Professional Documents
Culture Documents
Otc 24681 Ms
Otc 24681 Ms
This paper was prepared for presentation at the Offshore Technology Conference Asia held in Kuala Lumpur, Malaysia, 25–28 March 2014.
This paper was selected for presentation by an OTC program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been
reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material does not necessarily reflect any position of the Offshore Technology Conference, its
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Offshore Technology Conference is prohibited. Permission to
reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of OTC copyright.
Abstract
During the installation of large diameter steel piles, the overestimate of pile initial penetration and pile free fall will increase
the risk of offshore construction. At present, there is no mature method of calculating the soil dynamic resistance. Comparing
the pile design and pile driving record, we found that pile end resistance is critical to esimate the pile intial pentration. This
paper also studies the influence factors for pile free fall length during the initial penetration condition and driving.
LW3-1 CEP jacket foundation piles are one of the largest in the world with 4 – 108” dia. vertical skirt piles at each jacket
corner. Each pile is 158 m in length with a 135m pile target penetration. The maximum dry weight of each pile is 755 MT.
Complicated soil conditions have imposed difficulty to estimate the pile self penetration and pile free falling phenomenon.
Combining with fieldmonitoring data, the new evaluation methods for soil resistance are present. Such approach can apply for
this region in South China Sea.
Introduction
Recently more and larger jackets have been installed in the Asia Pacific area, such as South China Sea, Gulf of Thailand, West
Australia, and so on. With the increasing emphasis on the marine environment, the scale of platform is also growing. As the
fixed platform foundation, the design requirement for jacket is more rigorous. The Liwan (LW) 3-1 central processing
platform (CEP) platform is the largest offshore platform in Asia with the jacket load out weight of 32,000 MT and the topside
operating weight of 44,000 MT. LW3-1 CEP jacket is located at 189.5 m water depth, which is the deepest for a topside float
over installation in offshore history. The location of LW3-1 platform is shown in Figure 1.
LW3-1 CEP jacket foundation pile is the largest one in the world with 4×ø108"dia. vertical skirt piles at each jacket corner leg.
Each pile is at 158 m in length with 135 m design penetration depth and the dry weight of 755 MT. In the pile design, major
activities are performed as follows:1) Pile axial capacity check; 2) Pile lifting strength check; 3) Stick-up stability calculation;
4) Pile drivability; 5) Pile fatigue analyses; 6)Ppile shoe buckling and grout connection check. The design of jacket pile
foundation becomes more and more difficulty due to complicated soil strata, large pile diameter, very long and heavy piles,
driving under deep water, etc.
It is also very challenging to perform the large size pile installation analysis especially due to complicated soil strata (rock and
pieces of stones are discovered in geotechnical boreholes) for this project. This paper mainly focuses on the comparison
between the analytical predictions and the field measurement, the self-weight initial penetration and pile free fall length are
discussed. In addition, the correction factor for the static soil resistance based on the field measurement is also addressed. , The
analysis results indicate that the new method improving calculation accuracy for self penetration depth and drivability analysis.
This method can be used for future pile design in this region.
2 OTC-24681-MS
Design Criteria
Soil characterization
Site specific soil investigations have been extensively carried out. The soil investigation consists of boreholes where samples
are taken, and cone penetration tests (CPT). Each borehole location and depth is shown in Figure 2.
DH2 location (25m):
BH2 location (170m): E: 280 617.76m
E: 280 621.38m TN N:2 240 392.12m
N:2 240 386.72m
B4
DH5 location (25m):
E: 280 696.96m
DH4 location (25m): Center of LW3-1CEPOA-2 Platform : N:2 240 311.86m
E: 280 554.00m E: 280 625.48m
N:2 240 322.04m N:2 240 320.57m
m
driving, the lower bound and upper bound value of the mobilized soil skin friction is 25% and 40% of the static soil skin
friction in clays, while in sands the mobilized skin friction is 100% of the static skin friction, and the mobilized unit end
bearing is 100% of the static unit end bearing in both sands and clays and only acts at the annular area of the pile tip. For the
driving restart after delays, if the pile plugs at the tip, both the mobilized skin friction and unit end bearing are 100% of the
static soil resistance, and the end bearing acts at the entire area of the pile tip.
Pieces of stones are discovered from the geotechnical boreholes, the presence of stones or thin rock layers are expected to be
encountered when driving the piles at the platform location. The driving resistance of the rock layers was assessed from CPT
results, as listed in Table 3.
