You are on page 1of 13

ISSN (Print): 0974-6846

Indian Journal of Science and Technology, Vol 11(37), DOI: 10.17485/ijst/2018/v11i37/130775, October 2018 ISSN (Online): 0974-5645

Total Productive Maintenance in a Manufacturing


Industry: A Case Study of JISHU HOZEN
Implementation
Hemlata Vivek Gaikwad*
Department of Management Studies, Rajarambapu Institute of Technology Islampur – 415414, Maharashtra, India;
hemlata.gaikwad@ritindia.edu

Abstract
Objectives: To study the effectiveness and implementation of Jishu Hozen (JH) Pillar activity in achieving zero defects, zero
accidents, zero breakdown and zero wastages. Methods/Statistical Analysis: A unique approach was adopted based on
Action Research. A spiral of cycles involve planning, observing and analyzing. An Action Research team of organization’s
personnel was specially formed to carry out the necessary experiments and analysis using the Jishu Hozen pillar of total
productive maintenance. Findings: The Overall Equipment Effectiveness (OEE) of Alfing has increased over a period of
4 months. But still it has not reached up to World Class Goals i.e 85%. The actual production of the company is very less as
compared to the planned production. As a result the performance rating of the machine is very low which affects the overall
equipment effectiveness. So the company has to take some measures to increase their daily production as per the capacity
of the machine and achieve their targets of planned production. The uniqueness about the study is that Jishu Hozen
pillar is used in this study for studying overall effectiveness whereas the other papers reviewed had used all five pillars
of Total Productive Maintenance (TPM). Application/Improvements: By implementing JH activity, the responsibility and
belongingness of the employees is increased and the overall efficiency is increased by 85%.

Keywords: Kaizen, Overall Equipment Efficiency, Total Productive Maintenance (TPM), Zero Defects

1. Introduction product quality3. For most of asset-intensive industries the


maintenance costs are a significant portion of the opera-
Over past decade, various world classes innovates tech- tional cost, the maintenance expenditure accounts for
niques and management practices such as Just In Time 20–50% of the production cost for the industry depend-
(JIT), total quality maintenance, Total Productive ing on the level of mechanization4. If the right kind of
Maintenance (TPM), lean manufacturing, group tech- maintenance strategy is correctly implemented, there is
nology etc., are being implemented by manufacturing a visible positive effect on the production. Maintenance
companies. With these optional procedures, high quality has potential impact on controlling the cost of material,
products can be provided with minimum cost and line1. manpower, tools, and overhead5.
A global marketing survival in the dynamic and competi- TPM is a crucial maintenance program change maxi-
tive arena uninterrupted equipment will play a major role mizing machine utilization and hold emergency and
in increasing their productivity2. Hence it is important unscheduled maintenance to a minimum.TPM imple-
to improve the quality of maintenance as it a effects the mentation not only improves equipment efficiency and
overall equipment efficiency and consequently, the final effectiveness but at the same time results in reduction

*Author for correspondence


Total Productive Maintenance in a Manufacturing Industry: A Case Study of JISHU HOZEN Implementation

of manufacturing cycle time, size of inventory, custom- implementation. Section 3 deals with the excellence sys-
ers complaints. It also creates cohesive small autonomous tem developed at the concerned manufacturing industry
teams and increase the confidence and skills of indi- (Figure 1). Section 4 discusses in detail the steps involved
viduals6. The main objective of this paper is to study the in the implementation of TPM with special focus on JH
effectiveness of TPM implementation with special focus pillar starting with step 0 to step 7. Section 5 discusses the
on the first pillar Jishu Hozen at one of a world class results of the implementation and its analysis. It also dis-
manufacturing company and its impact on overall equip- cusses the problems encountered in implementation and
ment efficiency of the machines. The next section 2 of how they were overcome. The last section discusses the
the paper deals with the literature review of TPM and its conclusion of the study and implications.

Figure 1.  Excellence system at the manufacturing industry.

