Professional Documents
Culture Documents
INSTITUTE OF TECHNOLOGY
SCHOOL OF ARCHITECTURE AND CONSTRUCTION
TECHNOLOGY AND MANAGEMENT
PREPARED BY:
ABABO BICHAKA
MERON DEGU
MERON YADESSA
SEADA ABDU
SELAM AMDISA
GONDAR, ETHIOPIA
UNIVERSITY OF GONDAR
INSTITUTE OF TECHNOLOGY
SCHOOL OF ARCHITECTURE AND CONSTRUCTION
TECHNOLOGY AND MANAGEMENT
PREPARED BY ID NUMBER
GONDAR, ETHIOPIA
i
Declaration
We hereby declare that this thesis submitted by us in partial fulfillment of the requirements of
BSc degree in Department of Construction Technology and Management is our original work
carried out with the guidance of our advisor Samson Worku. It does not refer to writing of
others without stating it both in the text and reference. This thesis has not been submitted for
any degree in this or any other University.
ii
Acknowledgment
We would like to show gratitude to our advisor Mr. Samson Worku for his helpful comments,
consistent support and guidance for the completion of this thesis.
We would also like to thank the department of construction technology and management for
giving us support when we needed it.
Last but not least we would like to thank everyone who was willing to answer our questions
and gave us the information we required in the Construction Projects of University of
Gondar.
iii
Abstract
The construction projects in the University of Gondar are delayed due to different reasons.
The fact that the projects are delayed has a negative impact on the client, contractor and
consultant. They need to be questioned for the delay that has occurred since they can control
each activity in the construction.
The general objective of this research paper is to assess the cause and effects of delay in the
construction projects of University of Gondar. And the specific objectives are to identify the
causes and effects of delay, to recommend the possible solutions to minimize delay in the
construction projects of University of Gondar.
Data was collected through self administered questionnaire. The sampling technique is
simple random sampling. The data was analyzed by Relative importance index. The research
is quantitative therefore results were obtained by generalizing numerical data.
The result of this study implied that the client and the contractor have high contribution
factor for the cause of delay. The consultant has medium contribution factor and external
factors have very low contribution factor.
It is recommended that the client shall secure the removal of obstructions that prevents the
building before handing over projects the client should finish on time. The contractor should
work with the other stake holders in cooperation to avoid delay. The consultant should submit
and review designs also approve this design and provide proper inspections on time. And also
more research on construction delays should be done in order to develop guidelines, or
methods of minimizing the effects of construction delays
Table of Contents
iv
Senior Essay Approval................................................................................................................i
Declaration.................................................................................................................................ii
Acknowledgment......................................................................................................................iii
Abstract.....................................................................................................................................iv
List of Table............................................................................................................................viii
List of Figure.............................................................................................................................ix
CHAPTER ONE.......................................................................................................................1
1. INTRODUCTION................................................................................................................1
1.3. Objective.........................................................................................................................2
CHAPTER TWO.....................................................................................................................5
2. LITERATURE REVIEW....................................................................................................5
2.1. Definition........................................................................................................................5
v
2.3.2. The cause of construction delay by client..............................................................12
2.4.3. Dispute...................................................................................................................17
2.4.4. Arbitration..............................................................................................................18
2.4.5. Litigation................................................................................................................18
CHAPTER THREE...............................................................................................................23
3. RESEARCH METHODOLOGY.....................................................................................23
3.1. Introduction...................................................................................................................23
vi
CHAPTER FOUR..................................................................................................................29
4.1. Introductions.................................................................................................................29
CHAPTER FIVE....................................................................................................................47
5.1. Conclusion.....................................................................................................................47
5.2. Recommendation...........................................................................................................48
Reference..................................................................................................................................49
Appendix..................................................................................................................................51
Questionnaire.......................................................................................................................51
vii
List of Table
Table 3.1 : Likert scale questionnaire for causes and effect of delay......................................27
Table 4.1 : Survey Response....................................................................................................29
Table 4.2 : Survey respondents’ experience............................................................................30
Table 4.3 : Frequency level of the causes................................................................................33
Table 4.4 : Total value by multiplying frequency by importance degree................................36
Table 4.5 : Determination on average RII................................................................................38
Table 4.6 : Frequency level for each effects of delay..............................................................43
Table 4.7 : Calculating total value by multiplying frequency by importance degree..............44
Table 4.8 : Determination of RII and rank of the effects.........................................................45
List of Figure
viii
Figure 1.1: Research Structure...................................................................................................3
Figure 2.1: Types of delay.........................................................................................................6
Figure 2.2: Effects of Delay.....................................................................................................16
Figure 3.1 : Research Design...................................................................................................24
Figure 4.1 : Experience of respondents per year......................................................................30
Figure 4.2 : Percent of construction building in the present time............................................31
Figure 4.3 : Occurrence of delay of the construction project of University of Gondar...........31
Figure 4.4 : Rank of major causes of delay on the project.......................................................43
Figure 4.5 : Rank of effects of delay on the project.................................................................46
ix
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
CHAPTER ONE
1. INTRODUCTION
1.1. Research Background
The construction industry can highly impact the economic growth of a country. This industry
has a high potential of affecting other industries performance. The construction industry has
laid down the physical and technological foundations upon which modern civilization has
developed. There is no aspect of human life and civilization, upon which the construction
does not have a profound influence.Therefore, problems caused in construction should be
studied critically and the techniques of eliminating the problems should be well known. One
of the most abundant problems in the construction industry is delay. (Karmer, 2018).