Table 3 – The Calculation of SRD the Rock Layers
Figure 6 – The distance for pile free fall corresponding unit end bearing distribution
Table 4 – The Field Records for Self-penetration and Free Fall Length
bolw maximu
pile Borehole self penetation free fall range zone free fall distance count/last total m energy installation
NO. NO. (m) (m) (m) 1m bolws (KJ) date
A4-3 BH1 12 13.5~62 48 358 4570 1042 2012.9.3
B4-3 BH4 12.5 13.5~33,45~57,58~78 52 231 3643 1139 2012.9.3
A1-3 BH3 11.75 13.5~36,38~76,79~84 60 447 3548 785 2012.9.6
B1-3 BH2 12.0 13.5~72 59 394 4837 980 2012.9.8
B1-4 BH2 12.0 13~72 59 253 4003 987 2012.9.9
B1-2 BH2 12.0 12.5~71.5 59 224 3965 1006 2012.9.10
A1-2 BH3 12.0 15~27,39~60,62~74 41 211 4029 1027 2012.9.12
13.5~26,40~60.5,
A1-1 BH3 12.0 63.5~75 44.5 250 3752 993 2012.9.12
A1-4 BH3 12.0 13~36,40~60,63~68 48 191 3138 1040 2012.9.12
B1-1 BH2 12.0 13~72 59 198 3737 1040 2012.9.13
A4-4 BH1 12.0 13~36,40~60,69~76 50 191 3688 1040 2012.9.21
A4-2 BH1 12.0 14~34.5,41~60 39.5 207 4200 1037 2012.9.21
A4-1 BH1 26.5 41~60 19 313 4397 925 2012.9.21
B4-4 BH4 12.0 13.5~39.5,47.5~56 34.5 213 3288 1012 2012.9.21
B4-2 BH4 12.0 13.5~34.5,41.5~71 50 227 2900 1029 2012.9.21
B4-1 BH4 12.0 13~73 60 228 4888 1036 2012.9.22
6 OTC-24681-MS
Based on CPT results in Figure 7, soil resistancesin layer from 10.9m to 13.2m come from Medium dense to dense silt fine
7 OTC-24681-MS
sand. The end bearing capacity is underestimated during the pile detail design. Engineer can use cone resistance qc for unit
end bearing to calculation self penetration depth, the result is more in line with the actual situation.
Blows(per 0.5m)
0 50 100 150
0
5
10
15
20
25 B1-2 site record
30
35 unit skin friction 10%
40
45 unit skin friction 30%
50
Penetration(m)
55
60
1) Pile self penetration can be conservatively calculated using end bearing of CPT result
2) When the very dense sand or well cemented sandstone layer is present in shallow layers, the calculation of self
penetration depth shall be based on gross end bearing area.
3) The pile free fall should be carefully studied and estimated in order to reduce the installation risk.
4) It is observed that the effect of thin rock layers for pile driving is small.
5) For long pile with heavy and large diameter, the pile will usually stop in the sand layer when the end higher bearing
capacity is high when the gross end bearing area whether it is under self penetration or the end of free fall.
Acknowledgements
The authors thank China National Offshore Oil Corp. (CNOOC), CNOOC Ltd Shenzhen, China Offshore Oil Engineering Co.,
Ltd (COOEC) for their permission to publish this paper. Special thanks to Dr. GAO Jian who in the novellant engineering
service CO.LTD for technical guidance. The authors also thank all the team members for their hard work and cooperation to
make the project become a successful reality.
Nomenclature
API American Petroleum Institute
CNOOC China National Offshore Oil Corporation
COOEC China Offshore Oil Engineering Co., Ltd.
CEP Central Processing Platform
CPT Cone Penetration Test
References
[1] American Petroleum Institute, Recommended Practice for Planning, Designing, and Constructing Fixed Offshore Platforms – Working
Stress Design Supplement3 (21st edition), December 2007.
[2] Alm, T.& Hamre, L., 1998, “Soil Model for Driveability Predictions, ” Offshore Technology Conference, OTC-8835.
9 OTC-24681-MS
[3] Jardine, R.J. and Chow, F. C., 1996 “New design methods for offshore piles, Report to Marine technology directorate,” MTD,
Publication No.96/103.
[4] Offshore Technology Report for A Study Of Pile Fatigue During Driving and In-Service and of Pile Tip Integrity, Health & Safety
Executive, 2001.
[5] Smith, E A L, 1960, “Pile Driving Analysis by the Wave Equation,” Journal of the Soil Mechanics & Foundations Division, Vol. 80, No.
4, pp 35−61.
[6] Shang, De-zhong, 2007, “Methods to Calculate Soil Fatigue in Pile Driving,” China Harbour Engineering, Vol. 147, No. 1, pp 20−22.
[7] Robert S. Stevens, 1982, “Evaluating Pile Drivability for Hard Clay, Very Dense Sand, and Rock,” Offshore Technology Conference,
OTC-4205.
[8] Xu, Qing-xia, Huang, Yuan-xiong, 2000, “Analysis of Pile-driven and Soil's Reconsolidation by Finite Element Method,” Building