2 Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology
Hemlata Vivek Gaikwad

2.  Literature Survey 2.1.1  What is JISHU – HOZEN?


2.1.1.1  Individually Preserving Related Equipment
TPM: Total Productive Maintenance originally devel-
oped by Japan Institute of Plant Maintenance is being “I am working on the machine, so it is my responsibility to
viewed as the latest development in the evolution of maintain it” is the main principle in the TPM concept.
maintenance methods. TPM identified and affects all Many failures can be prevented if operators perform some
courses of equipment malfunctions and breakdown tightening, oiling, and cleaning. Malfunctions occur
and eliminates all concepts losses due to breakdown. that could have been avoided if operators had touched
The maintenance methods have evolved over time or moved equipment, because they could have sensed
through: abnormalities then.
This requires deviation of thinking that “failures are
1. Corrective or emergency or breakdown maintenance, the fault of the maintenance staff ” or that “failure was
2. Productive maintenance, caused because the wrong equipment was installed and I
3. Productive maintenance, have nothing to do with it”.
4. Productive maintenance ahead, and Jishu Hozen activities means that individual workers
5. Total productive maintenance. vary out routine inspection, oiling, parts replacement,
repair early detection of abnormalities, and precision
TPM includes: checking of their own equipment for the purpose of “pro-
tecting their own equipment”.
1. Restoring equipment to a new like condition,
2. Involving operation in maintenance of the machines 2.1.2  Becoming Expert Equipment Operators
and equipment operated by them,
The following capabilities are necessary for operators:
3. Training the labour force to improve their job skills,
4. Improving maintenance efficiency and effectiveness,
• Capability of firmly setting criteria for normality’s/
and
abnormalities (ability to set conditions,
5. Effectiveness using predictive and predictive mainte-
• Capability of abiding by condition-controlling rules
nance technology.
(ability to observe rules), and
• Capability of taking proper steps in the event
TPM is a comprehensive system including the
of abnormalities (ability to repair and handle
activities like restoring deterioration of equipment and
properly).
machines improving weakness of design of equipment
and machines, improving operation and maintenance
Persons who can meet these conditions are rightly
skills.
called expert equipment operators, who are able to
TPM helps to maintain process capability high stan-
find abnormalities in the cause family, sense probabili-
dards of quality and reliability continuous improvement
ties of defect or failure, and take steps to prevent their
and has a strong strategic relevance like TQM.
occurrence.
The concept of technology is used in the TPM model
like illustration, planned maintenance, replacements top
2.1.3  Targets of Jishu-Hoshen
management support, formation of a large committee and
a TPM program team • There are 3 main targets of JH. Improving the machine
condition by bringing together the maintenance and
2.1 Autonomous Maintenance (JISHU – production people and to see that the machine will
always remain in good condition,
HOZEN)7 • Prevent the forced deterioration of the machine develop
Let us now study Jishu – Hozen in detail: the ability in the production people for everyday

Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology 3
Total Productive Maintenance in a Manufacturing Industry: A Case Study of JISHU HOZEN Implementation

inspection, of the machine. It includes everyday clean- • Preparation of tentative standards and check sheet,
ing, inspection, oiling, simple repairs and changing • Visual control list,
worn-out parts, etc., • Visual controls for clirt time reduction,
• With JH activity the operators get better knowledge • Implementation of JH check sheet, and
about the machine. How the machine works? What • Audit report of JH step - 3.
is the root cause of commonly occurring problems?
How can we prevent them? Etc. Also it helps in finding Step 4: General Inspection
out the abnormalities quickly and taking corrective Step 5: Autonomous Inspection
actions over them, and
• The operators, the maintenance and the engineering Step 6: Standardization
dept should work hand in hand to promote the work- Step 7: Full Autonomous Maintenance
ing efficiency and reliability of the machine. Above all there is a step 0 which we call as prepara-
tory step or preliminary step. In this step we prepare
Thus achieving zero breakdowns in machine, giving a cleaning and lubrication map, do the arrangement
zero defect products and working in safe and zero acci- of cleaning tools and other materials, arrangement
dents working condition are main targets of Jishu Hozen. of red and white tags, training on JH pillars is given
to maintenance people, defining machine selec-
2.1.4  JH 7 Steps Methodology Approach tion criteria and machine wise JH activity plan is
S tep 1: Initial clean up. That means cleaning with done.
meaning
Approach for step 1 activities: 3. Case Study of Manufacturing
• Initial clean up and identification of abnormality,
Industry
• Preparation of abnormality tag matrix, The organization is a Multinational Company of Indian
• List and countermeasure against abnormality, origin and a technologically advanced global leader
• Type and effect of abnormality, in metal forging, having its presence across eleven
• Tag removal plan, manufacturing locations, in several sectors including
• Good to find case, oil and gas, automotives, non-automotives, locomo-
• One point lesson, and tives, construction and mining, marine and aerospace.
• Audit report of JH step -1. The company today has the largest storage of metal-
lurgical knowledge in the region and offers full service
S tep 2: Counter measures against sources of supply capability to its geographically dispersed cus-
contamination and hard to access areas tomers from concept to product design, engineering,
Approach for step 2 activities: manufacturing, testing and validation. It is world’s no.1
forging industry with its manufacturing units spread
• Sources of contamination and hard to access area for across India, Germany, Sweden, France and China. It
CLIRT, manufactures a wide range of high performance, critical
• List and countermeasure for source of contamination, and safety components for automotive and non-auto-
• List and countermeasure for hard to access area, motive sector.
• Result for CLIRT, and
• Audit report of JH step - 2.
4. Implementation of Jishu
Step 3: Preparation of tentative standards and visual Hozen
management We started from the step 0 of JH activity implementation
Approach for step 3 activities: on Alfing at Crankshaft Line 3.