A contract document normally includes the commencement and completion date of a project.
However if a problem occurs during construction, the project date is extended beyond the
agreed scheduled completion date, and delay arises. Generally, the delay in the construction
sector is defined as a “time overrun after the completion of a contract or beyond the date
agreed upon by the parties for delivery of the project”. (itzhaki, 2014). Even though the
construction industry is taking a more advanced and technology based approach for
construction delay is still one of the most repeatedly occurring problems in the construction
industry. Delay can negatively affect construction. For instance time overrun, cost overrun,
disputes, arbitration, litigation, total abandonment and others. This reveals that delay is a
chronic problem in construction projects. Delays in the construction sector have become a
global phenomenon. (Haseeb, 2011)
At this time of age planning and scheduling has a huge place in construction. But during
execution of construction projects, the works proceed at a slower pace than planned, and
delays frequently appear. This maybe caused due to budget inaccuracy, labor challenge,
approval, subcontractor schedules and compliance, lack of effective communication, poor
weather condition and others. (Sambasivan, (2007)). When delays do occur, they either
accelerate or extend duration beyond the scheduled completion date. Delays interrupt of
works in progress and decreases productivity. Delay is one of the reasons a contract
terminates.
Other studies show that the main cause of delay is inappropriate project management and
claim administration. (Abd El-Razek, 2008). Due to unexpected occurrence and contract
Department of CoTM 1
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
management problems, delay occurs. This has the capacity of affecting all parties involved in
the construction. Uncertainties will be eliminated if the project is well planned and scheduled
in every aspect (time, cost, quality, quantity and scope). This senior essay includes studies
concerning causes and effect of delay in an integrated manner in construction projects of
University of Gondar.
1.2. Statement of the Problem
The construction projects in the University of Gondar are delayed due to different reasons.
The fact that the projects are delayed has a negative impact on the client, contractor,
consultant and the environment. The parties responsible for the delay need to be involved in
this type of study. They need to be questioned for the delay that has occurred since they can
control each activity in the construction.
Therefore, this research duly investigates delay causing factors in university of Gondar,
Gondar, Ethiopia to forward visible and scientific solution to improve project performance.
1.3. Objective
1.3.1. General Objective
Assessment of the Causes and Effects of Delay in Construction Projects of University
of Gondar.
Department of CoTM 2
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Department of CoTM 3
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Chapter one of this reseach contanins Background, Problem statement and Justification,
Objective, Research Question, Scope, Limitation and Research Structure.
Chapter two of this research contains reviews of former researchs and studies that are related
to this topic.
Chapter three of this reseach includes: Introducton, research designing, research Instruments,
source of data, sample size determination, questionnaire design and data analysing method.
Chapter four of this research states the result of this research in a quantitative way. And
discusses some basic points.
Chapter five concludes and gives suggestions on how to stop this problem from occuring in
the future.
Department of CoTM 4
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
CHAPTER TWO
2. LITERATURE REVIEW
2.1. Definition
Enchase et al. 2006 defines construction industry as the tool through which a society achieves
its goals of urban and rural development. It is one of the sectors that provide important
ingredients for the development of an economy. Construction industry is a fast moving
industry and as its growth it encounters many problems and of this many problems one is the
problem of delay.
Delay in construction is a global phenomenon affecting not only the construction industry but
the overall economy of countries as well (Abd El-Razek, 2008)
In construction, delay could be defined as the time overrun either beyond completion date
specified in a contract or beyond the date that the parties agreed upon for delivery of a
project. (Lo, Fung and Tung ,2006) define delay as the slowing down of work without
stopping construction entirely and that can lead to time overrun either beyond the contract
date or beyond the date that the parties have agreed upon for the delivery of the project. Also
according to (Pickavance, 2005) In construction, the word “delay’’ refers to something
happening at a later time than planned, expected, specified in a contract or beyond the date
that the parties agreed upon for the delivery of a project. (Abdul-Rahman H. B., 2006)
According to (Assaf, 2006)Excusable delays are divided into two: compensable and non-
compensable delays. Compensable delays are caused by the owner or the owner's agents.
While non-compensable delays are caused by third parties or incidents beyond the control of
both the owner and the contractor. These delays are commonly called “acts of God” because
they are not the responsibility or fault of any particular party.
(Sambasvian, 2007)Future study has added another type of delay, concurrent delays. If there
is there only one factor is delaying the construction project; it is usually quite easy to
Department of CoTM 5
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
calculate both the time and money resulting from that single issue. Concurrent delay is a
more complicated and this is very typical in construction project. This situation happened
when more than one factor delays the project at the same time or in overlapping periods of
moment.
Also (Yang, 2007)has also categorized delay in to four categories this include Critical or non-
critical delay, Excusable or non-excusable delay, Compensable or non-compensable delay
and Concurrent or non-concurrent delay.
Department of CoTM 6
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
According to (Koushki, 2005)survey stated that the most significant cause of delay in the
traditional type of contract, in perspective of contractor and consultant. It is also stated that to
imparting the economic feasibility of capital project, extensive delays provide a fertile ground
for costly deputies and claim. The result indicated the contractor and consultant agreed that
owner interface, inadequate contractor experience, finance and payment, labor productivity,
slow decision making, improper planning and subcontractor are among the top ten important
factor.
