE (CONT'D)

DAYWORKS RATES FOR PLANT (CONT'D)

A Road vehicles
Tipper lorry, capacity 20 t
Light pick up 1 t capacity hr Rate Only
Water bowser, capacity ...................... litres hr Rate Only

B Welding and burning equipment

C Oxy-acetylene cutting, welding and burning equipment hr Rate Only


Electric welding set hr Rate Only

D Bulldozer (D6 or equivalent ) including operator hr Rate Only

E Bulldozer (D7 or equivalent ) including operator

F Concrete mixer, closed drum with hopper, any type of drive, hr Rate Only
fuel, all consumable stores and spares, capacity 10/7

G Dumper, fuel, all consumable stores and spares, capacity 3 hr Rate Only
ton tipper

H Motor lorry, fuel, all consumable stores and spares, hr Rate Only
capacity 3 ton tipper

J Wheel loader Cat 986 (or equivalent) including operator hr Rate Only

K Back hoe Cat 225 (or equivalent) including operator hr Rate Only

L Back hoe Cat 235 (or equivalent) including operator hr Rate Only

M Dump truck 20 tons (or equivalent) including operator hr Rate Only

N Dump truck 35 tons (or equivalent) including operator hr Rate Only

P Tractor and low bed trailer (or equivalent) including operator hr Rate Only

Q Roller 25T (or equivalent) including operator hr Rate Only

R Truck with 10 m3 tipper (or equivalent) including operator hr Rate Only

S Truck with 20 m3 tipper (or equivalent) including operator hr Rate Only

Total - SAR N.A.


Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 13
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
Total - SAR SAR
Carried to Collection

OVERHEAD AND PROFIT PERCENTAGE TO BE APPLIED


TO VARIATIONS / PROVISIONAL SUMS

The item for overhead and profit percentage uplift shall apply
to all Variations authorised by the Engineer.

The percentage inserted shall be applied to all variations and


shall include all overheads and profit.

The percentage inserted for overheads and profit shall not be


amended or changed unless instructed by the Engineer.

A The Contractor is to include here a percentage to be applied


to all variations for overhead and profit. % Not Extended
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 DW / 14
NUMBER
Bill of Quantities DAYWORK SCHEDULE
Infrastructure Construction

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR N.A.


Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
SECTION C
NUMBER
Bill of Quantities DAYWORK SCHEDULE
DW / S
Infrastructure Construction

Amount
Ref Description
SAR

DAYWORK
J WATERPROOFING
SCHEDULE

COLLECTION

Page DW / 1 N.A.

Page DW / 2 N.A.

Page DW / 3 N.A.

Page DW / 4 N.A.

Page DW / 5 N.A.

Page DW / 6 N.A.

Page DW / 7 N.A.

Page DW / 8 N.A.

Page DW / 9 N.A.

Total - SAR
Carried to Grand Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
SECTION C
NUMBER
Bill of Quantities DAYWORK SCHEDULE
DW / S
Infrastructure Construction

Amount
Ref Description
SAR
Total - SAR N.A.
Carried to Grand Summary