4 Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology
Hemlata Vivek Gaikwad

Step 0 - Preparatory Step list of abnormalities and conditions to what abnor-


- Arrangement of tools and equipment required for clean- mality will lead to,
ing of the machine and its nearby areas. For example: - Then a list of abnormal conditions was prepared
Gloves, cotton waste, nylon brush, wire brush, span- and countermeasures against these abnormalities
ners, shovel, allen keys, hammer, screw drivers, etc., were suggested. The table contains a list of abnor-
- Arrangements of red and white tags to be put at some mal items, why the items became abnormality, what
places on the machine where the abnormalities are will happen if it is left as it is and what are the coun-
identified, termeasures to remove these abnormalities,
- White tags denote the activities that are to be done - Using the data from the abnormality tag matrix, a pie
by the operator of the machine himself. For example: chart is obtained classifying the types of abnormalities
Tightening of loose bolts, Replacement of missing and showing, to what these abnormalities will lead to
parts, filling up of lubrication, Fixing of covers, clean- (breakdown, cost increase, quality defects or safety),
ing the covers, and - Then the tag removal plan is implemented where the
- Red tags denote the activities that are to be done operator and the maintenance department people
by planned maintenance department. For exam- work on removing and correcting the abnormalities
ple: Rerouting of cables, Arresting oil leakages, and fixing them. One abnormality is corrected then
Replacement of worn out machine parts. its tag is removed, and
- A tag status sheet was prepared which showed the
Step 1: Initial Cleaning daily status of the tags. For example: how many tags
were put and how many are removed.
We started this step with cleaning the rusted and oily
areas of the machine and identification of abnormalities S tep 2: Counter Measures Against Sources of
in the machine.
Contamination and Hard to Access Areas
 utting of Red and White Tags on the Tree
P - Some measures are taken against sources of con-
tamination and hard to access areas. These ways are
Stand Kept Near Alfing (Figure 2)
implemented so that the problems are cleared and
- After all the abnormalities were identified a sheet was there is lesser breakdown of machine, and
prepared called Abnormality Tag Matrix, - The abnormalities were inspected and necessary
- This sheet contains exact description of location that actions were taken to avoid the occurrence of the
is at which part of the machine is abnormality found, abnormalities.

S tep 3: Preparation of Tentative Standards and Visual


Management
- In this we prepare a CLIRT sheet which consists
some columns showing parts of machine, activities
to be done on that parts, standards, method of iden-
tifying the abnormalities, tools used to remove the
abnormalities, if something is abnormal then what
action should be taken, time required to performs
the action, frequency and responsibility i.e. by whom
should the count. So a CLIRT sheet for Alfing was
prepared which shows the summary of all actions
to be carried out on Alfing as countermeasures against
source of contamination and hard to access areas.
Figure 2.  Putting of red and white tags on the tree stand
kept near Alfing.

Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology 5
Total Productive Maintenance in a Manufacturing Industry: A Case Study of JISHU HOZEN Implementation

5. Discussion
5.1 Evaluating the Overall Equipment Effectiveness (OEE)

Calculations for Availability Rating


Availability Hours − Breakdown Hours
Availability Rating = × 100
Availability Hours

Breakdown time in mins.


April 965
May 1605
June 750
July 1110
Available Hours: 1310 daily, 39300 monthly
(Available Hours − Breakdown Hours) /
Available Hours × 100
Availability Rating for April =
× 100
(39300 − 965) / 39300×

97.54%

(Available Hours − Breakdown Hours) /


Available Hours × 100
Availability Rating for May =
(39300 − 1605) / 39300 × 100
95.91%
(Available Hours − Breakdown Hours) /
Available Hours × 100
Availability Rating for June =
(39300 − 750) / 39300 × 100

98.09%

(Available Hours − Breakdown Hours) /


Available Hours × 100
Availability Rating for July =
(39300 − 880) / 39300 × 100

97.76 %
Actual Production
Performance Rating = × 100
Planned Production
Total Production gained in nos.
April 2015
May 3874
June 4120
July 4145