Department of CoTM 7
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
As a contractor, misquoting a job estimate can be massively detrimental; some jobs are shut
down for weeks, months or even dropped altogether. Accurate estimating ensures there is
always enough money for materials, wages, and more. Using estimating software simplifies
bids, estimates, and financial project planning and makes the process somewhat foolproof.
Moreover, once estimates are complete, contractors need an easy way to get the project in
their construction management platform and get to work.
Once the job is underway, having real-time access to data is critical to see how job progress is
matching up with job costs. Unfortunately, many contractors are still relying on non-
integrated, on-premise software solutions, which often means data reporting is delayed
between the field and office, and those tasked with analyzing project productivity are often
working from information that is days, weeks, even months old. A cloud-based, integrated
construction management solution solves this by automating workflows and delivering
powerful data and analysis tools in real time.
The biggest challenge in the construction industry today is labor. The recession triggered
more than a decade ago left its mark on the industry, as many skilled workers laid off during
the downturn left to take jobs in other industries. Few have returned, and the younger
Department of CoTM 8
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
generations of workers entering the workforce have been less and less inclined to commit to
construction careers. Technology is helping to change that dynamic, while also streamlining
the HR and labor management workflows across construction organizations.
Correctly allocating a work crew can make or break a construction timeline. Rushing from
project to project is inefficient, and risks cutting corners. Technology is making this is an
easy fix, by streamlining scheduling and time collection for labor in the field and helping
project managers determine what crews are best suited for what projects.
2.3.1.3. Approvals
Everyone at some point in their career has played the dreaded waiting game. Waiting for
someone, somewhere to make a decision that is keeping the entire project from moving
forward. As a leader or project manager on the job, you have to make decisions that keep
projects moving. Coordinating actions and approving items quickly can keep construction
jobs on time (maybe even ahead of time) and in some cases, under budget.
With the real-time accessibility, timely data and powerful functionality that modern, cloud-
based, integrated construction software provides, contractors can automate tasks and
streamline workflows that ensure the right people see the right information at the right time.
If a change request is submitted for example, a project manger gets an alert on his dashboard,
and from his mobile device can approve and create a change order. In the back office, the
accounting team sees the change updated in real time, and in the executive suite, the CFO or
owner looking at real-time job costs can see changes approved changes reflected in the
figures as they occur. This seamless flow of information between the field, office and entire
team is powered by an intuitive collaboration solution designed to connect these once-siloed
operations.
If you’re a general contractor, you typically work with a number of subcontractors for each
project. Effectively managing them, their timelines and schedules, compliance
documentation, collaboration with other contractors and more is vital to a project’s success.
Department of CoTM 9
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
When the right hand isn’t talking to the left hand, projects can get delayed, and in some cases,
done incorrectly. Whether it’s communication from an owner, client, in the field or at the
office, everyone should be apprised as new updates like change orders or redesigns, or data
like job progress or job costs become available.
Ensuring all teams are using the same set of data across the project reduces the chances for
errors from a lack of knowledge. And, communication and collaboration audit trails come in
handy if a conflict does arise, giving the general contractor confidence that teams have all the
accurate information they need at all times to resolve issues before they become a project
problem.
One thing that can’t be controlled is the weather (it would be great if we could!).
Understanding that extreme conditions can’t be controlled, allows you to be prepared,
which can make a difference. If weather is hot and humid, or cold and snowy, account for a
slower pace in the timeline, and follow safe practices for crews. When wet weather hits,
providing a work team with waterproof gear and appropriate jobs can keep things moving.
Another weather-related item that can be controlled is how your business will be impacted in
the event of a natural disaster. Should an event like a tornado, hurricane, flood, fire, or
earthquake occur, how well would you be able to carry on operations? On-premise software
and in-house data storage/servers could easily be lost in such an event along with all of your
vital data. However, operating in the cloud, with complete, secure data backups done,
automatically means that your business can continue to function even if the home office isn’t
able to.
Learn more about avoiding delays and keeping your projects running on time with
Viewpoint’s suite of integrated, cloud-based construction software. To explore all Viewpoints
has to offer, get in touch with us. We’ll show you how software can alleviate delays and keep
your construction organization moving forward. (itzhaki, 2014)
Department of CoTM 10
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
This and likes of problems that the owner are creating are leading to financial difficulties to
contractors and the pitfalls on the progress of the projects. Therefore the owners should have
to release payments on time based on contract agreement and prepare sufficient fund in
advance to avoid delay in progress payments for executed work and contractor’s financial
difficulties. So as accelerate the project progress. According to [18] financial difficulty is
defined as getting into a situation where a respondent's credit is adversely impacted, such as
not paying bills. If the contractors have problem in paying money for the materials to be used,
laborers’ salaries and equipment to be used for construction work etc. we can say that they
are really in financial difficulties. A financial difficulty of contractors has reportedly been one
of the important reasons of delay in construction projects, they all found that delay in
payment from the client would eventually cause financial difficulties to the contractor. Thus,
most of the construction works cannot be carried out due to these financial difficulties.
