ARTICLE 7 - GYPSUM BOARD WORK

1.0. GENERAL

1.1. General Provisions

 a new job can be done after completion of all installation work to be installed above the ceiling has
been installed and tested (test).

 All work ceilings and partitions should be flat, neat and not bumpy.

 All materials posted must be new, good, no defects, wet, and not curved.

The color and texture of the material must be the same.

 peil height ceiling and partition must fit the plan drawings.

1.2. scope of Work

a. This section covers the terms / conditions (payment, delivery, storage, installation) for labor,
materials, and equipment.

b. Include the provision of ceiling and partition material: compound, tape, ceiling hanger frame,
mounting frame hanging and ceiling materials in places according to the plan drawings, and material
order partition. The scope of this work and the binding force for the entire job ceilings and partitions.
c. Relevant part:

 Paintwork

 Work Plastering

 Work Ceramics

 Work Marble / Granite

 Work Curtain Wall

 Carpentry Work and Connection

 Mechanical and Electrical Works

1.3. References

a. All work must refer to standards: E1477 and E 1264 Hymidity - plus Humiguard resistant.

b. Quality Assurance:

Qualifications manufacturing: product used here should be produced by companies that are well known
and have experience of successful and accepted by the Consultant Construction Management (CM) and
the client.

c. Worker Qualifications:

 At least there should be one person who fully understood against this section during the
implementation, understanding of the needs required, materials, and methods needed for
implementation.

 trained workforce available to be enough and have the required skills.

 In the acceptance or rejection of the workers, the Court, the client, and does not permit labor Planner
or less without his skills.
1.4. Delivery (submittals)

The contractor shall send to the client, MK, and Planner to the following for review prior to start of
work:

a. Shop drawings, which show:

1 The appointment of lay-out

2 Details insert and hanger spacing, and Fastening

3 Methods space / settings for all the main and cross runners.

4 The details of changes in the level of

5. Details on the installation of the ceiling fixtures (fixture) ceiling.

6 Positions for manhole (manhole inspection)

7 images that show coordination ME coordination and / or plumbing fittings and fixtures (lights,
sprinklers, etc.) if any, and the ceiling design and construction.

b. Examples of materials that show the actual size and color pattern.

c. Mock-ups representing ceiling mounting system.

d. Copy the complete technical specifications of the plant including detailed instructions for installation
materials.

1.5. Storage and Care Products


a. Materials should be sent in sealed protective containers from the factory or the manufacturer's name,
color, size and type.

b. Materials must be held / maintained with care to avoid damage in accordance with manufacturer's
instructions.

c. Material should be stored in a room, closed, stacked flat, up off the floor and protected from water,
all of which fit the manufacturer's instructions.

2.0. MATERIALS

2.1. Materials and Components

a. Materials used in this section shall be consistent with the rules and standards referred to herein, and /
or equivalent regulations and international standards, were approved by the client, MK, and Planner.

b. Gypsum panels to the ceiling should have a thickness of 12 mm plasterboard with recessed sides, in
accordance with the approval of the Court, the client, and Planner.

c. Screw fastening gypsum plasterboard ceiling system in the form of average relationship (flush) to
produce a smooth continuous surface that is ideal for all forms of decoration.

d. Aluminum frame must consist of a top cross rails, furring channels, and locking clip, in accordance
with the recommendations of the manufacturer.

e. Screws for fixing plasterboard to be anti-rust.


f. Ceiling types and patterns shall be in accordance with the approval of the Court, the client, and
Planner.

2.2. Gypsum Board Panel

Gypsum Ceiling Board for:

a. Finish: spray paint

b. Size: as picture plan

c. Thickness: 12 mm

d. Production: Jaya Board - Product: Boral or equivalent

e. Fire Rating: 60 minutes

f. Frame: Metal Furing to factory defaults

g. Extra Stock: 5%

h. System installation: Semi concealed grid

3.0. INSTALLATION

3.1. examination

a. Check areas scheduled to be installed this unit ceiling hanger to determine unevenness, inequality and
humid which may affect the quality and the implementation and execution of work.

b. Put a gap and estimate the possibility to access and difficult location before installation.
c. Do not precede job installing ceiling-mechanical and electrical works and it is necessary for a thorough
examination has been carried out to readiness and other works have been completed entirely.

d. The contractor must install gypsum plasterboard panels and accessories-accessories in accordance
with manufacturer's instructions, shop drawings, and this specification.

e. If there is a recommendation from the manufacturer has a different meaning of the specification here,
must wear a recommendation from the factory, except that the specification here should be applied as
directed by the Court and the client.

3.2. Installation of steel framing for suspended and furred ceiling

a. Buffer ceiling must be placed in accordance with reflected ceiling plans and details or in accordance
with the approved shop drawings, and will be on the line and level with other instruments or other
equipment that has been approved. Use the "turnbuckles" for leveling.

b. Hang the hanger from the structural ceiling of the building and do the following:

1 Install the hanger with the flat and free from contact with insulation or other objects within ceiling
plenum that are not a structural support or ceiling suspension system. Renggangkanlah hanger only
when necessary to avoid obstacles and compensate for the horizontal force by bracing, countersplaying,
or other effective means.

2 Fasten flat, elbows, channel, and rod hangers to structure, including connecting parts of the frame,
with gluing and tuck, eyescrews, or fasteners and other equipment that can strengthen and enough
structural including hanger type used, and the way that will not cause damage or fall due to age,
corrosion / rust, or high temperatures.

3 Do not connect or iron frame hanging on the ducting, pipes, or conduit.


c. Fit a metal frame components with size and the distance indicated but not less than that required of a
reference standard iron truss installation.

Wire hanger 1: 4 mm (8 gage) diameter: 1.25 Moc

Carrying 2 channel (Main Runners): 4 cm, 1.12 Moc

3 Rigid furring channel (furring Members): 60 cm Moc

d. Wire ties or furring ellipse to the main runners and to other structural support member in accordance
with that indicated by the manufacturer's recommendations.

3.3. The application and finishing gypsum board

General

a. Put a blanket of sound attenuator which was shown before the installation of acoustic ceiling panels
unless blankets are ready to be installed after the acoustic panels have been installed on one side.

b. Install ceiling panels, gypsum board with a transverse order to minimize the number of connections in
the midst of the tip area on each ceiling. Wear buffer at end connections of adjacent panels not less
than one part of the framework.

c. Install gypsum board panels with face side out. Do not install panels that are not perfect, damaged, or
damp. Tie panels together to straighten the edges and ends with not more than estrangement 1.5 mm
between the two panels. Do not be pushed into place.

d. Attach gypsum panels to steel studs so that the edge or end of each alignment panel attached to the
edge of the opening (unsupported) from flangers studs first.

e. Gypsum plasterboard will be closed along with the slotted connection type paper width of 50 mm.
f. The average connection will be as follows:

Basebond 60 will be mixed according to the manufacturer's instructions, then use a steel trowel, which
is used on all connections, so it will be a "savior" front panel.

g. Use the same principle to cover all the screws.

Immediately after all this has been set by means of an iron trowel, cut advantages Basebond 60.

By using the "stopping compound" mixed according the manufacturer's instructions, and screw
connections average will be smooth.

The entire surface of the ceiling must be flat, smooth the satisfaction of the Court, Tasks and Planner
giver.

3.4. installation

Gypsumboard Replace damaged during execution with no additional cost to a client.

3.5. cleaning

Once all work is complete, clean the ceiling panels of the former palm, dirt, grease, and other foreign
objects. Now it has been prepared in accordance with the desired difinish (specify).