6 Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology
Hemlata Vivek Gaikwad

Planned Production( as per cycle time): 174 nos. daily, 5220 nos. monthly
Actual Production /
Planned Production × 100
Productivity Rating for April =
2015 / 5220 × 100
38.60%
Actual Production /
Planned Production × 100
Productivity Rating for May =
3874 / 5220 × 100
74.21%
Actual Production /
Planned Production × 100
Productivity Rating for June =
4120 / 5220 × 100
78.92%
Actual Production /
Planned Production × 100
Productivity Rating for July =
4145 / 5220 × 100
79.40%
Numbre of OK parts
Quality Rating = × 100
Total Production
Production of OK parts
April 2015
May 3874
June 4119
July  4145
Number of OK parts / Total production× 100
Quality Rating for April =
2015 / 2015 × 100
100%
Number of OK parts / Total production × 100
Quality Rating for May =
3874 / 3874 × 100
100%
Number of OK parts / Total production × 100
Quality Rating for June =
4119 / 4120 × 100
99.97%
Number of OK parts / Total production × 100
Quality Rating for July =
4145 / 4145 × 100
100%

Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology 7
Total Productive Maintenance in a Manufacturing Industry: A Case Study of JISHU HOZEN Implementation

Calculations for Overall Equipment Effectiveness


Overall Equipment Effectiveness = Availability Rating × Performance
Rating × Quality Rating
For the Month of April
OEE = A × P × Q
0.9754 × 0.386 × 1
0.3765
37.65%
For the Month of May
OEE = A × P × Q
0.9591 × .7421 × 1
0.7117
71.17%
For the Month of June
OEE = A × P × Q
0.9809 × 0.7892 × 0.9997
0.7738
77.38%
For the Month of July
OEE = A × P × Q
0. 9776 × 0.7940 × 1
0.7762
77.62%
Month April May June July
Effectiveness in Percentage 37.65% 71.17% 77.38% 77.62%

Figure 3.  A gradual increase in overall equipment effectiveness of Alfing.

8 Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology
Hemlata Vivek Gaikwad

We can see that, implementation of Jishu Hozen activ- Defect & Rework Loss, Planned Shutdown Loss and
ity up to step 3 on Alfing has lead to increase in overall Setup & Adjustment Loss are four major losses occurring
equipment effectiveness of that machine. But still it has at CL3 in Figure 4. These four losses nearly contribute to
not reached up to World Class Goals i.e. 85% in shown 85% of total losses. The down time of four major losses is
in Figure 3. 17533 minutes = 293 hrs = 13 days (approx).
Analysis and Interpretation of 16 losses for the month Around 50% of losses occurred due to Failure Loss
of June: which contributed to 196 occurrences of the total. So we
There are total 358 occurrences of different type can rightly interpret that the breakdowns in machines
of losses and the total down time of all the losses is at CL3 largely occurred due to Failure Loss as shown in
20673 minutes = 344 hrs = 15 days (approx). Failure Loss, Figure 5.

Figure 4.  Graphical representation of major losses that occurred.

Figure 5.  Graphical presentation of percentage-wise losses.

Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology 9
Total Productive Maintenance in a Manufacturing Industry: A Case Study of JISHU HOZEN Implementation

Failure loss is among the major losses occurring at The analysis of frequency of various problems or rea-
CL3. The total down time of Failure Loss is 10413 minutes sons due to which Failure Loss occurs in machines in
= 174 hrs = 7.25 days (approx). Figure 6 shows machines Figure 7 shows that majority of the times the machine
on which failure loss occurs maximum times are found breakdown occurs largely due to breakage of the probe
out. stick, drive problem, lubrication problem, drill load prob-
Analysis of Failure Loss on the basis of frequent break- lem, etc. So if we want to eliminate the losses then we have
down for June: to correct the reasons behind occurrence of these losses.

Figure 6.  Graphical representation of percentage of failure loss versus machines.

Figure 7.  Graphical representation of frequency versus breakdown reason.

10 Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology
Hemlata Vivek Gaikwad

Counter measure plan for June: of all the losses is 26282 minutes. These four losses nearly
4W1H sheet (Kaizen Sheet) is made showing the steps contribute to 87% of total losses (Figure 8). The down
to be taken for elimination of losses. time of four major losses is 22947 minutes i.e. 382.45 hrs
Analysis and Interpretation of 16 losses for the month and 16 days (approx).
of July: Around 48.44% of losses occurred due to Failure Loss
We see that Failure Loss, Planned Shutdown Loss, which contributed to 177 occurrences of the total. So we
Defect & Rework Loss, and Cutting Blade Loss are four can rightly interpret that the breakdowns in machines
major losses occurring at CL3. There are total 382 occur- at CL3 largely occurred due to Failure Loss as shown in
rences of different type of losses and the total down time Figure 9.