Furthermore, postulated that insufficient capital is one of the major causes of financial
difficulties among contractors. Poor financial control by the contractor can lead to
insufficient capital. Hence, the contractor will have excessive debt, which causes them to face
financial difficulties, as they cannot pay back the debt.
2.3.1.9. Poor coordinating and communication with other parties
Construction projects performance requires improvement to fulfill the complexity of the
stakeholders’ needs and expectations. Coordination process is proposed as an efficient
solution for on time completion of construction projects. Therefore, coordination factors are
vital in ensuring a successful implementation of all project phases.
2.3.1.10. Lack of skilled professional in construction project management
Shortage of talent in the construction sector is a long-term problem and will continue to push
up project time and costs. The education and training capacity given through various higher
Department of CoTM 11
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
institutions, organizations etc. are clearly inadequate to meet the need of the large percentage
of skilled workers in the Ethiopian construction sector. The education system is often not
delivering the required number of specialists across project management, engineering,
surveying, contract management and the skilled/semi-skilled labor. The findings of this
research work is very similar to the findings of those research which were conducted in other
developing countries like for instance, have found delay in progress payments for completed
works, low productivity of labor, infective project planning and scheduling, contractor's’
financial difficulties, and unqualified / inadequate experienced labor were the most
significant factors that causes delay in Egyptian construction projects. Identified low
productivity of labor, escalation of materials price, contractor's’ financial difficulties, and
delay in progress payments for completed works, and infective project planning were among
the significant causes of delay in Malaysian construction industry. In the same manner have
indicated that contractor’s financial difficulty, escalation of materials price, and delay in
progress payments for completed works, and late delivery of materials were among the major
cause of delay in Nigerian construction projects. This similarity in the causes of delay
outcome among different countries shows that the causes are not specific only to some places
rather they are universal.
Department of CoTM 12
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
to provide adequate funding resources to contractors for the job done will make it difficult for
the contractors to meet project objectives.
2.3.2.9. Mistakes during construction and Rework due to error
Design errors indicate the total design effectiveness of a project, major design quality
problems occur during construction when errors, omissions and ambiguities in plans and
specifications become evident (Davis & Ledbetter, 1987). A large amount of country’s
maintenance resources is being expended on corrective or remedial measures to buildings and
their services due to design or construction defects.
2.3.2.10. Inappropriate construction method
Researchers start to explore construction methods, procedures, and technologies when there
is a structural collapse. Project failures related to CMs are normally investigated from
technical or risk perspectives. They are treated as an individual case or incident (e.g., Chase
1998; Delatte 2009).
2.3.2.11. Change orders by owner during construction
Change order is work added to or deleted from the original scope of work of a contract
which alters the original contract amount or completion date. The change has been defined as
any deviation from an agreed upon well-defined scope and schedule the words “Change
Order” conjure strong feelings of negativity for all involved in construction projects
Faridi and El-Sayegh (2006) identified. Slowness in decision making process by owner,:-
slowness in owner’s decision-making process and changes in materials type and specification
during construction by the owner as factors that contribute to causes of delay under this
category.
2.3.2.12. Conflicts between joint ownership of the project
Differences in perceptions among the participants of the projects, conflicts are inevitable. If
conflicts are not well managed, they are quickly turned into disputes. Disputes are one of the
main factors which prevent the successfully completion of the construction project. Thus, it is
important to be aware of the causes of disputes in order to complete the construction project
Department of CoTM 14
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
samples by the consultant, mistake in consultant drawing ,delay in approving major changes
in the scope of work by consultant, inflexibility (rigidity) of consultant, poor communication
and coordination between consultant and other parties, late review and approval of design
documents by consultants, conflicts between consultant and design engineer, inadequate
experience of consultant. Sambasivan and Soon (2007) identified contract management,
preparation and approval of drawings, quality assurance and control and waiting time for
approval of tests and inspections as factors causing delays under the consultant-related
categories. Iyer and Jha (2012) identified the factors of inadequate project formulation in the
beginning and reluctance in timely decision by the consultant as key causes of delay. Also
Gündüz (2013) identified delay in performing inspection and testing, poor communication
and coordination with other parties, and conflicts between consultant and design engineer as
the most significant in causing delays.
Other factors Absenteeism Labor, Low motivation and morale of labor, Low productivity of
labor, Personal conflicts among labor, Shortage of labor, Strike Labor, Damage of delivered
Department of CoTM 15
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Because of these issues project members concurs for the cases for the extra capital and
additional time connected with construction delay. The consequences of delay are different
for different project participants which also depend on the type of project. The general
consequences are cost overrun, time overrun etc. For the owner/client delay is the loss of
money, loss of time, loss of other facilities etc. For the contractor, delay means the loss of
wealth for more expenditure on equipment’s, other materials and for hiring the skilled labor.
(Mr. Tushar Khattri, 2016, p. 566)
According to the study Aibinu and Jagboro, (2002) revealed six effects of delay on project
delivery in construction industry which are: time overrun, cost overrun, dispute, arbitration,
total abandonment and litigation. Haseebet (2011) identify effects of delays in construction
industry as clash, claims, total desertion and slowing down the growth of the construction
sector.
Department of CoTM 16
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Department of CoTM 17
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
decision with arbitrator. If both parties accept the decision and the fault parties will take
responsibility to pay damages for project delay.
