work progress of gangs between VKT-KAPT and kmlp-vrjn section on 08/11/2022

slno gang no actual strength location of work done type of work done
1 5 1+18+2A 98/7-97/33 slack packing
2 6 1+20men km109/3-108/39 kapt all lines deweeding
lc38 km99/2-4 w/l indicators erected perpendicular
ptnos 31B,32B kapt lrj done
3 Blacksmith-movement- ptnos 31B,32B/kapt- lrj done with Gno6
4 USFD team not done any work still their equipment is to arrive kapt.
5 sto/pway/krcl-Tvrao movement- worked with Gno6 and lc38 w/l indicators erected perpendicular
6 vehicle movement- vkt to kapt, kapt to lc38 and lc38 to kapt, kapt to vkt
7 lcgatemen on duty on 08/11/2022
lc38-p.polamraju day, cms raju night
lc39-a.balakrishna day, g.praveen babu night
Lc40-g.roop sagar day, V.kondalarao night
erpendicular

erpendicular