Figure 8.  Graphical representation of major losses that occurred.

Figure 9.  Graphical presentation of percentage-wise losses.

Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology 11
Total Productive Maintenance in a Manufacturing Industry: A Case Study of JISHU HOZEN Implementation

Failure loss is among the major losses occurring at Figure 11 shows in frequency of various problems or
CL3. The total down time of Failure Loss is 12732 min- reasons due to which Failure Loss occurs in machines.
utes = 212 hrs = 8.84 days (approx). The machines on Majority of the times the machine breaks down due
which failure loss occurs maximum times are found out to Z-axis thermal alarm under engineering, X-axis
in shown in Figure 10. thermal alarm, under maintenance for Drive problem,
Analysis of Failure Loss on the basis of frequent break- etc. So if we want to eliminate the losses then we have
down for July: to correct the reasons behind occurrence of these
Problems on Individual Machines losses.

Figure 10.  Graphical representation of percentage of failure loss versus machines.

Figure 11.  Graphical representation of frequency versus breakdown reasons.

12 Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology
Hemlata Vivek Gaikwad

6. Conclusion be adapted to work in a variety of situations. If every-


one involved in a TPM program does his or her part,
From the above calculations, the researcher is able to con- an unusually high rate of return compared to resources
clude that the OEE of Alfing has increased over a period invested may be expected.
of 4 months. But still it has not reached up to World Class
Goals i.e. 85%. The actual production of the company is
very less as compared to the planned production. As a 7. References
result the performance rating of the machine is very low 1. Werner T, Weckenmann A. Sustainable quality assurance
which affects the overall equipment effectiveness. So the by assuring competence of employees, Measurement.
company has to take some measures to increase their 2012; 45(6):1534−39. https://doi.org/10.1016/j.measure-
daily production as per the capacity of the machine and ment.2012.02.025.
achieve their targets of planned production. Once the 2. McKone K, Schroeder R, Cua K. The impact of total produc-
daily production increases, the OEE of machine will also tive maintenance practices on manufacturing performance,
increase up to 85%. The implementation of JH activity Journal of Operations Management. 2001; 19(1):39−58.
has lead to increase of overall equipment effectiveness of https://doi.org/10.1016/S0272-6963(00)00030-9.
3. Hansson J, Backlund F, Lycke L. Managing commitment:
Alfing.
Increasing the odds for successful implementation of
By implementing the Jishu Hozen activity on Alfing,
TQM, TPM or RCM, International Journal of Quality and
firstly a feeling of belongingness and responsibility was Reliability Management. 2003; 20(9):993−1008. https://doi.
created in the minds of operator by making him the owner org/10.1108/02656710310500815.
of that machine. The operator became more responsible 4. Parida A, Chattopadhyay G. Development of a multi‐
and began to take more care of the machine. Secondly criteria hierarchical framework for Maintenance
different types of losses were identified that could have Performance Measurement (MPM), Journal of Quality in
led to breakdown of the machine. The machine would Maintenance Engineering. 2007; 13(3):241−58. https://doi.
have also produced defective jobs which can be avoided org/10.1108/13552510710780276.
by preparing a counter measure plan to eliminate these 5. Pintelon L, Gelders L. Maintenance management decision
losses using kaizen sheet. Due to the implementation of making, European Journal of Operational Research. 1992;
JH activity the machine looked cleaner and free from 58(3):301−17. https://doi.org/10.1016/0377-2217(92)90062-E.
6. Ahmed S, Hj. Hassan M, Taha Z. TPM can go beyond
defects. This is one step forward towards achieving the
maintenance: Excerpt from a case implementation, Journal
goal of zero breakdowns, zero defects, zero wastage and
of Quality in Maintenance Engineering. 2005; 11(1):19−42.
zero accidents. Today, with competition in industry at
https://doi.org/10.1108/13552510510589352.
an all-time high, TPM may be the only thing that stands 7. Telsang MT. Industrial Engineering and Production
between success and total failure for some companies. Management. 6th Edition. New Delhi: S Chand & Company;
It has been proven to be a program that works. It can 2009.

Vol 11 (37) | October 2018 | www.indjst.org Indian Journal of Science and Technology 13

You might also like