2.4.4. Arbitration
In current delay project, some of the contractual parties do not accept the mediator decision
and they appeal in arbitration. Arbitrator will also make the decision to solve the problem.
But if one of the parties does not accept the decision again made by Arbitrator, they still can
appeal the decision in litigation.
2.4.5. Litigation
In some delay project, the relevant parties because of still do not accept with the arbitrator
decision. They are appeal the result in litigation which is dispute resolution in the courts. In
litigation, the parties have a trial either by a court alone or by jury. If those parties are not
satisfied judgment again, then they can appeal again if they have any new evidence to proof
their right. But one the parties accept with the judgment, the faulty of parties need take
responsibility to pay the penalty.
2.4.6. Total abandonment
Total abandonment it means the whole project stop immediately because of client facing
financial difficulties. The abandonment of construction projects has resulted in many adverse
consequences to the economy, society and environment. Economically, it is a waste of useful
resources it reduces employment opportunities, slows down economic activities, government
loses revenue and foreign investors get deterred from funding construction projects in the
economy. Some of the current delay project totally abandoned because of client or contractor
problem which include clients bankruptcy, contractor run away, poor marketing and sales
strategies and so on. The effect of project totally abandoned will affect many parties such as
contractual parties which include contractor, consultant, sub-contractor, supplier and some
other relevant parties. Besides those parties, the purchasers will also suffer in cost damages
due to project abandoned. According to Sambasivan and Soon (2007), client based delay,
consultant-based, labor based, and external factors pay to the overall abandonment of the
projects. According to the study, during the period of 1997-2000 several projects were briefly
abandoned due to financial problems.
Department of CoTM 18
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
a) A penalty of 0.1% or 1/1000 of the value of undelivered Service for each day of delay until
actual delivery or performance.
b) The cumulative penalty to be paid by the Contractor shall not exceed 10% of the contract
price.
Under clause 73 Extension of Intended Completion Date sub-clause 73.1 states The
Contractor may request an extension of the Intended Completion Date if he is or will be
delayed in completing the contract by any of the following causes:
b) Artificial obstructions or physical conditions which could not reasonably have been
foreseen by an experienced Contractor;
c) Compensation Event occurs or a change order for modification is issued which makes it
impossible for completion to be achieved by the Intended Completion Date;
d) Administrative orders affecting the date of completion other than those arising from the
Contractor's default;
e) Failure of the Public Body to fulfill his obligations under the Contract;
f) Any suspension of the works which is not due to the Contractor's default;
g) Force majeure;
h) Any other causes referred to in these GCC which are not due to the Contractor's default.
Department of CoTM 19
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
b)Completing all work which is stated in the contract as being required for the works or
sections to be considered to be completed for the purpose of taking over.
Under sub-clause 8.4 (Extension of Time for Completion) states the Contractor shall be
entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to an extension of the Time for
Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking-
Over of the Works and Sections] is or will be delayed by any of the following causes:
(a) Variation (unless an adjustment to the Time for Completion has been agreed under Sub-
Clause 13.3 [Variation Procedure]) or other substantial change in the quantity of an item of
work included in the Contract,
(b) A cause of delay giving an entitlement to extension of time under a Sub-Clause of these
Conditions,
(e) Any delay, impediment or prevention caused by or attributable to the Employer, the
Employer’s Personnel, or the Employer’s other contractors.
If the Contractor considers himself to be entitled to an extension of the Time for Completion,
the Contractor shall give notice to the Engineer in accordance with Sub-Clause 20.1
[Contractor’s Claims]. When determining each extension of time under Sub-Clause 20.1, the
Engineer shall review previous determinations and may increase, but shall not decrease, the
total extension of time.
Under sub-clause 8.7 (Delay Damages) If the Contractor fails to comply with Sub-Clause
8.2 [Time for Completion], the Contractor shall subject to notice under Sub-Clause 2.5
[Employer’s Claims] pay delay damages to the Employer for this default. These delay
damages shall be the sum stated in the Contract Data, which shall be paid for every day
which shall elapse between the relevant Time for Completion and the date stated in the
Taking-Over Certificate. However, the total amount due under this Sub-Clause shall not
exceed the maximum amount of delay damages (if any) stated in the Contract Data.
Department of CoTM 20
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
These delay damages shall be the only damages due from the Contractor for such default,
other than in the event of termination under Sub-Clause 15.2 [Termination by Employer]
prior to completion of the Works. These damages shall not relieve the Contractor from his
obligation to complete the Works, or from any other duties, obligations or responsibilities
which he may have under the Contract.
Under Clause 47 (Liquidated Damages for Delay) If the Contractor shall fail to achieve
completion of the Works within the time prescribed by Clause 43 hereof, then the Contractor
shall pay to the Employer 1/1000 of the contract price per day as liquidated damages for such
default and not as a penalty for every day or part of a day which shall elapse between the time
prescribed by Clause 43 hereof and the date of certified completion of the works. Depending
on the nature of the works, Liquidated damage higher than the minimum limit provided
herein above may be fixed in the contract. The Employer may, without prejudice to any other
method of recovery, deduct the amount of such damages from any monies in his hands, due
or which may become due to the Contractor. The payment or deduction of such damages
shall not relieve the Contractor from any other of his obligations and liabilities under the
Contract.
Under Clause 44 (Extension of Time for Completion) Should the amount of extra or
additional work of any kind or any cause of delay referred to in these Conditions, or
exceptional adverse climatic conditions, or other special circumstances of any kind
whatsoever which may occur, other than through a default of the Contractor, be such as fairly
to entitle the Contractor to an extension of time for the completion of the Works, the
Engineer, after due consultation with the Employer, determine the amount of such extension
and shall notify the Employer and the Contractor accordingly.
Department of CoTM 21
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
According to Aibinu and Jagboro (2002), identified two methods to minimize or if possible
eliminate time overrun were: acceleration of site activities, and contingency allowance.
During construction stages, the contractor should carry out his responsibility to make sure the
work progress can complete in time. If found that work progress are not equal to the estimate
schedule. The contractor may carry out with acceleration such as hire additional worker.
Besides that, the client may allow contractor standby some extra cost for unforeseen event
such as accidents.
According to Koushki, et al. (2005), revealed that the minimization of time delays and cost
overruns would require: ensure adequate and available source of finance until project
completion; ensure timely delivery of materials. During pre-construction, a client may
prepare a good cash flow within the contract period. Once the client does not enough money
to cover up construction cost, he can borrow a term loan or bridging loan from the bank to
cover the cost until the whole project completed. It will avoid project delay due to client not
enough capital. Besides that, the contractors make sure that material are order with a reliable
suppliers and can receive it on time. (Karmer, 2018).
Department of CoTM 22
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
CHAPTER THREE
3. RESEARCH METHODOLOGY
3.1. Introduction
This chapter describes the research procedures to be followed in conducting the
study. This will include the research design, research instruments, and sources of
data, sample size determination, questionnaire design, sampling technique and data
analysis. It deals about questionnaire distribution, collection of questionnaire
response and analysis of data from the answers collected. The answers were provided
by the client, consultants and contractors of construction projects in University of
Gondar. The major purpose is to point out the identified causing factors and effects of
delay in the construction the projects and then rank them.
Department of CoTM 23
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Problem Identification
Foramtion of Objective
Litrature Review
Design of questionnaire
Destribution of Questionnaire
Data Collection
Preparation of data
Analysis of Data
Conclusion/Recommendaton
Department of CoTM 24
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Researches relevant to this topic which were made available by the researcher as a secondary
source of data were used.
The other secondary source of data used is books (used as a reliable data for the preparation
of literature review), published sources (free published sources), journal (for quantitative
data), website (governmental and private) and other sources that were relevant to the topic of
this study. These sources were easily accessible. This data were helpful in conducting a
successful research. This data contributed in time and cost saving for the research that is
conducted. The data made it easier to carry out further research.
3.5. Research Sample and Population
The research will be conducted in university of Gondar building construction projects; the
target population includes owners, consultants, managers, engineers, and contractors in
building construction projects. A systematic random sample was selected to ensure a
representative sample of all targeted respondents using
There are 26 building construction projects in university of Gondar among this we select 10
building construction randomly because we don’t have enough time to distribute the
questionnaire paper. The population that are found in the seven project are listed below
1. Unity engineering plc., has 1 site engineer and 1 office engineer, 1 consultant
generally they are 3 persons
2. Gondar university lot-21 project by Yirgalem construction, has 1 project manager,
and 1 consultant and 1 client they are 3 persons
3. Gondar university lot-21 project by Zamra construction plc, has 1 office engineer 1
consultant generally 2
4. Gondar university lot-22 project by engineering service directorate, has 1 consultant 1
site engineer 1 client they are 3
Department of CoTM 25
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
5. Gondar university clinic and site work by Seyoum Assefa general contractor, has 1
site engineer 1 office totally 2
6. Gondar university lot-21project natural and computational science laboratory building
and site by Ethiopian construction design and supervision Work Corporation has 1
consultant 1 site engineer, 1 office engineer they are 3 persons
7. Ict building by E.C.D.S.W.CO, has 1 consultant 1 site engineer 2
X=3+3+2+3+2+3+2/10=1.8
n= 47/1+47(0.005)2
n= 46
Fourty six (46) Stakeholders who are found in 26 Building Constructions are our sample size.
Where,
p is total population
N is sample size
E is error margin
Department of CoTM 26
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
3, cause of delay:-This is used to collect the data on different causes of the delays happened
in that particular project.
4. Effects of Delays - Using these questions the effects of the delays on the project are
identified.
The questionnaire is based on Likert Scale of five ordinal measures from one (1) to five (5)
according to level contributing. According to John F. (2001), Likert Scale is easier to use for
respondent to express their level of opinion. For the frequency of cause’s occurrence, each
scale represents the rating as shown in
Table 3.1 : Likert scale questionnaire for causes and effect of delay
Important degree
A*N
Where,
Department of CoTM 27
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
The importance indices were calculated for all delay causes and effect were ranked
accordingly. In order to identify how project delay can be mitigated, it is important to identify
the responsible party.
Department of CoTM 28
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
CHAPTER FOUR
4. RESULT AND DISCUSSION
4.1. Introductions
This part of the study deals with the analysis and discussion of the data gathered from the
questionnaire survey that was distributed among the stake holders and project literature
review. It includes the identification of the factors causing delay in building construction
projects of Gondar University, the most responsible party for the occurrence of delay and the
effects this delay has caused in the projects. The procedure used in analyzing the results was
aimed at establishing the relative importance of the various factors that causes delay in the
building projects and their effects. The questionnaire gave each respondent an opportunity to
identify the factor that was likely to cause construction delay and their respective effects by
giving the response for each variables of delay. The percentages of respondents‟ response
were ranked for analysis purpose. On the basis of the ranking of the variables by the various
groups, it was possible to identify the most important factors that caused delay and their
effects in building construction projects of Gondar University.
Rejected 0 0 0
Department of CoTM 29
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Of the 15 questionnaires returned, 9(60%) were answered by contractors and5 (33.33%) were
responded by consultant and 1(6.67%) were responded by client.
From the above table it can be observed that from the 18 questionnaires distributed 15 were
returned.
2-4years 8 50%
total 16 100%
Regarding number of years involved in construction, 18.75 percent of respondents have less
than 2 years, 50 percent of those have between 2 to 4 years and 31.25 percent of those have
more than 4 years.
experience of respondants
7
6 6
6
5 5 5
5
4 4 4 4
4
3 3
3
2 2 2 2
2
1
1
0
1 2 3 4 5 6 7 8 9 10
Department of CoTM 30
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
1000%
800%
600%
400%
200%
0%
0 2 4 6 8 10 12
From the date gathered and as shown in the figure above most of the construction projects are
above 50% in construction.
13.33%
86.66%
yes no
From the responses we got and the above figure 87% of the stakeholders have answered that
the project is facing delay where as 13.33% have answered that the project of the construction
buildings is not facing that much of a delay.
Department of CoTM 31
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
The construction delay is universally evident reality and is counted as a common problem in
construction projects. Delays in construction projects happen because of various factors and
causes. In our research a total of 32 delays causing factors were identified and classified in to
four factor groups: client related factors, contractor related factors, consultant related factors,
and external factors.
This section supplements the result from questionnaire survey to have an overview on
the causes of delay in the construction projects of University of Gondar. For the data analysis
we have used RII to determine the major factor that causes the delay. Relative importance
index analysis allows identifying most of the important criteria based on participants' replies.
The contribution of each of the factors to overall delays was examined and the ranking of the
attributes in terms of their criticality as perceived by the respondents was done by use of
Relative Importance Index (RII) which was computed using equation. To determine the
ranking of different factors from the viewpoint of contractors and consultants, the Relative
Importance Index (RII) was computed using RII Equation;
The following are factors causing delay in the building construction project of Gondar
University.
Department of CoTM 32
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
To calculate with RII first we determined the frequency or weight of the cause listed in the
questioners this are the responses given by each respondents. Each listed causes of delay
were given different degree, where the respondents gave answer to by considering their
importance level as causes of delay.
1 2 3 4 5
1 Owner/Client related
2 Consultant related
Department of CoTM 33
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
3 Contractor related
Department of CoTM 34
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
The above table shows the frequency level given to each of the cause that is listed in the
table.
After this we proceed to calculating 5n5 + 4n4 +3n3 + 2n2, we multiply each frequency by the
degree of importance assigned to each value and calculate the total for each cause. The results
are as follows;
Department of CoTM 35
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
1 Owner/Client related
2 Consultant related
Department of CoTM 36
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
engineer
3 Contractor related
Department of CoTM 37
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
After this we calculate the RII, average RII and rank each causes based on calculating the
average RII of each causes.
1 Owner/Client related
Department of CoTM 38
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
construction
2 Consultant related
3 Contractor related
Department of CoTM 39
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
scheduling.
Department of CoTM 40
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
After calculate the RII of each sub causes and then we calculate the average RII for
each main causes the summation of RII of each sub causes is divided by the number of
sub-cause belonging to the same main factor.
Department of CoTM 41
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
As we can see from the above explanation factors related to owner and contractor have a very
high contribution for the causes of the delay on the project with RII values of 0.60571 and
0.58963 respectively. Whereas consultant related factors have medium contribution to the
Department of CoTM 42
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
cause of the delay in the construction with RII value of 0.56167 and external related factors
have low contribution to the delay with RII value of 0.51429.
RII
0.62
0.605710000000001
0.6 0.58963
0.58
0.561670000000002
0.56
0.54
0.52 0.51429
0.5
0.48
0.46
Owner/Client related fac- Contractor related factors Consultant related factors External related factors
tors
The following are factors effects of delay in the building construction project of Gondar
University.
To calculate with RII first we determined the frequency or weight of the effects listed in the
questioners this are the responses given by each respondents. Each listed effect of delay were
given different degree, where the respondents gave answer to by considering their importance
level as effect of delay.
Table 4.6: Frequency level for each effects of delay
1 2 3 4 5
Department of CoTM 43
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
project stop
5 Lawsuits 2 2 7 2 2
6 Litigation 2 2 7 1 3
7 Negotiation 1 3 3 7 1
After this we proceed to calculating 5n5 + 4n4 +3n3 + 2n2, we multiply each frequency by the
degree of importance assigned to each value and calculate the total for each effect. The
results are as follows;
5 Lawsuits 2 4 21 8 10 45
6 Litigation 2 4 21 4 15 46
7 Negotiation 1 6 9 28 5 49
After this we calculate the RII, average RII and rank each causes based on calculating the
average RII of each effects.
Department of CoTM 44
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
5 Lawsuits 45 15 75 0.6 6
6 Litigation 46 15 75 0.613 5
7 Negotiation 49 15 75 0.653 3
Department of CoTM 45
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
RII
0.733333333333334
0.8 0.693333333333334
0.7 0.626666666666667
0.613333333333334 0.653333333333334
0.613333333333334
0.600000000000001
0.6
0.5
0.4
0.3
0.2
0.1
0
From above we can see that time overrun is the major effect of delay on the projects affecting
the progress of the work. Cost overrun is also the next biggest effect chosen by the
respondents casing additional amount of money in order to complete the project. The other
factors are negotiation, dispute among the contracting parties, litigation, total abandonment of
the project and lawsuits in adverse cases.
Department of CoTM 46
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
CHAPTER FIVE
CONCLUSION AND RECOMMENDATION
This chapter includes the conclusions and recommendations that would help in solving the
occurrence of delay and its effects in the University of Gondar construction projects. The
objective of this study was to determine the delay causing factors, effects of delays and to
recommend solutions to minimize delay in the construction projects the research was
conducted. This chapter gives also direction on how delays can be minimized in construction.
5.1. Conclusion
Based on the literature reviews and the results of questionnaire responses the following
conclusions were drawn.
1. The following causes are identified as a potential delay causes in the university of
Gondar construction projects.
i. The first factor implies the highly rated delays are caused by the Owner. For instance:
Delay in progress payments by owner, inadequate client’s finance and payments for
completed works are the most influential delay causing factors in university of Gondar
construction projects.
ii. Difficulties in financing project by contractor Contractor’s slowness in site mobilization.
Rework due to errors during construction and Equipment breakdown and maintenance
problems are causes of delay that occur due to contractor.
Factors of medium contribution
i. Changes in government regulations and laws and Effects of subsurface conditions are
some causes of delay due to external factor.
2. The highly rated effect of delay is time overrun. It affects the progress of work and results
extension of time. Cost overrun additional amount of money required in order to compete
the project, Negotiation Dispute among the contracting parties and, abandonment are
effects that encountered of the delay.
Department of CoTM 47
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
5.2. Recommendation
The purpose of the following recommendation is not to deeply address areas that need
improvement in the University of Gondar construction projects. The analysis of the
questionnaires has suggested the client, the contractors and the consultants have contributed
their own share in causing delay to the project. Hence the following recommendations are
focused towards improvements to be made on these causes.
The client shall secure the removal of obstructions that prevents the building before handing
over projects the client should finish on time. So when construction begins it will not bring
any challenges. And also the client should follow up the timely submission of design review
and approval by the engineer.
As the contractor is also one of the parties involved in the construction process they also have
a stake on the successful completion of the project. So, they are directly involved in the
construction process completing the project on time also means the success of their work. So
for the project to be completed on time the contractor should work with the other stake
holders in cooperation to avoid delay.
The consultant is also one of the stake holders involved in the construction process .It is also
responsible for the timely completion of the project so as the client won’t incur additional
cost. So the consultant should submit and review designs also approve this design and
provide proper inspections on time so the works will be executed according to the scheduled
time. They should have a proper and good communication with the client and the contractor
in order to achieve their objectives properly.
Department of CoTM 48
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Reference
Abd El-Razek, M. B. (2008). Causes of delays in building construction projects in
Egypt. Journal of Construction Engineering and Management , Vol. 134 No. 11, pp.
831-841.
Koushki, P. A.-R. (2005). Delays and cost increases in the construction of private
residential projects in Kuwait. In P. A.-R. Koushki, Construction management and
economics (pp. 23(3), 285-294.). Kuwait.
Department of CoTM 50
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Appendix
Questionnaire
University of Gondar
Institute of Technology
School of architecture and construction technology and management
Department of construction technology and management
Questionnaire
Dear madam/sir___________________________________________
We are fifth year students at University of Gondar, Institute of Technology. And we are
currently undertaking our Bachelor of Science degree in Construction Technology and
Management. And as graduating students we are conducting out thesis research on assessing
the causes and effects of delay in the construction buildings of University of Gondar. The
main objective of our research is to identify the major causes and effects of delay in the
construction projects that are conducted in the University of Gondar.
The research will be conducted by five group members with the guidance of our advisor Mr.
Samson Worku.
And as your firm is one of the stakeholders participating in this construction projects we
kindly ask for you cooperation in filling out questionnaires and answering our pending
questions. And we firmly assure you that any information you provide us is strictly
confidential and used only for our research or academic purposes. Please take a good look at
our questionnaires and fill out all the questions. Thank you very much for your time and
cooperation.
0912-21-05-67
0936-23-47-55
Department of CoTM 51
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Department of CoTM 52
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
Department of CoTM 53
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
1) In the table below there are some factors that cause delay in the construction projects.
Please define the degree of importance of this causes in resulting delay in construction
projects.
2 Consultant related
Department of CoTM 54
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
3 Contractor related
Department of CoTM 55
Assessment of the Causes and Effects of Delay in the Construction Projects of University of Gondar 2013 E.C.
2) In the table below are some of the effects of delay in the construction projects. Please
define the degree of importance of these effects of delay in construction projects.
1 2 3 4 5
project stop
5 Lawsuits
6 Litigation
7 Negotiation
Department of CoTM 56